Citation : 2010 Latest Caselaw 2284 Del
Judgement Date : 29 April, 2010
* HIGH COURT OF DELHI: NEW DELHI
+ FAO (OS)No.230/2010 & CM No.6478/2010
Judgment reserved on: 13th April, 2010
% Judgment delivered on: 29th April, 2010
NATIONAL HIGHWAYS ..... Appellant
AUTHORITY OF INDIA
Through: Mr. Ramji Sriniasan, Sr.
Adv. with Mr. Sumit
Gahlot and Ms. Padma
Priya, Advs.
Versus
ANDHRA EXPRESSWAY LIMITED ..... Respondent
Through: Mr. Sumeet Lal, Adv.
Coram:
HON'BLE MR. JUSTICE VIKRAMAJIT SEN
HON'BLE MR. JUSTICE A.K. PATHAK
1. Whether the Reporters of local papers may
be allowed to see the judgment? Not necessary
2. To be referred to Reporter or not? Not necessary
3. Whether the judgment should be reported
in the Digest? Yes
A.K. PATHAK, J.
1. Appellant assails the judgement dated 29th January,
2010 passed by the learned Single Judge whereby objections
under Section 34 of the Arbitration and Conciliation Act,
1996 (for short hereinafter referred to as A & C Act) against
the award dated 14th September, 2009 passed by the Arbitral
Tribunal, have been dismissed.
2. The brief background of the case, leading to the
passing of the impugned order, is that the Respondent was
incorporated by a consortium of M/s. Gammon India Ltd. &
Punj Llyod Ltd., the two joint venture partners. Respondent
entered into a Concession Agreement (hereinafter referred
to as "Agreement") with the Appellant on 30th October, 2001
for the work of strengthening the existing two lane
carriageway between Dharamvaram and Tuni from 253
Kilometers to 300 Kilometers, on N.H. 5 in the state of
Andhra Pradesh and for widening thereof to four lanes dual
carriageway. The concession period was to start from 30th
May, 2002 and end on 29th November, 2019. As per the
Agreement, Respondent was to construct the carriageway
within the stipulated period and had to operate and maintain
the same thereafter. In return, the Respondent was to
receive Annuity to the tune of Rs.279.12 million on each
Annuity Payment Date as specified in Schedule „J‟ of the
Agreement. The first instalment of Annuity payment was to
be released to the Respondent on 30th May, 2005.
Agreement envisaged appointment of an Independent
Engineer for supervision and monitoring of the contracted
work, carried out by the Respondent. M/s. Zaidun Leeng
SDN. BHD-Acrtefact Projects (JV) was appointed as the
Independent Engineer. In addition to the payment of
Annuity under Article 8 of the agreement, Respondent was
also entitled to bonus if project was completed before the
stipulated date, that is, 29th November, 2004, as certified by
the Independent Engineer. Bonus amount was to be
determined on the basis of a formula, as contained in clause
8.3 of the Agreement.
3. During execution of the project, there were delays and
hindrances at various stages, inasmuch as, the project sites
were not handed over to the Respondent in time even
though, the same was Appellant‟s obligation as envisaged
under Article 3 of the Agreement. That apart, villagers had
also obstructed the work at the sites in various stretches.
Inspite of these obstructions, delays and hindrances,
Respondent succeeded in completing almost the entire
construction work by July, 2004, except with respect to the
certain parts of the Project Sites, which were not handed
over to it by the Appellant. Under the Agreement it was
open to the Independent Engineer to issue Provisional
Certificate to the Respondent if the project facilities could be
opened for commercial operations notwithstanding the fact
that certain incomplete items of work referred to as "Punch
List" items were not complete. More over according to the
Agreement the date of issue of such certificate was deemed
to be the Commercial Operation Date (COD).
4. By a letter dated 16th July, 2004 Respondent requested
the Independent Engineer for its concurrence for exclusion
of incomplete work from COD requirement. Said request had
to be made as payment of annuity could not have
commenced from 30th May, 2005 i.e. first Annuity Payment
Date, resulting in Respondent being unable to repay
outstanding loans taken by it, inasmuch as, the Appellant
would have also incurred liability to extend time for
completion of project work, thus pay bigger amount of bonus
later because of delay, as the „X‟ factor in the formula for
determination of bonus would have become operative. In
these circumstances, keeping in mind the far reaching
ramifications that would have ensued on both the parties, a
supplementary agreement dated 12th May, 2005 was
executed between Appellant and the Respondent whereby
incomplete part of work was delinked from the COD
requirement and pursuant thereof a Provisional Certificate
was issued.
