Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Green Delhi Bqs Ltd. vs Delhi Transport Corporation And ...
2010 Latest Caselaw 1751 Del

Citation : 2010 Latest Caselaw 1751 Del
Judgement Date : 5 April, 2010

Delhi High Court
Green Delhi Bqs Ltd. vs Delhi Transport Corporation And ... on 5 April, 2010
Author: S.Ravindra Bhat
*              IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                              DATE OF RESERVE: 09.03.2010
                                                                PRONOUNCED ON: 05.04.2010
+              IA Nos.5773/2009, 5985/2009 & 7333/2009 in CS(OS) 790/2009


GREEN DELHI BQS LTD.                                                       ..... Plaintiff

                       Through: Mr. S. Ganesh, Sr. Advocate with Ms. Shally
                       Maheshwari and Ms. Megha Mukerjee, Advocates.
                                           versus

DELHI TRANSPORT CORPORATION AND ORS.                                       ..... Defendant

                       Through: Mr. Parag P. Tripathi, Mr. Anuj Bhandari and
                       Mrs. Avanish Ahlawat, Advocates.

CORAM:
MR. JUSTICE S. RAVINDRA BHAT

1.     Whether the Reporters of local papers         YES
       may be allowed to see the judgment?

2.     To be referred to Reporter or not?            YES

3.     Whether the judgment should be                YES
       reported in the Digest?

MR. JUSTICE S.RAVINDRA BHAT

*

1. The plaintiff (hereafter called "Green Delhi") sues the defendant for declaration that the Defendant's (hereafter "DTC") refusal to hand over 17 BQS sites (near the airport) to it (the plaintiff) is illegal, and a declaration that refusal of the Defendant Nos.1 and 3 to shift the 18 BQS to more convenient locations is fraudulent and illegal. The suit seeks a declaration that Green Delhi is liable to pay only Rs. 32,880/- per BQS per month, instead of the contracted Rs. 93,800/- per month. Consequential decrees for mandatory injunctions, are sought. Green Delhi seeks a decree for permanent injunction restraining DTC from taking coercive measures against it in terms of a letter dated 31.03.2009; likewise a permanent injunction to restrain the defendants from invoking and en-cashing some bank guarantees.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 1

2. Briefly, the facts are that DTC issued a global tender, on 08.01.2007, for construction of 225 Bus Queue Shelters (BQS) on Build, Operate and Transfer basis for a period of 10 years. Green Delhi bid for the project, and tendered for the venture. DTC, after evaluating the tender, issued an offer letter, on 28th May, 2007. The parties executed a Concession Agreement on 26.07.2007, which contained the terms of contract. The implementation period of the contract was 26 weeks, together with an additional period of one month. In terms of the Agreement, 225 sites were earmarked for the project, and listed in Schedule A (to the agreement). DTC could, under Article 13.1 (of the agreement) increase the number of BQS by 10% without change in the other terms. Likewise, Article 14 enabled DTC to, within one year of achieving the COD, decide to augment the project capacity upto 25% of the 225 BQS. The material terms of the Agreement, including the definition clause, are extracted below:

"ARTICLE-1 DEFI NITIONS & INTERPRETATION

1. Definitions:- In this Agreement, the following words and expressions shall, unless repugnant to the context or meaning thereof, have the meanings hereinafter respectively assigned to them:

"Accounting Year" means the financial year (Financial year for the purpose of turnover and net worth is acceptable as per the bidder‟s financial year. But the financial year for other purposes including execution/implementation/operation and maintenance of the work pertaining to this tender will be as per the DTC‟s financial year i.e. form 1st April to 31st March).

"Agreement" means this Agreement including Schedules „A‟ through „L‟ hereto, and any amendments thereto made in accordance with the provisions of this Agreement.

"Applicable Laws" means all laws, promulgated or brought into force and effect and all Rules and Regulations made and all Notifications and Guidelines issued there under by government of India, Government of Nation al Capital Territory of Delhi, MCD, DTC, Statutory Authorities and other local bodies including all judgments, decrees, injunction, writs and orders of any court of record, as may be in force and effect during the subsistence of this Agreement.

"Applicable Permits" means all clearances, permits, authorizations, consents and approvals under or pursuant to Applicable Laws, required to be obtained and maintained by the Concessionaire, in order to implement the Project and to provide the Project Facility in accordance with this Agreement.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                         Page 2
              "Arbitration Act"     means the Arbitration and Conciliation Act, 1996 and shall

include any modifications to or any re-enactment thereof as in force from time to time.

