Citation : 2010 Latest Caselaw 3637 Del
Judgement Date : 6 August, 2010
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.290/2010 & CM No.7824/2010
BHARAT SANCHAR NIGAM LTD. .....Appellant through
Mr.Dinesh Agnani with
Ms. Leena Tuteja, Advs.
versus
HARYANA TELECOM LTD. .....Respondent through
Mr.Narendra M. Sharma,
Mr. Abhishek Sharma, Advs.
WITH
FAO(OS) No.385/2010
BHARAT SANCHAR NIGAM LTD. .....Appellant through
Mr.Dinesh Agnani with
Ms. Leena Tuteja, Advs.
versus
HARYANA TELECOM LTD. .....Respondent through
Mr.Narendra M. Sharma,
Mr. Abhishek Sharma, Advs.
% Date of Hearing : August 02, 2010
Date of Decision : August 06, 2010
CORAM:
* HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MS. JUSTICE MUKTA GUPTA
1. Whether reporters of local papers may be
allowed to see the Judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the Judgment should be reported
in the Digest? Yes
FAO(OS)290/2010 Page 1 of 19
VIKRAMAJIT SEN, J.
1. These Appeals assail the Judgment of the learned Single
Judge dated 15.3.2010 dismissing the Appellants‟ Objections
under Section 34 of the Arbitration & Conciliation Act, 1996
(A&C Act for short) on the ground that they could not be
entertained having been filed beyond the prescribed period of
prescription set-down in third sub-section of that very Section.
The learned Single Judge has applied Union of India -vs-
Popular Construction Co., (2001) 8 SCC 470 wherein their
Lordships have clarified that "Section 34(1) itself provides that
recourse to a court against an arbitral award may be made only
by an application for setting aside such award „in accordance
with‟ sub-section(2) and sub-section(3). Sub-section(2) relates to
grounds for setting aside an award and is not relevant for our
purposes. But an application filed beyond the period mentioned
in Section 34, sub-section(3) would not be an application „in
accordance with‟ that sub-section. Consequently by virtue of
Section 34(1), recourse to the court against an arbital award
cannot be made beyond the period prescribed". Considerations
analogous to Section 5 of the Limitation Act, 1963 (Limitation
Act) would palpably be available in terms of proviso to Section
34(3), that is, for the period spanning 30 days after three
months have elapsed from the date on which the concerned
party had received the Arbitral Award. We may immediately
revert to Section 31(5) of the A&C Act which mandates that
after the Arbitral Award is made, a signed copy shall be
delivered to each party. The case of the Appellants is that a
signed copy of the Arbitral Award was not delivered to them by
the Arbitrator, although a photocopy thereof had been provided
to it by the Respondents/Claimants. There is considerable
controversy even with regard to the date on which the said
photocopy was made available by the Respondents to the
Appellants.
2. The Award in FAO(OS) No.290/2010 (in Arbitration Case
No.113/98 arising out of Suit No. AA164/1997) is for a sum of
` 1,16,37,288/- together with interest at the rate of eighteen per
cent per annum, in the event that the Appellants fail to make the
payment within two months of the Award which was pronounced
on 7.8.2000. The Award in FAO(OS) No.385/2010 (in Arbitration
Case No.114/1998 arising out of Suit No. AA 163/1997) is for a
sum of ` 1,49,78,142/- with interest at the rate of eighteen per
cent per annum in the event that the Appellants fail to make the
payment within two months of the Award which was pronounced
on 7.8.2000. Although it is a matter of speculation whether the
Objections filed by the Appellants would have found favour with
the learned Single Judge, the fact remains that by declining to
consider the Objections on the premise that they had been
preferred beyond the prescribed period of prescription, the
Union of India would become liable to discharge the principal
sum of ` 2,66,15,430/- together with interest of ` 4,79,07,774/-.
Negligent or egregiously incorrect legal action seems to have
become the preserve of the Government and/or Corporations
held or controlled by it. This is obviously because of lack of
answerability of its officers, as the present case will make
manifest.
3. The wisdom expressed by the Privy Council over a century
ago in Nazir Ahmad -vs- King Emperor, AIR 1936 PC 253
continues to remain contemporarily contextual. The Privy
Council observed that if an action has to be taken in a particular
manner, it must be carried out in that manner only, else it may
be held not to have been effected at all. The wisdom of this
pronouncement is manifestly evident in the facts of the present
case. This abiding reasoning in respect of strict compliance with
the procedural requirement of a statute had been applied by the
Hon‟ble Supreme Court in Ramchandra Keshav Adke -vs-
Govind Joti Chavre (1975) 1 SCC 559; Shiv Bahadur Singh -vs-
State of Uttar Pradesh, AIR 1954 SC 322 and Deep Chand -vs-
State of Rajasthan, AIR 1961 SC 1527. In Ramchandra, the
Court was called upon to decide whether Section 5(3) of
Bombay Tenancy and Agricultural Land Act, 1948, which deals
with verification of the alleged surrender of possession by the
tenant was compulsory, and the effect of its non-compliance.
