Citation : 2010 Latest Caselaw 3975 Del
Judgement Date : 30 August, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.338/2010 & CM No.8828/2010
NATIONAL HIGHWAYS
AUTHORITY OF INDIA .....Appellant through
Mr. Parag P. Tripathi, ASG
with Ms. Aparajita Swarup &
Mr. Anuj Bhandari, Advs.
versus
UNITECH-NCC JOINT VENTURE .....Respondent through
Ms.Priya Kumar, Adv.
for the Respondent
% Date of Hearing : July 23, 2010
Date of Decision : August 30, 2010
CORAM:
* HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MS. JUSTICE MUKTA GUPTA
1. Whether reporters of local papers may be
allowed to see the Judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the Judgment should be reported
in the Digest? Yes
VIKRAMAJIT SEN, J.
1. This Appeal impeaches the decision of the learned Single
Judge by which the Objections of the Appellants under Section
34 of the Arbitration & Conciliation Act, 1996 („A&C Act‟ for
short) came to be dismissed. We think it relevant to record, at
the very threshold, that the Appellants have concurrently and
consecutively lost at all the four tiers that have preceded this
Appeal.
2. The Appellants firstly lost before the „Engineers‟ who they
have themselves selected pursuant to a Global Tender. The
„Engineers‟ are an independent entity, namely, SHELADIA-
RITES [JV], Vishakhapatnam. SHELADIA ASSOCIATES is
incorporated in United States, whereas the other Joint Venturer
is RITES Limited, a well-known and reputed Indian engineering
corporation. It is these Consultant/Engineers who, by virtue of
Clause 5.2.1 of the Contract, are empowered to resolve
ambiguities, omissions, errors, faults and other defects in the
Drawings or any other Contract Document as perceived by the
Contractor (Respondents before us). The Contractor had
approached the said „Engineers‟ to decide the question of
whether the Contractors/Respondents were entitled to claim
escalation on the Contract Work. The Appellants had adopted
the view that they were not liable to pay escalation and price
variation on the original quantity of work contracted as per Bill
of Quantity (BoQ) items but only on deviation in work provided
for in Clause 60.1(d). This stand is taken even though
indubitably the period within which the Contract was to be
completed was spread over thirty-two months and was for
a value of ` 1,46,00,000,00/-. The Engineers had, on an
interpretation of the Contract, decided that the
Contractors/Respondents were entitled to escalation even on
BoQ items. The Respondents had, in accordance with the
re-worked formula for calculating the escalation, claimed a
sum of ` 1,55,87,88,905/-; but the Engineers had quantified
and found due and payable by the Appellants to the
Respondents only on the sum of ` 17,27,18,420/-.
3. The second tier is the Dispute Resolution Board which,
poignantly, had been approached not by the Appellants but by
the Respondents. This was for the reason that, predicated on the
original formula contained in the Agreement, the Respondents
had laid a claim for approximately ` 1,55,00,00,000/-. In other
words, the Appellants were even till this stage satisfied with
the correctness of the computation whereby the escalation
was restricted to ` 17,27,18,420/- by the „Engineers‟.
4. The third stage of adjudication was before the Arbitral
Tribunal which was approached by the Respondents once again
underscoring the position that the Appellants had no grievance
or opposition to the grant of ` 17,27,18,420/- + ` 57,04,914/-
The Arbitral Tribunal, by means of a detailed Award, upheld the
decision of the previous two entities and allowed interest at the
rate of 10 per cent per annum.
5. Undaunted by these findings, the Appellants have invoked
Section 34 of the A&C Act by filing Objections before the
learned Single Judge. Once again, its contentions have been
roundly and soundly rejected. The learned Single Judge found
the attitude of the Appellants obdurate and stubborn, contrary
to the stand taken by the Appellants themselves for the major
part of the Contract, and keeping the frivolity of the Objections
in perspective, ordered that the actual costs, as quantified on
Affidavits be paid by the Appellants to the Respondents,
together with interest at the rate of nine per cent per annum in
case the costs were not paid within 45 days.
6. We have already highlighted the fact that it was
the Respondents who had approached the Dispute
Resolution Board, assailing the quantification of escalation of
` 17,00,00,000/- as calculated by the „Engineers‟. We have
underscored the obvious inference that the Appellants were
satisfied with this calculation. What is of added relevance is that
payments were made without demur by the Appellants until the
27th Running Bill. The Respondents had billed under Clause 60.1
which included escalation on the Running Contract Bills. These
Bills did not pertain to any „variation‟ or „extra work‟ ordered by
the Appellants. The conduct of parties is indicative of their
understanding of the contract which governed their dealings.
According to Ms. Priya Kumar, learned counsel for the
Respondents, the sharp turnaround was the consequence of the
advisory dated 20.5.2004 issued by National Highways
Authority of India that escalation/price variation "is not
available in those agreements where it is not found in the
express language". What transpires is that after making the
payments of escalation upto the 27th Running Bill, the
somersault of the Appellants led to their making recoveries of
amounts already paid from the subsequent Bills presented by
the Respondents.