5. On delinking the incomplete work by 30th October,
2004, road was ready for commercial operations; meaning
thereby that COD had been achieved thirty days prior to the
Stipulated Project Completion Date (SPCD) which was 29th
November, 2004. On 6th May, 2005, Respondent requested
the Independent Engineer to issue a Provisional Certificate
and also approve Respondent‟s invoice in terms of clause 8.5
(a) of the Agreement and also requested the Appellant to pay
first annuity of Rs.279.12 million along with bonus of Rs.
4,65,20,000/- for achieving the COD on 30th October, 2004.
6. Appellant communicated its approval to the
Independent Engineer on 13th May, 2005 for issuing a
Provisional Certificate with effect from 30th October, 2004.
In turn, Independent Engineer issued a Provisional
Certificate dated 14th May, 2005 mentioning COD as 30th
October, 2004. In spite of issuance of Provisional
Certificate, Appellant did the not pay bonus amount.
Consequently, Respondent invoked arbitration proceedings
in terms of Article 17.1 of the Agreement. Respondent
appointed Hon‟ble Mr. Justice G.T. Nanavati. Former Judge,
Supreme Court of India; whereas Appellant appointed
Lieutenant General Y.P. Khurana (Retired) as its Arbitrator.
Two Arbitrators then appointed Justice A.M. Ahmadi, Former
Chief Justice of India as the Presiding Arbitrator. Three
Arbitrators constituted an Arbitral Tribunal, which published
its Award on 14th September, 2009 thereby directing
Appellant to pay Rs.4,65,20,000/- as bonus to the
Respondent for early completion of the work together with
interest @ 9% per annum with effect from 30th May, 2005 till
the awarded amount was paid by the Appellant along with
cost of arbitration amounting to Rs.5,00,000/-.
7. The question raised before the Arbitral Tribunal was
whether Respondent was entitled to claim bonus for early
completion of work or not.
8. Before the Arbitral Tribunal Respondent contended
that the work was to commence from 30th May, 2002 and to
be completed on 29th November, 2004 in terms of the
Agreement dated 30th October, 2001. The first date of
payment of annuity was 30th May, 2005. For the reasons
beyond the control of either party to the contract, certain
items of work could not be completed before SPCD,
therefore, both the parties, in terms of Article 19.7 of the
Agreement, entered into Supplementary Agreement on 12th
May, 2005 to provide for various situations which were not
foreseen by the parties at the time of signing the Original
Agreement dated 30th October 2001. By virtue of
Supplementary Agreement certain terms in the main
contract were modified and it was decided to delink certain
items which could not be completed due to obstructions and
hindrances in the project work which were beyond the
control of either of the parties.
9. Relevant clauses of Article 5.4 of the Agreement reads
as under :-
"Project Implementation
(a) Construction Works
(i) xxxxxxxxx
(ii) xxxxxxxxx
(iii) xxxxxxxxx
(iv) xxxxxxxxx
(v) xxxxxxxxx
(vi) xxxxxxxxx
(vii) All Tests shall be conducted in accordance with Construction Requirements. If the Tests are successful and all parts of Project Facilities can be safely and reliably opend for commercial operation, the Independent Engineer shall issue Completion Certificate:
Provided, notwithstanding that certain works or things forming part of Construction Works are not complete, if following Tests the Independent Engineer determines that the Project Facilities can be safely and reliably opened for operations, the Independent Engineer may issue the Provisional Certificate to the Concessionaire. The Provisional Certificate shall have appended thereto a list of outstanding items signed jointly by the Independent Engineer and the Concessionaire ("Punch List"). All Punch List items shall be completed by the Concessionaire within such time as may be determined by the Independent Engineer, not exceeding 90 (ninety) days of the date of issue of the Provisional Certificate. Upon satisfactory completion of all Punch List items, the Independent Engineer, shall promptly and in any case within 15 days thereof, issue Completion Certificate.
(viii) xxxxxxxxx
(ix) xxxxxxxxx
(x) The Project shall be deemed to be completed and open to traffic only when the Provisional certificate or the completion is issued
by the Independent Engineer in accordance with the provisions hereof".