"Change in Law" means the occurrence of any of the following after the date of this Agreement.

a. The enactment of any new Indian law;

b. The repeal, modification or re-enactment of any existing Indian law; c. The commencement of any Indian law which has not entered in to effect until the date of this Agreement;

d. A change in the interpretation or application of any Indian law by a court of record as compared to such interpretation or application by a court of record prior to the date of this Agreement; or e. Any change in the rates of any of the taxes.

"COD" means the Commercial Operations Data of the Project which shall be the date on which the Independent Engineer has issued the Completion Certificate or the Provisional Certificate upon completion of construction of the Project and which shall, subject to the provisions of this Agreement, be not later than 4 weeks plus 44 weeks from the date of signing of this Agreement.

"Commencement Date" means the date on which the physical possession of first lot of 25 BQS such that BQS in each lot are at contiguous locations and location of the stretch of each lot is decided by DTC is handed over by DTC to the Concessionaire which shall not be later than 4 weeks from the date of this Agreement.

"Termination" means termination of this Agreement and the Concession hereunder pursuant to a Termination Notice or otherwise in accordance with the provisions of this Agreement but shall not, unless the context otherwise requires, include the expiry of this Agreement / Concession due to expiry by efflux of time to the Con cession Period in the normal course

"Termination Date" means the date of which the Termination Notice (as per article 16.2) has been delivered or deemed to have been delivered by a Party issuing the same to the other Party in accordance with the provisions of this Agreement.

      2.1    Grant of Concession
             a)     Subject to and in accordance with the terms and conditions set forth in

this Agreement, DTC hereby grants and authorises the concessionaire to investigate, study, design, construct, operate and maintain the Project Facility and to exercise and /or enjoy the rights to collect revenue from displaying advertisements at earmarked locations on Bus Q Shelters as set forth in this Agreement (collectively "the Concession"). The

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 3 Concessionaire shall pay prescribed Concession Fee to DTC for grant of above Concession.

Stand Fee: Any Stand fee paid by Bus operator(s) to DTC will not be part of concessionaire‟s revenue and concessionaire has no right/claim over this.

(b) The title, interest, ownership and rights with regard to Bus-Q- Shelters constructed by the Concessionaire for DTC along with fixtures/fittings provide therein shall vest with the DTC except that these will be operated and maintained by the Concessionaire during the concession period as agreed in this Agreement. Title, interest in and ownership of land remains with the land owning agency.

2.4 PROJECT SITE DTC hereby undertakes to handover to the Concessionaire physical possession of the Project Site (Bus-Q-shelters) free from encumbrance together with the necessary rights of way/way leaves for the purpose of implementing the Project in accordance with this Agreement but subject to the rights of DTC and the land owning agency. The handing over of the sites in lots of 25 BQS at a time such that BQS in each lot are at contiguous locations and location of the stretch of each lot is decided by DTC shall commerce within 30 days from the date of this Agreement. The handing over of sites shall be linked to agreed construction schedule.

Handing over/ taking over physical possession of the site (s) shall comprise the following stages:

a) Batch-wise offer of sites to the Concessionaire by DTD

b) Joint Survey by DTC and Concessionaire of each site of the batch and,

c) Preparation of site plan of each site by the Concessionaire based upon joint survey and its approval by DTC

DTC confirms that upon the Project Site being handed over pursuant to the preceding para, the Concessionaire shall have the right to enter upon, occupy and use the Project Site and to make at Concessionaire‟s costs, charges and expenses such development and improvements in the Project Site as may be necessary or appropriate to implement the Project and to provide the Project Facility subject to and in accordance with the provisions of this Agreement.

2.6 INFORMATION ABOUT THE PROJECT SITE The information about the Project Site set out in Schedule „A‟ is provided by DTC in good faith and with due regard to the matters for which such information is required by the Concessionaire. DTC agrees to provide to the Concessionaire, upon a reasonable request, any further information relating to the Project Site, which DTC may now possess or may hereafter come to possess. DTC, however,

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 4 makes no representation and gives no warranty to the Concessionaire in respect of the condition of the Project Site.

