Citation : 2010 Latest Caselaw 3864 Del
Judgement Date : 19 August, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision: 19th August, 2010
+ LPA 589/2010
SANJAY PLASTIC INDUSTRIES ..... Appellant
Through : Mr. Sunil Satyarthi and
Mr. Raman Gandhi, Advs.
versus
DSIDC & ANR ..... Respondents
Through : Ms. Anusuya Salwan with Ms. Renuka Arora, Advs. for DSIDC Mr. Tariq Sami, proxy Adv. for Mr. A.
Javed for R-2
AND
+ LPA 590/2010
DUA POLYMERS PVT LTD ..... Appellant
Through : Mr. Sunil Satyarthi and
Mr. Raman Gandhi, Advs.
versus
DSIDC & ANR ..... Respondents
Through : Ms. Anusuya Salwan with
Ms. Renuka Arora, Advs. for DSIDC
Mr. Tariq Sami, proxy Adv. for Mr. A.
Javed for R-2
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE MANMOHAN
1. Whether reporters of the local papers be allowed to see the judgment? Yes
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
DIPAK MISRA, CJ
Regard being had to the commonality of the controversy involved in
both the appeals, they were heard analogously and are being disposed of by
a common order.
2. The resume' of facts which are necessary to be stated are that the
appellants-writ petitioners (hereinafter referred to as „the appellants‟)
invoked the extraordinary jurisdiction of this Court under Article 226 of the
Constitution of India for issuance of mandamus to the respondent-Delhi
State Industrial Development Corporation (for short „DSIDC‟) as well as the
Commissioner of Industries to give possession of industrial plots measuring
100 sq. metres allotted in favour of the appellants by the first respondent. A
further prayer was also made for issuance of a writ of certiorari for
cancellation of the order dated 10th July, 2002.
3. The factual exposition as discernible is that both the appellants had
applied for the plot of the industrial land measuring 400 sq. metres in
December 1996 under the re-allocation scheme and had deposited the
earnest money. They were extended the benefit of allotment and in
pursuance of the same, a letter of demand was sent by the DSIDC requiring
them to deposit 30% of the revised estimated cost of the plot @ Rs.4,200/-
per sq. metre after adjustment of the earnest money that had already been
deposited. The first installment was required to be paid by 31 st October,
2000. The appellant, M/s Dua Polymers (Pvt.) Limited, did not comply with
the same on the ground that the earnest money had already been deposited
with DSIDC. Similar letter was issued by the appellant, namely, M/s Sanjay
Plastic Industries. After writing such letter, as is evident from the order
impugned, the appellants waited till 18th November, 2008 to approach this
Court for redressal of their grievance. The learned Single Judge did not
entertain the writ petition basically on the ground that the order of
cancellation was passed against the appellants on 10th July, 2002 and they
had approached the writ Court on 18th November, 2008 and, hence, the
doctrine of delay and laches is squarely attracted to the case at hand.
Additionally, the learned Single Judge referred to the decision of the
Supreme Court in M.C. Mehta v. Union of India rendered on 12th
September, 2000 directing that if payment is not made by any of the allottees
on a demand being raised, their allotment shall stand cancelled and they
shall have to close down the unit immediately.
4. Questioning the soundness of the aforesaid order, Mr. Gandhi, learned
counsel for the appellants, urged that the learned Single Judge has fallen into
error by throwing the writ petition overboard on the ground of delay and
laches without adverting to the merits of the case despite the fact that a stand
was taken in the writ petitions that a series of representations and complaints
were made to the DSIDC and, therefore, the cause of action remained alive.