The Court opined that "the imperative language, the beneficent
purpose and importance of these provisions for efficacious
implementation of the general scheme of the Act, all unerringly
lead to the conclusion that they were intended to be mandatory.
Neglect of any of these statutory requisites would be fatal.
Disobedience of even one of these mandates would render the
surrender invalid and ineffectual. .... The rule will be attracted
with full force in the present case because non-verification of
the surrender in the requisite manner would frustrate the
purpose of this provision". In Deep Chand, the Supreme Court
adverted to the rule in Nazir Ahmad to hold that a statement of
account which has not been recorded in strict compliance of
Section 164 of Code of Criminal Procedure, 1973 would not be
admissible as a confession. In Ram Phal Kundu -vs- Kewal
Sharma, (2004) 2 SCC 759, the Court declined to look into any
extrinsic evidence to inquire into the question as to who shall be
deemed to have been set up as a candidate by a political party
and would only look at the paragraphs delineated by the
Symbols Order of Election Symbols (Reservation and Allotment)
Order, 1968 which lay down the mechanism for ascertaining
when a candidate shall be deemed to be set up by a political
party and the procedure for substitution of a candidate.
4. We mention these decisions since we perceive it is
poignant to point out that if the statutory necessity of delivering
a signed copy of the Arbitral Award is not rigorously complied
with, it will, more often than not, pregnant with pernicious
potentialities. This is particularly so since the A&C Act has
ordained that Objections preferred after 120 days, of the
delivery [under Section 31(5)] or the receipt [under Section
34(3)] of the Arbitral Award, cannot be considered by the Court.
Scope to condone delay after this period has not been vested in
the Court. The word „party‟ has been defined in Section 2(h) of
the A&C Act to mean a party to an arbitration agreement. We
may, therefore, be pardoned if we repeat, reemphasize and
reiterate the Nazir Ahmad dictum. If the fasciculus of
Section 31 is read holistically, it will be crystal clear that all the
actions postulated in that provision pertain to the powers and
responsibilities of the Arbitral Tribunal. The Section does not
envisage any role of the Claimant. Inasmuch as sub-section
31(5) speaks of „each party‟, the delivery/receipt of the Arbitral
Award has to be strictly effected on each party itself in
contradistinction to its agent or officers etc. In FAO(OS)
No.578/2009 titled Karmyogi Shelters Pvt. Ltd. -vs-
Benarsi Krishna Committee, a Division Bench of this Court
was concerned with the controversy whether the onerous
obligations of the statute had been adequately met by the
service of Arbitral Award on the Advocate of one of the party
concerned. The Division Bench lamented that considerable
judicial time had been wasted in entertaining arguments
surrounding sufficiency of service simply because the statute
has not been strictly complied with. It was further held that
Section 2(g) of the A&C Act does not take within its sweep the
service of the Arbitral Award on an agent of any of the parties to
the arbitration. The Bench had also found it inappropriate to
extrapolate the ratio in Nilkantha Sidramappa Ningashetti -vs-
Kashinath Somanna Ningashetti, AIR 1962 SC 666 on the
premise that whilst condonation of delay in filing the Objections
under the earlier and repealed Arbitration Act, 1940 could be
prayed for before the Court, this indulgence is available only for
a comparatively short period of 30 days under the A&C Act.
Karmyogi applied an earlier decision of the Division Bench in
National Projects Constructions Corporation Limited -vs-
Bundela Bandhu Constructions Company, AIR 2007 Delhi
202:139 (2007) DLT 676 which, in turn, applied, as it was bound
to, the dictum in Union of India -vs- Tecco Trechy Engineers &
Contractors, (2005) 4 SCC 239. We should immediately
differentiate the case before us from the earlier case since the
delivery/receipt of the Arbitral Award by the Advocate of the
Appellants has remained unsubstantiated. The factual matrix in
Reshma Construction -vs- State of Goa, 1998(3) Bombay CR 837
: 1999(1)MhLJ 462 is strikingly similar to the case before us. An
amendment in the Award had been prayed for and the Court
observed that it was the duty of the Applicant to collect a
corrected and signed copy of the amended Award. The Court
also observed that it was the mandatory duty of the Arbitrator to
issue a copy of the Award to each and every party to the
proceedings. In Kempegowda -vs- National Highway Authority
of India, 2008(2) ALR 393 Karnataka the High Court has held
that Section 31(5) of the A&C Act required the Arbitrator to
ensure delivery of a copy of the Award on the parties to the
arbitration proceedings. The compensation in accordance with
the Award dated 21.2.2003 was disbursed on 27.10.2003.
