Citation : 2010 Latest Caselaw 3716 Del
Judgement Date : 10 August, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ IA No. 7859/2008 in CS(OS) NO. 528/2008
Date of Decision : 10.08.2010
M/s Reliance Builder ...... Plaintiff
Through: Mr. R. S. Tomar, Advocate
Versus
Om Satyam Co-operative
Group H/S Ltd. & Anr. ....... Defendants
Through: Mr. Madhukar
Pandey, Adv. for the
defendant no. 1.
CORAM :
HON'BLE MR. JUSTICE V.K. SHALI
1.
Whether Reporters of local papers may be allowed to see the judgment? YES
2. To be referred to the Reporter or not ? NO
3. Whether the judgment should be reported in the Digest ? NO
V.K. SHALI, J. (oral)
IA No. 7859/2008
1. This order shall dispose of an application bearing no.
7859/2008 filed by the defendant no. 1 under Section 8 of
the Arbitration and Conciliation Act, 1996 for reference of the
dispute between the plaintiff and the defendants to Arbitral
Tribunal in terms of the agreement.
2. Briefly stated the facts of the case are that the
plaintiff/Reliance Builders filed a suit for recovery of
Rs.55,50,000/- against the defendant no. 1 and made the
Registrar Co-operative Society, Government of NCT of Delhi
as defendant no. 2. It was alleged in the suit that the plaintiff
had entered into an agreement for construction of 90 flats on
a plot of land measuring 6733.32 sq. meters situated at Plot
No. 13, Sector-4, Dwarka, New Delhi for the benefit of the
members of the society. This agreement was entered into
between the plaintiff and the defendant no. 1 on 30.12.1998.
The details of the work to be executed are given in the said
agreement which are not of much relevance for the purpose of
deciding the present application.
3. In the said agreement there was an arbitration clause
contained in Clause 34 of the agreement which reads as
under:
"Except where otherwise provided for in the contract all questions and disputes relating to the meaning of the specification, designs, drawings and instruction herein before mentioned and as to the quality of workmanship or materials used on the work or as to any other question, claim, right matter or thing whatsoever in any way arising out of or relating to the contract, design, drawings, specification, estimates, instructions orders of these conditions or otherwise concerning the
works or the execution or failing to execute the same whether arising during the progress of the work or after the completion or a bodement thereof shall be referred to a sole Arbitrator to be appointed by the Secretary of the owner, in case of the arbitrator to whom the matter is originally referred being transferred or vacating his office or being unable to act for any reason whatsoever, the Secretary of the owner shall appoint another person to act as arbitrator in accordance with the terms of the contract. It is also a term of this contract that no person other than the secretary of the owner shall appoint an arbitrator, and if for any reason, that is not possible the matter is not to be referred to arbitration at all. The arbitrator so appointed shall be an approved Arbitrator of the Institute of Arbitrator and approved for the valuation of matter to be so referred."
4. It is alleged by the plaintiff that the despite having executed
the work, the defendant no. 1 did not clear the 10th running
bills of the plaintiff as a consequence of which dispute arose
between the plaintiff and the defendant no.1. The plaintiff
refused to hand over the possession of the flats to the
defendant no.1 society. The Managing Committee of the
defendant no.1/society in order to break impasse held
meeting with the plaintiff and arrived at a settlement and
executed a fresh agreement on 12.06.2003. This fresh
agreement was called as a supplemental agreement, the
defendant no. 1 had agreed to make the balance payment to
the plaintiff in two installments by way of 90 cheques, each
cheque for a sum of Rs.1,75,000/- while as the plaintiff was
to carry out certain works in the individual flats numbering
90, the details of which are given in the agreement. It is
stated that despite the 90 cheques having been issued by the
plaintiff only 70 cheques were honoured while as the
remaining 20 cheques were dishonoured which necessitated
the filing of the present suit Rs.50,55,000/- which included
principal amount of Rs.35,00,000/- of 20 cheques @
Rs.1,75,000/-.
5. The learned counsel for the plaintiff has stated that the
possession of all the flats had been handed over to the
members of the defendant no.1/society after execution of the
works as stipulated in the supplement agreement but the
balance payment of 20 cheques were not released.
6. The defendant no. 1 on being served on the very first date
filed an IA no. 7859/2008 wherein it took the plea that
according to the agreement dated 30.12.1998 there is an
arbitration clause between the plaintiff and the defendant
no.1, and therefore, the dispute deserves to be referred to an
arbitrator and the present suit cannot continue. It was stated
by the learned counsel for the defendant no.1 during the
course of his oral submissions that the new agreement was
executed on 12.06.2003 but it was only supplementary
agreement, and therefore, the said agreement cannot override
the first agreement dated 30.12.1998 as a consequence of
which the arbitration clause which existed between the
parties originally came into operation. Apart from this legal
submission made by the defendant in the application is that
there have been averments in extenso making the allegation
of embezzlement, fraud and collusion against one Sh. Lal
Chand, Ex-Secretary of the defendant no.1/Society, Sh. K. P.