It is contended by him that when such a substantial right is affected, it was
not apposite on the part of the learned Single Judge not to adjudicate the lis
on merits but to accept the stand put forth by the DSIDC that the allotment
stood cancelled because of non-compliance of the conditions incorporated in
the order of allotment and further erroneously placing reliance on the
observations of the Apex Court. The learned counsel, to buttress his
submissions, has invited our attention to the decisions rendered in M/s Dehri
Rohtas Light Railway Company Limited v. District Board, Bhojpur and
others, AIR 1992 SC 802 and Allahabad Bank v. State of West Bengal AIR
2007 SC (Supp) 519.
5. Resisting the aforesaid submissions, Ms.Anusuya Salwan, learned
counsel for the respondent-DSIDC, submitted that continuous representation
in a matter of this nature does not keep a lis or right alive as the same was
done in pursuance of the directions issued by the Supreme Court and
initially a list was prepared giving priority and in the priority list, the names
of the appellants were included but when they failed to comply with the
conditions incorporated in the letter of allotment, they cannot lie in slumber
for such a long period and make an endeavour to get the right alive which
had become extinct. The learned counsel further submitted that the
controversy has been put to rest by this Court in LPA No. 101/2009 Sunil
Dua v. Government of NCT of Delhi and Others decided on 12.05.2009
and in LPA No. 48/2008 Dinesh Lalwani v. DSIDC.
6. To appreciate the rival submissions raised at the Bar, we have
carefully perused the order passed by the learned Single Judge. The
submission of Mr.Gandhi, learned counsel for the appellants, is that the
direction issued by the Supreme Court not being mandatory and in the realm
of discretion, the DSIDC should have condoned the delay and considered the
application. On a perusal of the order passed in Sunil Dua (supra), it is
evincible that a Division Bench of this Court had held as under:
"3. There is no dispute that the Supreme Court‟s order dated 12th September, 2000, desired that allotment of those who did not make substantial payment should be cancelled. As per the DSIDC, according to the directions of the Supreme Court, the draw of plots was held on 3rd October, 2000 and eligible allottees held successful in the draw were issued allotment letter. Under the allotment letters, 50% of the demand was to be made immediately on issuance of the allotment letters. The last date
for payment of 50% was extended upto 31st March, 2001 by press notification. It was also stated on behalf of the DSIDC that by a public notice dated 21st January, 2001, published in „Times of India‟, allottees were informed that the Supreme Court of India in its hearing dated 24th January, 2001, had extended time for receipt of 100% payment in the case of allottees at Narela, Badli, Jhilmil and Patparganj as well as 50% payment in case of Bawana upto 31st March, 2001. A number of allottees did not deposit 50% payment within the stipulated time, however, keeping in view the hardship faced by the allottees, it was decided by the DSIDC that all those allotees who did not make the first 50% payment on time would be given an option to withdraw their amounts deposited and keep only the security deposit amounts with the Corporation and DSIDC would maintain a separate list of these allottees and their cases may be considered after new land was acquired and developed and after complying with the Supreme Court‟s order for exhausting the pending allottees. A copy of the notice dated 26 th August, 2001 is annexed at page 109 of the paper book, a copy of the public notice dated 26th January, 2001 published in the newspaper is annexed at page 121 of the paper book and a copy of the order dated 12th January, 2000 passed by the Supreme Court is annexed at page 101 of the paper book."
7. In view of the aforesaid, it is evincible that a cut off date had been
fixed. We do not intend to advert to the facet whether after the cut off date
the application could have been entertained or not, inasmuch as that may be
determined on the anvil of numerous facts. Keeping the said issue open, we
are inclined to proceed whether in the obtaining factual matrix, the DSIDC
has committed any illegality by cancelling the letter of allotment issued in
favour of the appellants. It is urged by Mr. Gandhi that the only ground on
which the learned Single Judge has actually dismissed the writ petition is
delay and laches. He has drawn immense inspiration from the decision in
M/s Dehri Rohtas Light Railway Company Limited (supra). In the said
case, the Apex Court has opined that the dismissal of belated and stale claim
under Article 226 of the Constitution of India is not a rule of law but a rule
of practice. Their Lordships have observed that where the illegality is
manifest in the order and the reason for not challenging the order is
appositely explained, the delay in filing the writ petition should not be taken
into consideration.