Limitation, however, was held to have started to run only on
8.12.2003 when the Appellant was delivered with a copy of the
Award. In Ramesh Pratap Singh -vs- Vimala Singh, 2004(2) ALR
147 (MP), the Jabalpur Bench of the said Hon‟ble High Court
found service of an unsigned/photocopy of an Award to be
wholly irrelevant and held that the period of limitation should be
counted from 27.7.1998, on which date a signed copy of the
Award has been furnished to the Appellant/Objector.
5. It also seems to us that it is imperative that delivery/
receipt of the Arbitral Award should be at the instance,
responsibility and authority of the Arbitral Tribunal. In the case
in hand, the Arbitral Award appears to have been dispatched
under „Certificate of Posting‟ and not recorded delivery, and
that too to the Advocate of the Appellants. „UPC‟ merely
evidences the posting of a letter/envelope and not its service. In
matters of moment, such as delivery/receipt of an Arbitral
Award, the Arbitral Tribunal is duty-bound to ensure that the
Award is actually delivered directly to the party concerned. It is
our fervent hope that the Arbitrators and Arbitral Tribunals
shall henceforward consider their judicial contract to have
culminated only upon their being satisfied that each of the
parties before it has actually been served with the Arbitral
Award. If the recorded delivery is returned undelivered, the
Arbitral Tribunal must dispatch it once again until it is served or
there is sufficient reason to assume that it stands served.
6. Learned counsel for the Respondent has laid great store
on the alleged service of the Arbitral Award at the instance and
the initiative of the Claimant/Respondent on the
Chairman/Secretary, Department of Telecommunication (DoT)
on 29.9.2000 and 4 days later on the Central Registry of the
DoT. It has also been emphasized that there has been an
admission with regard to these asseverations in the Petition. On
a complete and not a piecemeal reading of the pleadings, this is
not correct. Furthermore, reliance has been placed on remarks
on the file of the Appellants. These would be relevant as
evidence of actual service only if steps for service on the
Appellants had been initiated in consonance with the statutory
provisions, viz. by the Arbitral Tribunal itself. What had
transpired in the present case, however, is that due to an error
in the numbering of the matter, an amendment in the Arbitral
Award was necessitated and a copy of the corrected Award is
stated to have been served by the Respondent on the Appellants
on 6.11.2000. The application was moved by the Respondents
under Section 33 of the A&C Act and facially, therefore, the
period of 90 days would have to be computed from the date on
which that application was disposed of and not prior thereto.
Learned counsel for the Respondent is, therefore, entirely
wrong in adverting to any alleged event prior to 6.11.2000, on
which date the application for correction was disposed of by the
learned Arbitrator. Had the Appellants not filed the application,
time for filing Objections would commence, uncontestably, from
6.11.2000. In any event, receipt of a photocopy of the Arbitral
Award prior to this date, when amendments to the Arbitral
Award were carried out, would be an anachronistic error. If the
arguments of the Respondent are to be accepted, then the
requirement of limitation to be calculated only from the date on
which a certified copy of a judicial order sought to be impugned
before the Appellate Forum would become otiose. Till date, no
Court has adhered to this opinion, and for good reason, since a
truncated or edited copy of a decision could be supplied by an
adversary and if actions taken thereon are held to be binding,
alarming and dangerous repercussions may ensue.
7. Since there has been a complete infraction of the statutory
provisions so far as service of the Arbitral Award on the
Appellants is concerned, we hold that the period of limitation
had not started to run when the Objections were filed in the
various Courts by the Appellants. As a general proposition,
therefore, the period of 90 days for filing Objections, as
stipulated in Section 34 of the A&C Act, would have to be
computed from the date on which the concerned party was
served or received the singed copy of the Arbitral Award from
the Arbitral Tribunal. This, however, does not entirely solve the
conundrum which has arisen before us.
8. So far as FAO(OS) No.290/2010 arising out of OMP
No.251/2001 is concerned, the Appellant/BSNL appears to have
filed Objections under Section 34 of the A&C Act on 12.12.2000,
but in the Court of the District Judge, Ambala, Haryana, by the
Haryana Circle Department of Appellant. These Objections came
to be rejected on 16.5.2001 on the ground that the appointment
of the Chairman having been made by the High Court of Delhi
this Court alone should exercise jurisdiction in respect of any
further lis under the A&C Act including the entertainment and
decision on Objections. Certified Copy of these Orders was
received by the Appellant on 22.5.2001. The learned District
Judge, Ambala, inter alia, relied on Section 42 of the A&C Act.