      2.7    PEACEFUL POSSESSION
             DTC warrants that:

a) The Concessionaire shall have no obligation/liability as to payment of any compensation whatsoever to whosoever for the use of Project Site or any part thereof for the project during the concession period except the payment of Concession Fee.

b) The Concessionaire shall, subject to complying with the terms and conditions of this Agreement, remain in peaceful possession and enjoyment of the Project Site during the Concession Period. In the event the Concessionaire is obstructed by any Person/ Company claiming any right, title or interest in or over the Project Site or any part thereof DTC shall, if called upon by the concessionaire, defend the Concessionaire against such claims and proceedings and also keep the Concessionaire indemnified against any direct loss or damages which the Concessionaire may suffer, on account of any such right, title, interest or charge which shall be limited to depreciated cost of the BQS.

             ARTICLE 3 Performance Security

      3.1    PERFORMANCE SECURITY

The concessionaire shall, as the Performance Security for due and punctual performance of its obligations during Construction and Operation, deliver to DTC, beofr eor at the time of the execution of this Agreement a Demand Draft for Rs.20 (twenty) million in favour of CMD, DTC. In case bidder who submitted bids for both packages is evaluated to be highest financial bidder in the both packages, then two separate demand drafts for Rs. Twenty million each as above shall be submitted in favour of CMC/DTC.

This amount shall be returned without interest to the Concessionaire 90 days after handing over of the BQS to DTC on expiry of Concession period. The performance Security shall be returned after deducting the claims if any.

ARTICLE 16 EVENT OF DEFAULT 16.1 Event Of Default Notwithstanding anything herein contained, breach by Concessionaire of the terms and conditions of the Agreement, and specifically any of the following events of default means the concessionaire event of Default.

             CONCESSIONAIRE EVENT OF DEFAULT




IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                          Page 5

Any of the following events shall constitute an event of default by the Concessionaire (Concessionaire Events of Default") unless such event has occurred as a result of a DTC event of Default or a Force Majeure Event. (1) The Concessionaire falls to commence the construction works within 30 days from the Commencement date.

(2) The Concessionaire falls to open and establish an Escrow Account within six months from signing of Concession (3) The Concessionaire falls to achieve COD within 44+4 weeks from the Commencement Date.

(4) Any representation made or warranty given by the concessionaire under this agreement is found to be false or misleading.

(5) The Concessionaire creates any Encumbrance on the Project Site/Project Facility in favour of any person.

(6) The aggregate shareholding of the members of the members of the Consortium/Sponsors falls below the minimum prescribed under Article 20.1 (x9) of the Strategic partner reduces his shareholding or withdraws before the lock in period of 5 years.

(7) The transfer, pursuant to law of either (a) the rights and/or obligations of the Concessionaire under this Agreement, or (b) all or part control of the Concessionaire except where such transfer in the reasonable opinion of DTC does not affect the ability of the Concessionaire to perform, and the Concessionaire has the financial and technical capability to perform its material obligations under the Agreement;

(8) A resolution is passed by the shareholders of the Concessionaire for the voluntary winding up of the Concessionaire;

(9) Any petition for winding up of the Concessionaire is admitted by a court of competent jurisdiction or the concession are is ordered to be would up by Court except for the purpose of amalgamation or reconstruction, provided that, as part of such amalgamation or reconstruction, the property, assets and undertaking of the concessionaire are transferred to the amalgamated or reconstructed entity and that the amalgamated or constructed entity has unconditionally assumed the obligations of the Concessionaire under this agreement and the project agreements, and provided that:

(i) the amalgamated or reconstructed entity has the technical capability and operating experience necessary for4 the performance of its obligations under this agreement and the project agreements;

(ii) the amalgamated or reconstructed entity has the financial standing to perform its obligations under this Agreement and the project agreements and has a creditworthiness at least as good as that of the Concessionaire as at the Commencement Date; and

(iii) this Agreement remains in full force and effect.

(10) the Concessionaire suspends or abandons the operations of the project without the prior consent of DTC, provided that the Concessionaire shall be deemed not to have suspended abandoned operation if such suspension/ abandonment was (j) as a result of Force Majeure Event and is only for the

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 6 period such Force Majeure is continuing, or (ii) on account of a breach by DTC of its obligations under this Agreement;

(11) the Concessionaire repudiates this Agreement or otherwise evidences an intention not to be bound by this agreement;

(12) the concessionaire repudiates this Agreement of otherwise evidences an intention not to be bound by this Agreement;

(13) The Concessionaire has neglected or failed to regularity and properly maintain the Bus-Q- Shelters in clean and hygienic conditions and to keep the Bus-Q-Shelters in a state of good repair at its own cost;

(14) The Concessionaire is otherwise in material Breach of this agreement and wishes to surrender. The surrender may be accepted only for complete package of the Bus-Q-Shelters. The declaration of DTC regarding accepting the surrender shall be final and binding.