(Emphasis Supplied)
10. Clause 3 of the Supplementary Agreement reads as
under:
"3. That in consideration of the following items, having been de-linked by the NHAI from the COD requirement, the concessionaire shall not claim additional time, additional annuity or bonus for the delays like delay in delivery of the sites, stoppages of construction works by villagers etc., and that they shall complete all the remaining works with due expedition as per provisions and as and when the site is made available after the COD, issue of Provisional Certificate.
(a) xxxxxxxxxxx
(b) xxxxxxxxxxx
(c) xxxxxxxxxxx
(d) xxxxxxxxxxx
11. In view of the supplementary agreement, Provisional
Certificate was issued on 14th May, 2005 by the Independent
Engineer mentioning therein the date of completion of
project as 30th October, 2004 which was prior to the SPCD,
i.e. 29th November, 2004. The work was completed one
month prior thereto; thereby making Respondent available to
the benefit of bonus in terms of clause 8.3 of the Agreement
read with Supplementary Agreement.
12. As per the Appellant, as the project work was not
completed in all respect, therefore, Respondent was not
entitled to bonus in terms of the Agreement only on the basis
of a Provisional Certificate in spite of the Supplementary
Agreement. Respondent was entitled to bonus, had it
completed the entire project before the stipulated SPCD.
13. After scrutinizing the relevant clauses of the
Agreement as well as Supplementary Agreement Arbitral
Tribunal concluded as under:
"16. This provision of the contract and the above formula make it clear that early completion of the Project i.e. SPCD-COD and positive „X‟ factor because of delays mentioned in that provision would entitle the Concessionaire to get bonus. In this case bonus is not claimed on the basis that there were delays of the type entitling the Concessionaire to get the Bonus. It is claimed because the claimant/concessionaire was able
to complete the project work before SPCD. As stated earlier the project work was successfully completed by the claimant over the site which were made available to it. It was not possible for the respondent to hand over other sites to the claimant. As the whole project work was not completed, the Independent Engineer could not have issued Completion Certificate, in absence of which the claimant would not have got his request for payment of Annuity processed by the Respondent and would have suffered financial difficulties. The Respondent would have incurred liability to extend time for completion of the Project and also pay more bonus because of the delay which was likely to be caused. Thus a situation had arisen for both the parties to find some solution and as the Supplementary Agreement states it was decided to de-link the incomplete part and provide for it separately. Article-(iii) of the Supplementary Agreement if read carefully makes it clear that in consideration of de- linking the incomplete works from COD, the claimant gave up its right to claim additional time for the delays referred to in that Article and also the higher amount of bonus. It is a matter of fact that there was considerable delay of the type contemplated by Article (iii)
and even when Provisional Certificate was granted, some obstructions and hindrances still existed. The claimant was not responsible for the delay and he could not have completed the work because of those obstructions and hindrances. That would have entitled the claimant to ask for extension of time and other consequential entitlements including more bonus. It was this benefit which the claimant gave up. It had not given up the right accrued to get bonus which had accrued earlier on early completion of the project work. In our opinion, this is the correct reading of that article and therefore the contention raised by the learned counsel Mr. Ramaswamy has to be rejected as misconceived as it is based upon misreading of that article."
(Emphasis supplied)
14. Learned Single Judge was of the view that the Arbitral
Tribunal had rendered findings after construing the merits of
the case and scrutinising the relevant clauses of the
Agreement read with Supplementary Agreement and that no
manifest error or perversity could be found therein; that the
interpretation put by the Arbitral Tribunal on the relevant
Clauses of Agreement and Supplementary Agreement was
justified, equitable and valid interpretation of the said
Clauses. Hence the courts‟ interference was not required.
15. It was contended by the Appellant before the learned
Single Judge, by placing reliance on clauses 3 and 7 of the
Supplementary Agreement, that merely on the basis of
Provisional Certificate, Respondent was not entitled to
receive bonus, since by virtue of Clauses 3 and 7 of the
Supplementary Agreement, the respondent had relinquished
its right to claim additional annuity and bonus as contained
in Original Concession Agreement because certain items of
work remained incomplete. Learned Single Judge negated
this argument on the ground that in a commercial contract
such as the present one, on the commencement of the toll
road, on issuing of a Provisional Certificate, Appellant
started earning toll from the road built by the Respondent.