The Objections eventually came to be filed in this Court on
9.7.2001. The Objections, OMP No.215/2001, were accompanied
by an application filed by the Appellant/BSNL seeking
condonation of delay, which was supported by an affidavit dated
30.8.2001 of the Assistant General Manager, Telecom, Haryana
Circle, Ambala, BSNL. The first hearing in the High Court of
Delhi was held on 31.8.2001. We will have to consider whether,
assuming that the time spent in the Court not possessing
jurisdiction (in the Ambala Court) can be excluded while
computing the period of 90/120 days, there is sufficient
explanation for the subsequent period, that is, 16.5.2001 to
9.7.2001.
9. The submission of the Appellants in both the Appeals is
that the delay should be condoned because the Appellants had
initiated proceedings bona fide in a Court not possessing
jurisdiction. We have also perused an Order of the High Court of
Himachal Pradesh, Shimla passed on 16.7.2001 in terms of
which the Objections filed by the Appellant before us were
rejected while considering an application filed by the
Respondents under Section 42 of the A&C Act read with Order
VII Rule 11 of the Code of Civil Procedure, 1908 (CPC for short);
later application was allowed. The wanton, ill-advice and
reckless action of the BSNL in approaching Courts in Ambala,
Chandigarh and the High Court of Himachal Pradesh at Shimla
has completely confounded the confusion.
10. In FAO(OS) No.385/2010, arising from OMP No.17/2002
Objections under Section 34 of the A&C Act came to be filed on
30.1.2001 in the Court of the District Judge, Union Territory,
Chandigarh which returned them by Orders dated 19.11.2001.
Meanwhile, the Respondent/Decree Holder had initiated
execution proceedings in this Court which attached the Bank
Accounts of the Appellant to the extent of ` 1,56,52,158/-.
Objections in this Court were filed on 3.1.2002.
11. We have expressed the opinion, hereinabove, that since
the Arbitral Award was not delivered by the Arbitral Tribunal
[as envisaged in Section 31(5) of the A&C Act] to the party, the
period for filing of Objections must be held not to have
commenced. Would this view remain steadfast even in
circumstances where Objections have actually been filed by the
concerned party albeit in the wrong Court. This is the legal
nodus which remains to be answered. It is axiomatic
jurisprudence that there is no estoppel against the statute. In
this case, however, this principle would not apply for the reason
that the party concerned, upon having filed Objections, has
exercised a right vested and bestowed upon it by virtue of a
statute. Moreover, law unhesitatingly and unquestionably acts
on admissions made by a litigating party. In this case the
Appellant has itself stated that copies of the Award were
received by it (from the Respondent/Decree Holder) on
6.11.2000, and thus, we find good reason to take this date as
the commencement of the period of limitation. On principles
analogous to Section 14 of the Limitation Act, 1963, the period
expended in a Court not possessing jurisdiction would have to
be excluded. Exclusion of time is an exercise totally distinct
from condoning the delay in filing an action. On the rejection or
return of the Plaint/Objections, the period for refiling cannot be
left open-ended. High Courts have taken the position that the
Court rejecting the plaint/petition is not possessed with powers
to fix a date within which the action must be filed in another
Court. By the introduction of Section 10(a) in Order VII, by Act
104 of 1976, this position has been changed and the vacuum has
been filled. It is now open to the Plaintiff/Petitioner to move an
application in the First Court, thereby specifying the Court in
which he proposes to present the plaint or refile the action after
its return, and pray that the First Court may fix a date for the
appearance of the parties. If the First Court passes such orders,
Sub-rule(4) clarifies that in this event the transferee Court
would not be required to once again issue notice to the
Defendant/Respondent.
12. It is trite that the Plaintiff/Petitioner may consider it
expedient or prudent to challenge the return or rejection order
before the Appellate forum; or it may decide to abide and
comply with the Order. In the first case, the time spent before
the Appellate Court may also have to be excluded. In the latter
case, the question that arises is how much time should be
reasonably allowed to the Plaintiff/Petitioner to file the rejected
Plaint in the Court which it considers rightly possesses
territorial jurisdiction. It seems incongruent to us that if the
Petitioner stands restricted to an initial period of 90+30 days, a
larger period can be allowed for the purpose of such refiling. So
far as this is concerned, we are in virgin legal territory as no
statutory provision appears to have been prescribed by any
legislation. We would, in these circumstances, hold that the
refiling must be carried out within the total span of 90 days,
leaving the Court with the discretion to condone any delay
restricted to a further period of 30 days provided sufficient
cause has been disclosed. The date of rejection in Ambala Court
was 16.5.2001; in Chandigarh on 19.11.2001 and in the High
Court of Himachal Pradesh on 16.7.2001. As already noted
above, the Objections were initiated in this Court in OMP
No.215/2001 on 31.8.2001 and in OMP No.17/2002 on 3.1.2002
respectively.