(15) Repeated non payment of salaries, wages and other dues of its employee (including employees of the contractors) including depositing PF and ESI premiums in time;

(16) The concessionaire falls to pay the concession, fee in time: (17) Non settlement of 3rd party claims on DTC as a consequence from the fault of the Concessionaire.

16.2 TERMINATION DUE TO EVENT OF DEFAULT TERMINATION FOR CONCESSIONAIRE EVENT OF DEFAULT (1) Without prejudice to any other right or remedy which DTC may have in respect thereof under this agreement, upon the occurrence of a Concessionaire Event of Default, DTC shall be entitled to terminate this Agreement by issuing a Termination Notice to the Concessionaire, provided that before issuing the Termination Notice, DTC shall be a notice in writing inform the Concessionaire of its intention to issue the Termination Notice (the "Preliminary Notice"). In case the underlying breach/default is not cured within a period of 60 (sixty) days from the date of the Preliminary Notice (Cure Period) DTC shall be entitled to terminate this agreement by issuing the termination notice. Provided further, that

(a) If the default is not cured within 30 (thirty) days of the Preliminary Notice, DTC shall be entitled to appropriate the performance security followed by issue of intimation of appropriation to concessionaire.

(b) If the default is not cured within 30 (thirty) days of issue of intimation of appropriation and a fresh performance security is not furnished within the same period in accordance with Article 3.2, DTC is entitled to issue the termination notice.

(2) The following shall apply in respect of cure of any of the defaults and/or breaches of this agreement.

(i) The Cure period provided in this Agreement shall not relieve the concessionaire from liability for damages caused by its breach or default;

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 7

(ii) The Cure period shall not in any way be extended by any period of suspension under this agreement;

(iii)If the cure of any breach by the Concessionaire requires any reasonable action by the Concessionaire that must be approved by DTC or any Government Agency hereunder the applicable cure period shall be extended by the period taken by DTC or the Government Agency to accord the required approval.

16.3. RIGHTS OF DTC ON TERMINATION Upon Termination of this Agreement for any reason whatsoever, DTC shall have the power and authority to;

(i) Take possession and control of project assets forthwith;

(ii) Prohibit the Concessionaire from entering upon the Project Assets/ dealing with the project or any part thereof;

(iii) DTC shall not be responsible for any payment due by the Concessionaire to his sub contracts/ lenders or any other agencies. All such matters have to be settled by the Concessionaire."

3. Green Delhi had caused bank guarantees, in terms of the agreement, to be issued in favour of DTC, on 22nd May, 2008 and later on 25th September, 2008. The suit contends that Green Delhi had been handed over 200 sites by DTC, for development, in early March 2008; a letter dated 24.03.2008 is relied on for this purpose. The plaintiff also alludes to a letter to DTC dated 04.03.2008, mentioning that it was agreeable to accept certain alternative sites, and listing out 80 such sites. Green Delhi contends that the DTC issued a letter on 22.05.2008 mentioning that the size of the project had been determined as 248 BQS, by invoking Article 13. DTC also stated that 195 sites were available with Green Delhi, and offered 53 to it. The list of such additional sites was attached to the letter, which requested Green Delhi to complete construction of 248 BQS by 10.07.2008. Green Delhi also mentions about a letter of 26.11.2007, issued by DTC, that the project size had been increased to 310 sites, and that 85 sites would be handed over. It is submitted that Green Delhi, in fact, took possession of 248 sites, pursuant to this representation. It is stated that project sites were to be handed over in lots of 25 each; yet, DTC failed to hand over a large number of such sites, for various sundry reasons. Green Delhi specifically underlines the alleged default of DTC in handing over 17 out of 24 sites, near the Airport, which are the most commercially viable.