Singh allegedly unelected President and Sh. Rajbir Singh, the
proprietor of the plaintiff in defrauding the defendant
no.1/society for siphoning off the funds of the society. All
these averments are not relevant for deciding the present
application under Section 8 of the Arbitration and
Conciliation Act.
7. The plaintiff has filed a reply to the application raising the
plea that there is no arbitration agreement in as much as the
supplement agreement between the parties did not envisage
the settlement of the dispute between the parties by way of a
Arbitral Tribunal. Reference was made to a clause of the
supplementary agreement wherein it was stated that Courts
only in Delhi will have the jurisdiction and the said clause
read as under:-
"All disputes arising out of or in any way connected with the agreement shall be deemed to have arisen in Delhi and only the Court in Delhi have the jurisdiction or to determine the same."
8. In the event of any dispute arising between the parties only
Delhi Courts would have the jurisdiction which would clearly
mean that the intention of the defendant at no point of time
was to have the dispute adjudicated by the Arbitral Tribunal
as envisaged in the original agreement.
9. The main contention of the learned counsel for the defendant
is that the second agreement which was executed on
12.06.2003 in pursuance to which 90 cheques were issued
was a supplement agreement to the first agreement dated
30.12.1998. That being so the second agreement does not
obliterate the arbitration clause in Clause 34 of the first
agreement. If at all the plaintiff has any grievance with
regard to the additional amount he had to have the dispute
adjudicated by the Arbitral Tribunal .
10. The learned counsel for the defendant has in order to
substantiate this point has referred a judgment titled A. K.
Jaju Vs. Avni Kumar AIR 2003 DELHI 364 wherein under a
somewhat similar circumstances, the second agreement
which was executed between the parties had specifically made
a mention that the agreement was in continuation of the first
agreement and it was held that the second agreement which
was in continuation of the first agreement did not mean to
override the first agreement. Since the first agreement
contains an arbitration clause, therefore, the dispute had to
be referred to the Arbitral Tribunal.
11. I have considered the submissions made by the learned
counsel for the defendant no. 1 and have also gone through
the judgment cited. So far as the judgment title A. K. Jaju
Vs. Avni Kumar (Supra) is concerned, no doubt, the learned
Single Judge of this Court has held that the second
agreement which was entered into between the parties was a
continuing agreement, and therefore, by using of said term
continuing agreement the arbitration clause which was
contained in the initial agreement did not get obliterated as a
consequence of which the dispute was referable to arbitration,
does not apply to the facts of the present case. In the
present case, the word which has been used is supplemental
agreement. It may be pertinent here to mention that under
the original agreement dated 30.12.1998, the details and the
type of construction which was expected to be carried out by
the plaintiff were mentioned in extenso in the first agreement.
In the second agreement between the parties certain jobs or
works which were allegedly not completed in addition to the
earlier work were agreed to be executed by the plaintiff
subject to payment of Rs.1,75,000/- by each of the
allottee/member of the defendant no.1/society. It may also
be relevant to mention that out of the 90 cheques each for a
sum of Rs.1,75,000/- nearly 70 cheques were already
encashed by the present plaintiff, and therefore, it could not
be said that the arbitration clause which was contained in the
original agreement dated 30.12.1998 is deemed to be
extended to supplement agreement also and consequently the
plea of the defendant under Section 8 (i) of the Arbitration
and Conciliation Act would act as a bar to the entertainment
of the suit. This view also gets support from the fact that in
the supplement agreement the parties have specifically stated
that all the disputes which may arise between the plaintiff
and the defendant no.1 would be within the jurisdiction of the
Delhi Courts only. Thereby meaning that the parties in the
event of any dispute between them on account of
supplemental agreement could invoke the jurisdiction of Delhi
Courts. If that be the condition this was contrary to the
condition contained in Clause 34 of the original agreement
dated 30.12.1998 under which the dispute had to be referred
to Arbitral Tribunal. Therefore, the factum of having a new
clause of jurisdiction in the agreement and the fact that the
agreement is a supplemental agreement only with regard to
the works to be executed does not necessarily place the facts
of the present case at par with facts of the reported case so as
to adopt the interpretation of that case.
12. I, accordingly, feel that there is no merit in the contention of
the learned counsel for the defendant no. 1 that the present
dispute is covered by the arbitration agreement and
consequently has to be referred for adjudication by an
Arbitral Tribunal. The application of the defendant no. 1 is
dismissed as being without merit.
13. There are two IAs bearing no. 7859/2008 and 10317/2009 by
virtue of which the proceedings before the learned Arbitrator
who has been appointed by the defendants during the
pendency of the proceeding and is a former Additional District
Judge (Punjab) he is restrained by way of an ex-parte ad
interim injunction from proceeding ahead with the arbitration
dispute. So far as the said application of the proceedings
before the Arbitral Tribunal is concerned, that is also allowed.
The learned Arbitrator cannot adjudicate the dispute between
the parties as the suit continues to be in the High Court.
With these observations all the three IAs stand disposed of.
V.K. SHALI, J.
AUGUST 10TH , 2010 KP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!