13. Mr. Sharma, learned counsel for the Respondent/Decree
Holder, has contended that since the Objections were rejected
under Order VII Rule 11 of the CPC in the Ambala Court, the
relief permitted by Section 14 of the Limitation Act would not be
available. After the filing of the Objections in this Court, the
Appellant avowedly preferred a Review before the Ambala Court
praying that the Objections ought to have been returned under
Order VII Rule 10 and not rejected under Order VII Rule 11 of
the CPC. Where a Court arrives at a conclusion that it does not
possess jurisdiction, it should not proceed further and should
only pass orders which would consequentially ensue; in most
cases for the rejection of the plaint/petition/Objection or with
the dismissal thereof, with liberty for filing them in a competent
court in accordance with law. The Review was dismissed on the
ground that it had been preferred beyond the period of
limitation; secondly that the High Court of Delhi was already
seized of the Objections and no prejudice was shown to have
been caused. Therefore, the Review was not dismissed on
merits. This being the situation, we think that there is no
alternative but to treat the action of the Ambala Court as one
standing and predicated on Order VII Rule 11 of the CPC,
thereby rejecting the Objections and not dismissing them.
14. Learned counsel for the Appellants has submitted that the
legal action taken in the High Court of Himachal Pradesh at
Shimla may be discounted as totally irrelevant since it has no
further bearing on the Issues that have arisen before us.
15. However negligent and ill-advised the action taken by the
Appellants may be, we do not see them as not bona fide.
Therefore, the period spent by the Appellants in the Court at
Ambala and Chandigarh ought to be excluded while computing
the period of limitation. As has already been disclosed above, in
the case in hand, because of the admissions of the Appellants
before us, the starting point of limitation is 6.11.2000. The
Objections were filed in Ambala on 12.12.2000. Keeping in view
the proviso to Section 14(3), remission, allowance or exclusion
is allowable to the Appellants from 12.12.2000 till the rejection
of the Objections on 16.5.2001 and also from 16.5.2001 till
22.5.2001 since a Certified Copy was available only on
22.5.2001. The Objections were eventually filed on 9.7.2001,
thereby exhausting 47 days. So far as Objections are concerned,
a total of 82 days have been exhausted from the date of
receiving Award and filing Objections in Delhi, excluding the
time spent in Ambala. The Objections were, therefore, filed
within 90 days prescribed under Section 34 of the A&C Act and
should be entertained on merits.
16. We shall now deal with the Objections filed in Chandigarh.
Since they were filed on 30.1.2001, the Appellant had exhausted
84 days commencing from 6.11.2000. The Appellant would be
entitled to exclusion of the period from 30.1.2001 till 23.11.2001
when the certified copy of the Order, along with the entire file,
was received by it. The Appellant had exhausted 84 days from
6.11.2000 to 31.1.2001, leaving 6 days available to it for
refilling in the appropriate Court. If 30 additional days are
condoned, the filing should have been carried out in this Court
with 36 days from 23.11.2001. Since this period had expired
when this Court was in Winter Vacation, the Appellant, if it had
filed the Objections on the reopening day, would have the
benefit of the entire period of Winter Vacation. The first day of
reopening was 3.1.2002, on which the Objections were actually
filed in Delhi. Hence, the filing of Objections would be deemed
to have been done within 120 days. Keeping the convoluted
facts of the filing in the Chandigarh in view, we think it
appropriate to exercise powers reserved to the Court under
Section 34 of the A&C Act to condone a delay of 30 days for the
period between 91st day and the 120th day which expired on the
day of reopening. Since the filing occurred within this period,
these Objections also would have to be heard on merits.
17. For these reasons, the Appeals are allowed but with costs
of ` 1,00,000/-, out of which ` 50,000/- will be made payable to
the Prime Minister‟s Relief Fund and the balance be paid to the
Respondents. Subject to payment of costs to be paid within two
weeks, both Objections are remanded to the learned Single
Judge for their determination on merits.
( VIKRAMAJIT SEN ) JUDGE
( MUKTA GUPTA ) JUDGE August 06, 2010 tp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!