4. Green Delhi narrates that on 07.05.2008, it asked DTC to hand over possession of the said 85 sites. At that stage, on 22nd May, 2008, DTC reduced the project size to 248 sites. Green

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 8 Delhi however, insisted that the original 310 sites should be handed over, to which DTC agreed. The suit mentions that again, on 27th May, 2008, DTC was reminded to hand over 85 sites. According to Green Delhi, 248 sites were constructed, out of which 200 were handed over to DTC, in good faith. Next, it is mentioned that DTC agreed to shift some sites from under flyovers, at the request of Green Delhi, which it did not do, in respect of 18 locales; mention is made of a letter dated 27th November, 2008. In this background, says Green Delhi, a meeting was held in the office of the Chief Secretary, NCT of Delhi, where it was disclosed by DTC for the first time that 17 sites were in the possession of Delhi International Airport Ltd (DIAL), which had refused to hand over them; Green Delhi mentioned in the meeting that this aspect had been suppressed from it, by DTC, at the stage of inviting bids. Green Delhi states, in the suit, that in this meeting, it was agreed as follows:

5. The plaintiff, Green Delhi, next submits that instead of complying with the terms of the understanding, DTC started demanding the outstanding concession fee of Rs. 5,03,09,713/- through its letter dated 20th January, 2009. A reference is made to several letters written to DTC reminding it about the commitment to hand over 17 sites. The plaintiff then submits about another meeting dated 03.03.2009, the minutes of which were circulated in the letter of 09.03.2009. The relevant extract of the said minutes are as follows:

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                             Page 9
 The letter also stated that:




Green Delhi states that there were lacunae in the minutes, and that it offered alternative proposals, to resolve the issue. It also asked for a meeting to discuss the issue, on 24th April, 2009, which the DTC refused. In this background, the DTC issued a preliminary notice on 31.03.2009 threatening to terminate the Concession Agreement and take coercive action. Green Delhi responded, denying the allegations, by its letter, dated 24.04.2009. In this background of circumstances, the present suit was filed. Green Delhi states that it was induced, by the DTC's representations, to invest over Rs. 75 crores, under the belief and understanding that the promised sites, 17 airport sites would be handed over. The said sites had, according to its pre-bid estimates, revenue yielding capacity to constitute 60% of its earnings through the entire contract.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 10 The default and neglect by DTC in handing over possession of those plots fundamentally altered the basis of the contract. Green Delhi relies on a project and feasibility report submitted to Yes Bank, which reveals that possession of those 17 sites was of the essence and an integral part of the contract.

6. This Court had, by its order directed that Green Delhi could pay Rs. 66,76,045/- per month towards the concession fee, instead of the full amount. On that day, i.e .01.05.2009, DTC invoked the bank guarantee. By a further interim order, dated 5th May, 2009, DTC was restrained from en-cashing the bank guarantee subject to Green Delhi paying the amount directed, according to the previous order.

7. Green Delhi argues that handing over of the 17 sites was vital for it, and an essential basis for its accepting the offer. It relies on the project report furnished to its banker, indicating that the bulk of advertising revenue was to be generated from the BQS near the Airport, as the situational advantage it offered outdid the other locations. It is argued that when Green Delhi entered into the contract, there was an understanding that the sites, including the 17 sites, would be handed over to it. DTC increased the project size to 310 sites, promising to hand over 85 sites, but did not do so, and later did not adhere to the promise to hand over these 17 vital sites. It is submitted that DTC's position, in the Court, that Green Delhi had accepted alternative sites in lieu of the 17 airport sites, is incorrect, and contrary to the record. It is also argued that in response to a query under the Right to Information Act, (RTI), that DTC had responded on 04.09.2009, conceding that its Board of Directors had increased the project size to 310 and approved the development of additional 85 sites.

8. Learned senior counsel on behalf of Green Delhi contended that the refusal or inability of DTC to hand over the most economically viable sites, which effectuates the contract, has altered the situation so drastically, that the Court should confirm the equitable order made on the first date of hearing relieving it (Green Delhi) from the obligation to pay Rs. 93,800/- per month for each BQS as concession fee, and allow it to pay a lesser amount. It is submitted that the documents and materials placed on record clarify that a diligence survey had been undertaken in respect of each of the 225 sites originally offered, which were classified (by Green Delhi) into five categories, i.e. A++; A+; A, B and C according to their estimated revenue commercial viability. Sites in A++ category were expected to fetch over Rs. 5,50,000/- per month, whereas