7. It is obvious that the interpretation of the Contract forms
the fulcrum of the dispute between the two adversaries before
us. As already mentioned, the power to interpret the Contract
was reposed in the „Engineers‟ as per Clause 5.2.1. of the
Contract. The Engineers, on a thorougher and lucid examination
of the contract, have concluded that escalation was
contractually payable on the Contract itself as well as on any
variation thereto. Even under the regime of the repealed
Arbitration Act, 1940, their Lordships have opined in the
celebrated Judgment of Sudarsan Trading Company -vs-
Government of Kerala, (1989) 2 SCC 38 that -"Once there is no
dispute as to the contract, what is the interpretation of that
contract, is a matter for the arbitrator on which the court
cannot substitute its decision". The continuity of this opinion is
manifest from a reading of H.P. State Electricity Board -vs- R.J.
Shah, (1999) 4 SCC 214 inasmuch the Court reiterated the
position that - "when the arbitrator is required to construe a
contract then merely because another view may be possible the
court would not have justified in construing the contract in a
different manner and then to set aside the award by observing
that the arbitrator has acceded the jurisdiction in making the
award". Numaligarh Refinery Limited -vs- Daelim Industrial
Company Limited, (2007) 8 SCC 466 records that with regard to
the interpretation of a contract, the decision of the Arbitrator
should not be interfered with by the Court. After adverting to
Tarapore & Company -vs- Cochin Shipyard Limited, (1984) 2
SCC 680, their Lordships recorded that there can be no quarrel
with the proposition that - "if a question of law is specifically
referred to by the parties to the arbitrator for decision, award of
the arbitrator would be binding on the parties and court will
have no jurisdiction to interfere with the award even on ground
of error of law apparent on the face of award". Very recently, in
McDermott International Inc. -vs- Burn Standard Co. Ltd.,
(2006) 11 SCC 181 after perusal of a plethora of precedents,
their Lordships have enunciated this aspect of the law in the
following manner:-
112. It is trite that the terms of the contract can be express or implied. The conduct of the parties would also be a relevant factor in the matter of construction of a contract. The construction of the contract
agreement is within the jurisdiction of the arbitrators having regard to the wide nature, scope and ambit of the arbitration agreement and they cannot be said to have misdirected themselves in passing the award by taking into consideration the conduct of the parties. It is also trite that correspondences exchanged by the parties are required to be taken into consideration for the purpose of construction of a contract. Interpretation of a contract is a matter for the arbitrator to determine, even if it gives rise to determination of a question of law. (See Pure Helium India (P) Ltd. v. ONGC, AIR 2003 SC 4519 and D.D. Sharma v. Union of Indi, (2004) 5 SCC 325.)
113. Once, thus, it is held that the arbitrator had the jurisdiction, no further question shall be raised and the court will not exercise its jurisdiction unless it is found that there exists any bar on the face of the award.
114. The above principles have been reiterated in Chairman and MD, NTPC Ltd. v. Reshmi Constructions, Builders & Contractors, AIR 2004 SC 1330, Union of India v. Banwari Lal & Sons (P) Ltd, AIR 2004 SC 1983, Continental Construction Ltd. v. State of U.P., (2003) 8 SCC 4 and State of U.P. v. Allied Constructions, (2003) 7 SCC 396.
8. In the case before us, the Arbitral Tribunal has
unequivocally upheld the interpretation of the contract
expressed by the „Engineers‟ who have been contractually
empowered by the parties to impart meaning to the sundry
clauses of the subject Agreement.
9. It would be perilous and constitutionally unjustifiable to
ignore and lose sight of Parliament‟s endeavour to curtail curial
interference in arbitration awards. Section 34 of A&C Act does
not contemplate the existence of errors on the face of the
Award, which the Supreme Court has clarified to be beyond
judicial interference. The learned Single Judge has, in the
impugned Order, rendered a threadbare consideration of the
terms of the Contract and his conscience has not been provoked
in the least bit. The learned Single Judge has failed to find any
infraction of the public policy of India. However much we
stretch our thinking, we cannot conceive of a construction of the
contract contrary to that carried out by the Competent Authority
and more particularly by the learned Single Judge. Interference
by us will be justified if the views of the learned Single Judge
can be perceived as a perversity.
10. The learned Additional Solicitor General has reiterated the
argument made before the learned Single Judge, which,
succinctly stated, is that words cannot be added or taken away
from a contract and the only permissible interpretation is a
facial and literal interpretation of the terms delineated in the
Contract itself. Our attention has been drawn towards State
Bank of India -vs- Mula Sahakari Sakhar Karkhana Ltd., (2006)
6 SCC 293 where it has been observed that documents "must
primarily be construed on the basis of the terms and conditions
contained therein. While construing a document the court shall
not supply any words which the author thereof did not use".