Road became operational and toll started flowing resulting
earnings to the Appellant rendering corresponding benefit to
the Respondent as well. Learned Single Judge, inter alia,
observed as under:
"Keeping in view the aforesaid parameters, I do not find any illegality or violation of the contractual provisions or any perversity by the Arbitration Tribunal. The
interpretation put by the Arbitration Tribunal on the clauses of the Supplementary Agreement is a justified, equitable and valid interpretation of the clauses of the Supplementary Agreement. In any case the interpretation is one plausible interpretation of a reasonable person, such interpretation cannot be interfered with while hearing objections to an Award under Section 34. In fact, I find the opposition of the petitioner to be very surprising because I cannot understand how the petitioner can claim commercial benefits from an earlier completion of the contract but deny the commercial benefits to the contractor for early completion viz the bonus payable for early completion. The scales of justice in commercial contracts of this nature, in my opinion, have been very evenly balanced by the Arbitrator and I do not find any fault whatsoever in the Award."
16. Arguments advanced by the Appellant before the
learned Single Judge have been reiterated before us but we
are not convinced with the same. The scope of interference
by the court under Section 34 of the A & C Act is very
limited. Unless the action of the Arbitrator is illegal, that is,
it is beyond the law of the land or that the same is beyond
the contractual provisions or that the findings/conclusions
are so perverse which shocks the judicial conscience, award
cannot be interfered with. In other words, if the action of
Arbitrator is illegal the court would interfere with an award.
The court does not sit as an Appellate Court over the
findings and conclusions of the Arbitrator and if two views
are possible, the court will not interfere with the award
merely if it is of another view than the view taken by the
Arbitrator. There is no doubt in mentioning that the
Arbitrator is entitled to interpret the relevant clauses of the
contract. Unless there is gross perversity in such
interpretation, the court would refrain itself from the
interfering in the award in exercise of its jurisdiction under
Section 34 of the A & C Act.
17. In Delhi Development Authority vs. R.S. Sharma and
Company, New Delhi, reported in (2008) 13 Supreme Court
Cases 80, it was held that interference by the court under
Section 34(2) of the A & C Act is open only if an award is (i)
contrary to substantive provisions of law; or (ii) the
provisions of the Arbitration and Conciliation Act, 1996; or
(iii) against the terms of the respective contract; or (iv)
patently illegal; or (v) prejudicial to the rights of the parties;
the award could be set aside if it is contrary to: (a)
fundamental policy of Indian law; or (b) the interest of India;
or (c) justice or morality. The award could also be set aside
if it is so unfair and unreasonable that it shocks the
conscience of the court.
18. In the backdrop of above settled legal position, we
have examined the award and do not find any perversity
therein. Facts are not in dispute. Concession Agreement
was entered into on 30th October, 2001; work was to
commence from 30th May, 2002 and was to be completed on
29th November, 2004. Majority of the substantial work was
completed on 30th October, 2004, i.e., much prior to the
stipulated date of completion of work. However, entire work
could not be done for the reasons which were beyond the
control of both the parties, inasmuch as, the site could not be
handed over by the Appellant to the Respondent in time. In
these circumstances, both the parties sat across the table
and decided to delink such incomplete items vide
Supplementary Agreement executed between the parties on
12th May, 2005, pursuant whereof a Provisional Certificate
was issued mentioning the date of completion as 30th
October, 2004, which admittedly was one month prior to the
stipulated date of completion. The said certificate was
issued by the Independent Engineer only after obtaining
approval of the competent authority. Work having been
completed prior to the stipulated date of completion
Respondent became entitled to bonus as has been held by
the Arbitral Tribunal. We do not find any perversity in the
view taken by the Arbitral Tribunal.
19. After having scrutinized the relevant clauses of the
Agreement and the Supplementary Agreement, in the facts
of this case, the Arbitral Tribunal as also the learned Single
Judge have arrived at a conclusion that Respondent was
entitled to bonus, which is a possible view. We also do not
find any justifiable reason to interfere with the same.
20. In the light of the above discussions, we find the
present appeal to be devoid of merits and the same is
dismissed.
A.K. PATHAK, J
VIKRAMAJIT SEN, J.
April 29, 2010 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!