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 11 those in the least commercially viable category, i.e. C were expected to fetch Rs. 35,000/- per month. Invoking the doctrine Rebus sic standibus, or discharge of contractual obligations due to supervening events and circumstances, it is submitted that the failure to hand over the most commercially viable sites, undermined the very purpose of Green Delhi's offer, and the basis of the contract, which entitles the Court to make an equitable interim order, protecting its interests. Counsel submitted that Green Delhi has already invested in excess of Rs. 89 crores, and permitting the DTC to take coercive action and invoke the bank guarantee would mean that the Bus Queue Shelters would be dismantled, thus destroying the larger public purpose. Reliance was placed on the judgment reported as Old World Hospitality Ltd .v. IHC 73 (1997) DLT 374 and Pioneer Publicity Corporation -vs- Delhi Transport Corporation 103 (2003) DLT 442 for the submission that the Court can appropriately injunct the party in default, in a contract, from taking precipitate action, in its terms.

9. Green Delhi argues that the express terms of the contract, more particularly clause 16 spells out a negative covenant, which binds the DTC and prevents it from terminating the arrangement, as is sought to be done. It is argued that as events of default have been defined exhaustively, in clause 16, therefore, un-enumerated conditions cannot be the basis for determining the contract. The plaintiff consequently argues that the exceptions spelt out in Section 42 of the Specific Relief Act apply to entitle it to the injunctions sought for. Reliance here is placed upon the judgment of the Supreme Court reported as Gujarat Bottling Co. Ltd v. Coca Cola Co., 1995 (5) SCC 545.

10. It is submitted that in any event the invocation, in the present case was not in terms of the bank guarantee. As a consequence the plaintiff Green Delhi is entitled to injunction restraining its encashment. The relevant portions of the bank guarantee invocation letter, dated 01.05.2009, issued by the DTC are as follows :

"Dear Sir,

A. By the letter of award No.Sr.Mgr (Civil)/07/65 dated 28.05.2007 issued by DTC to lead partner, M/S Jindal Stainless Ltd. (a company incorporated under the company act, 1956) having its registere office at O.P. Jindal Marg, Hissar, Haryana and Head Office at 12-Bhikaji Cama Place, New Delhi-110066, the consortium was granted the construction of 225 nos. bus queue shelters (enhanced to 248 nos. bus queue shelters on build, Operate and Transfer Basis).

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                            Page 12
        B.      The concession agreement was signed between Delhi Transport Corporation and

the concessionaire M/S Green Delhi BQS Pvt. Ltd. on 27.06.07 according to which performance guarantee equal to three times of license fee of 200 nos. bus queue shelters has been submitted by the concessionaire through above cited bank guarantees as per article 3 of the agreement.

C. That the concessionaire is not making the payment of concession fee in respect of 200 nos. bus queue shelters for which provisional COD has been granted and the concessionaire is also not offering 48 nos. bus queue shelters for COD and as such an amount of approximately Rs. 11.50 cores has become outstanding. The above acts on the part of concessionaire amounts to default as per the terms of the agreement. Preliminary notice to this effect has been issued by DTC to the concessionaire under Clause No.16.2(i) of the concession agreement. The concessionaire was requested to cure the default within 30 days of preliminary notice issued by DTC and received by the concessionaire on 31.03.09.

D. Since the period of 30 days within which the concessionaire was required to cure the default has already expired and the concessionaire has not taken any steps to cure the default, the notice for encashment of Bank Guarantee has been issued to concessionaire under Article 16.2(1)a of the concession agreement.

In view of the above, you are requested to pay the sum of Rs.6,22,15,000/- through demand draft in favour of CMD, Delhi Transport Corporation immediately, as per the concessionaire has failed to discharge his obligation under the concession agreement."

11. In this connection, learned counsel for the Green Delhi relies upon the judgment reported as Hindustan Steel Works Construction Limited v. Tarapur & Co., AIR 1996 SC 2268. It is argued here that the competent authority empowered to invoke the guarantee has not done so and besides letter, dated 01.05.2009 nowhere states that the plaintiff had failed to meet its performance/ obligation in terms of the concessional agreement during the implementation period. Green Delhi submits that since the fulcrum of the contract was based on the number of sites, particularly those with revenue generating capacity being handed over by DTC, an eventuality, which did not occur, irretrievable injustice would ensue and visit the plaintiff if the DTC were allowed to en-cash the bank guarantees.