That very Judgment, however, notices that surrounding or
attending circumstances can be taken into consideration if
ambiguity is encountered. In Provash Chandra Dalui -vs-
Biswanath Banerjee, 1989 Supp. (1) SCC 487, their Lordships
have clarified that if the contract is to be construed with
reference to its objects and the whole of its terms and that "it is
legitimate in order to ascertain the true meaning of the words
used and if that be doubtful it is legitimate to have regard to the
circumstances surrounding their creation and the subject
matter to which it was designed and intended they should
apply". For the sake of brevity, we shall refrain from discussing
each precedents cited by learned counsel for the parties as it
would only be avoidable prolixity. We must constantly be
mindful of the fact that these dialectics are relevant before the
Arbitral Tribunal.
11. The following observations from the impugned Award
rendered by the Arbitral Tribunal, which has been affirmed
without reservation by the learned Single Judge, are worthy of
reproduction:-
1.10 Taking into account all the above arguments of the parties, we are of the considered view that on a conjoint reading of Bidding Date Sub-clause 14.4, ITB Sub-clauses 14.4 and 31.4, Sub-clauses 70.1, 70.2, 70.6 and 70.7 and 70.8, 60.1 and 60.2 of COPA, the conclusion is inevitable that all these clauses are consistent and provide that price adjustment is payable on the entire work comprising all BOQ items including variations and daywork except where such variations and daywork are otherwise subject to adjustment (that are valued at current prices). All these sub-clauses corroborate one another and are in complete harmony except for sub-clause 70.3 which has ambiguity and errors as explained in para 1.5.4.
1.12.3.5 We have considered the contentions of both the parties. In our view, the National Highways Authority of India (NHAI), the author of the Contract document, was conscious of the fact that tender documents are not perfect and mistakes may have occurred. Words used in clause 5.2.1 are "ambiguities", "omissions", "errors" "faults" and "other defects" in the Drawings or other Contract Documents. Under this clause the Engineer was given enabling power. The Engineer can resolve the ambiguity or correct the error or supply the omission to remove contradictions and inconsistencies. By doing this, the Engineer was not re- writing the contract but only exercising a contractual power.
According to Sub-clause 67.3 of the Contract "Any dispute in respect of which the Recommendation(s), if any, of the Board has not become final and binding
pursuant to Sub-clause 67.1 shall be finally settled by arbitration as set forth below. The arbitral tribunal shall have full power to open-up, review and revise any decision, opinion, instruction, determination, certificate or valuation of the Engineer and any Recommendation
(s) of the Board related to the dispute." The Arbitral Tribunal has the contractual power to resolve the ambiguity or correct the error or supply the omission in the contract document emanating from Sub-clauses 67.3 and 5.2.1 of the Contract and Section 28(3) of the Arbitration and Conciliation Act, 1996. Drafting error can be corrected and defect cured under this Clause to make the contract to conform to the true intention of the parties. Removing the drafting error is not to re-write the contract. The Arbitral Tribunal is not re-writing but only interpreting the contract.
...
"1.13.3 We find that the Engineer has throughout the execution of the Work firmly maintained that price escalation is payable on all BOQ items.
12. We need to constantly remind ourselves that we are not
experts in every field. In the present case, the Arbitral Tribunal
comprised of a former Director and Chief Engineer, appointed
by the Respondents, a former Engineer-in-Chief, PWD appointed
by the Claimant; both of them appointed a Chief Engineer
MORT&H as the Presiding Arbitrator. Before encapsulating the
operative part of the Award, these expert Engineers have
unanimously observed as follows:-
1.16.2 It is our experience that as per sound engineering practice based on FIDIC guidelines adopted in such civil construction contracts, price adjustment clause is included in the contracts to take care of the increase/decrease in the price of materials, bitumen, cement, labour, machinery and P.O.L.(Petrol/Diesel, Oil and Lubricants) during the period of execution. The Contractors are required to quote their rates prevailing at the time of preparation of their Bid. The price adjustment clause is applicable to all items of the work. The reason is that in long term contracts the increase in the price and cost of inputs into the BOQ items during the period of execution is so uncertain and the Contractors are not expected to bear such uncertain extra burden.
This factor of usage of the trade has also to be taken into account by the Arbitral Tribunal in making their decision as per Section 28(3) of the Arbitration and Conciliation Act."
13. Having articulated this appreciation of law, it would be
illogical for us to enter into a detailed dialectic upholding the
views of the Arbitral Tribunal with regard to the interpretation
of the contract vis-à-vis the claim for escalation on the BoQ
contained in the contract. We uphold the detailed reasoning of
the learned Single Judge in the impugned Order which, in turn,
had appreciated the conclusion of the Arbitral Tribunal. No
perversity has been detected by the learned Single Judge as also
by us. We affirm that the contract envisages payment of
escalation on BoQ spelt out in the contract as well as on
deviations and extra work subsequently placed by the
Appellants on the Respondents. For these reasons, the Appeal is
devoid of merit and is dismissed along with pending application
with additional costs of ` 30,000/-.
( VIKRAMAJIT SEN ) JUDGE
( MUKTA GUPTA ) JUDGE August 30, 2010 tp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!