8. Be it noted, the factual matrix in the said case was absolutely different
as is evident from paragraph 12 of the order. For the sake of convenience,
we think it apt to reproduce paragraph 12:
"12. The question thus for consideration is whether the appellant should be deprived of the relief on account of the laches and delay. It is true that the appellant could have even when instituting the suit agitated the question of legality of the demands and claimed relief in respect of the earlier years while challenging the demand for the subsequent years in the writ petition. But the failure to do so by itself in the circumstances of the case, in our opinion, does not disentitle the appellant from the remedies open under the law. The demand is per se not based on the net profits of the immovable property, but on the income of the business and is, therefore, without authority. The appellant has offered explanation for not raising the question of legality in the earlier proceedings. It appears that the authorities proceeded under a mistake of law as to the nature of the claim. The appellant did not include the earlier demand in the writ petition because the suit to enforce the agreement limiting the liability was pending in appeal, but the appellant did attempt to raise the question in the appeal itself. However, the Court declined to entertain the additional ground as it was beyond the scope of the suit. Thereafter, the present writ petition was filed explaining all the circumstances. The High Court considered the delay as inordinate. In our view, the High Court failed to appreciate all material facts particularly the fact that the demand is illegal as already declared by it in the earlier case."
9. In our considered opinion, the said case is distinguishable on facts.
The learned counsel for the appellants has also placed heavy reliance on the
decision in Allahabad Bank v. State of West Bengal AIR 2007 SC (Supp)
519 wherein the Apex Court took note of the fact that the delay itself in the
said case, when the representations were made, would not have resulted in
the dismissal of the writ petition in limine. On a scrutiny of the facts in the
said case, it is perceivable that the High Court of Calcutta had issued the
direction permitting the petitioners to submit several representations and
when no decision was taken, the writ petition was filed, the same being
imperative. We think it appropriate to reproduce paragraph 5 in entirety:
"5. Mr. K.K. Venugopal, learned senior counsel appeaing for the appellant submitted that the High Court has erroneously concluded that there was inaction on the part of the appellants or that there was any delay. In fact in terms of the earlier directions of the High Court, several representations were made to the Competent Authority. Since no action was taken, filing of the writ petition became imperative."
10. On a scrutiny of the said decision, we notice that the said decision was
rendered in a different factual backdrop and is distinguishable.
11. In this regard, we think it condign to refer to certain citations in the
field. In C. Jacob v. Director of Geology & Mining, (2008) 10 SCC 115,
the Apex Court has held as follows:
"10. Every representation to the government for relief, may not be replied on merits. Representations relating to matters which have become stale or barred by limitation, can be rejected on that ground alone, without examining the merits of the claim. In regard to representations unrelated to the Department, the reply may be only to inform that the matter did not concern the Department or to inform the appropriate Department. Representations with incomplete particulars may be replied by seeking relevant particulars. The replies to such representations, cannot furnish a fresh cause of action or revive a stale or dead claim.
11. When a direction is issued by a court/tribunal to consider or deal with the representation, usually the directee (person directed) examines the matter on merits, being under the
impression that failure to do so may amount to disobedience. When an order is passed considering and rejecting the claim or representation, in compliance with directions of the court or tribunal, such an order does not revive the stale claim, nor amount to some kind of "acknowledgment of a jural relationship" to give rise to a fresh cause of action."
12. In Union of India & Ors. V. M.K. Sarkar, (2010) 2 SCC 59, it has
been held thus:
"14. The order of the Tribunal allowing the first application of respondent without examining the merits, and directing appellants to consider his representation has given rise to unnecessary litigation and avoidable complications. The ill- effects of such directions have been considered by this Court in C. Jacob v. Director of Geology and Mining: (2008) 10 SCC 115:
"9. The courts/tribunals proceed on the assumption, that every citizen deserves a reply to his representation. Secondly, they assume that a mere direction to consider and dispose of the representation does not involve any 'decision' on rights and obligations of parties. Little do they realize the consequences of such a direction to 'consider'. If the representation is considered and accepted, the ex-employee gets a relief, which he would not have got on account of the long delay, all by reason of the direction to 'consider'. If the representation is considered and rejected, the ex- employee files an application/writ petition, not with reference to the original cause of action of 1982, but by treating the rejection of the representation given in 2000, as the cause of action. A prayer is made for quashing the rejection of representation and for grant of the relief claimed in the representation. The Tribunals/High Courts routinely entertain such applications/petitions ignoring the huge delay preceding the representation, and proceed to examine the claim on merits and grant relief. In this manner, the bar of limitation or the laches gets obliterated or ignored."
15. When a belated representation in regard to a 'stale' or 'dead' issue/dispute is considered and decided, in compliance with a direction by the Court/Tribunal to do so, the date of such
decision cannot be considered as furnishing a fresh cause of action for reviving the "dead" issue or time-barred dispute. The issue of limitation or delay and laches should be considered with reference to the original cause of action and not with reference to the date on which an order is passed in compliance with a court's direction. Neither a court's direction to consider a representation issued without examining the merits, nor a decision given in compliance with such direction, will extend the limitation, or erase the delay and laches.
16. A court or tribunal, before directing "consideration" of a claim or representation should examine whether the claim or representation is with reference to a "live" issue or whether it is with reference to a "dead" or "stale" issue. If it is with reference to a "dead" or "stale" issue or dispute, the court/tribunal should put an end to the matter and should not direct consideration or reconsideration. If the court or tribunal deciding to direct "consideration" without itself examining the merits, it should make it clear that such consideration will be without prejudice to any contention relating to limitation or delay and laches. Even if the court does not expressly say so, that would be the legal position and effect."
13. In Naresh Kumar v. Department of Atomic Energy & Ors, Civil
Appeal No. 3138/2008 decided on 08.07.2010, the Apex Court has held
thus:
"If an employee keeps marking representation after representation which are consistently rejected then the appellant cannot claim any relief on that ground."
14. From the aforesaid enunciation of law, it is luculent that stale claims
do not get a new lease of life because the affected person has been
representing to the authorities. It is also luminescent that the directions by
the courts to dispose of the claim or representation without deliberation on
merits do not extend the period of limitation or extinguish the facet of delay
and laches. It also does not create a new cause of action. To put it
differently, the stale claims remain stale and the dead claims do not rise like
a phoenix. A direction to deal or consider a representation is not a
„Mahamantra‟ on which a litigant can build an edifice to canvass that the
cause of action or his grievance remains alive to be addressed on merits.
The doctrine of delay and laches visits like the chill of death and does not
spare anyone, even the one who fosters the idea and nurtures the notion that
he can sleep to avoid death and eventually proclaim "Deo gratias" - „thanks
to God‟.
15. In the case at hand, the appellants were very much aware that the
allotment stood cancelled on 10th July, 2002. No acceptable reason has been
given as to why they waited till November, 2008. As has been urged before
us, they approached the authorities making complaints and representations.
Particularly, in a case of this nature, one cannot lie in slumber and wake up
at his own pleasure and approach the writ Court. The writ Court may have
the immense power to entertain the writ petition ignoring the facet of delay
but that would depend upon the facts of the case. However, in the case at
hand, the appellants were allotted particular land in lieu of sealing of the
industry on the basis of a policy and though they were put in a priority
category, yet they did not avail the benefit. Thereafter, they have been
placed in the waiting list. Others who are not put in the priority category
have already been brought to priority category and they should have a
chance and, therefore, extending the benefit of equity which is also a facet of
equitable jurisdiction under Article 226 of the Constitution of India to the
appellants would be inequitable to others. The same, we are disposed to
think, is unwarranted.
16. In view of our preceding analysis, we do not perceive any merit in
these appeals and, accordingly, the same are dismissed without any order as
to costs.
CHIEF JUSTICE
MANMOHAN, J AUGUST 19, 2010 AK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!