12. DTC, in its written statement, as well as in the reply to the temporary injunction application (I.A. No. 5773/2009, 5999/2009) as well as in the application for vacation of the interim order (IA 7333/2009) submits that since Green Delhi was the highest bidder for the

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 13 contract and its terms was acceptable the concession agreement was entered into; for a tenure of 10 years. Schedule K of the agreement prescribes the concession fee payable by the plaintiff (the concessionaire) during the tenure. DTC submits that although the agreement was for 225 BQS yet under Article 13 the number could be increased or decreased by 10% without change in other conditions. It is submitted that as per the agreement, sites for 225 BQS were given to Green Delhi; during the implementation period. However, 53 sites could not be made available because of the development work in the area. DTC submits that it exercised the option and increased the number of BQS to 248 and there was specified list of 80 sites, out of which 52 were handed over to Green Delhi. DTC concedes that 200 sites had been made operational and were being used, for which a concession fee of Rs.93800/- per BQS per month was being paid.

13. It is submitted that 48 BQS were also ready in January 2009 but were not operationalised deliberately, which resulted in loss of revenue to it (the DTC). The DTC submits that Green Delhi for the first time raised a dispute with respect to 17 sites that were to be initially in the airport area. Such sites were not made available by the land owning agency, i.e. DIAL. Consequently Green Delhi was given alternative sites, which has resulted in the increased number of BQS at 248 as against the 225. DTC admits to a meeting in the office of the Chief Secretary, NCT of Delhi on 8.01.2009 when it was pointed out that Green Delhi was not operating 48 BQS and also not paying license fee on one pretext or the other. It also mentions about the letter dated 20.01.2009 stating that the sum of Rs.5,03,09,713/- was outstanding towards concession fee and interest in respect of 200 BQS, for which commencement of date had been granted. DTC submits that initially 172 BQS were handed over from amongst the original list of 225. An alternative list of sites were given to the plaintiff, which by letter dated 04.03.2008 showing a list of 80 BQS including the list of alternative sites against unfeasible BQS. The balance 53 sites were allotted on 22.5.2008. It is submitted that despite this being a position Green Delhi did not hand over the 48 sites in spite of their having been constructed. DTC relies upon the letter dated 27.11.2008 stating that it admitted that it contains an admission that Green Delhi had 248 BQS ready but could not proceed further due to a major credit crunch.

14. It is submitted that Green Delhi, after December 2008, for the first time started harping on non-availability of 17 sites near the airport area and how it was important for it to generate revenue. Its counter offers and proposals were not acceptable to the DTC, a position which was

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 14 expressly and clearly made known to Green Delhi. Another meeting was held and eventually, DTC issued a notice on 30.3.2009 intimating the acts of default and requiring Green Delhi to rectify them. Since the Green Delhi's reply, dated 24.4.2009 neither addressed the real issue nor assured of any remedial action, the DTC invoked the bank guarantees on 01.05.2009. It is further stated that the allegation that bank guarantees were not invoked in accordance with the terms, is denied.

15. It is argued that essentially what Green Delhi is seeking from the Court is a re-definition of the terms of the contract. In other words, the Court is asked to re-write the contract, an unworkable proposition. The learned Additional Solicitor General, appearing for DTC submits that the Green Delhi is clearly in default and has not performed what it was expected to under the contract. In the circumstances, it is not entitled to any equitable relief. Counsel relies upon the letters, dated 04.03.2008 and 22.05.2008, which clarified the understanding of both parties that the total number of sites made available were 248. That the plaintiff was satisfied with this all along is clear from the letter of Green Delhi, dated 27.11.2008, which talked about difficulties other than the handing over of the 17 airport sites. Reliance is also placed upon the letter of the Consultant RITES, dated 30.12.2008 written to DTC submitting that the 48 BQS had in fact been made ready. It was under these circumstances that the first letter, dated 20.01.2009 requesting Green Delhi to clear the outstanding amounts, was issued. A reminder was issued on 03.02.2009, to which Green Delhi in its reply, for the first time mentioned about the 17 shelters (which were also recorded in the minutes of meeting, dated 08.01.2009). The request, for altering the terms of the contract, was rejected on 09.03.2009 by the DTC. It is thus argued that, as neither the contemporaneous correspondence, nor indeed the contract mentioned the alleged essentiality of the 17 airport sites, Green Delhi cannot argue that their non-availability strikes at the root of the contract and makes them commercially unfeasible.

16. It is also submitted that the request for change was articulated for the first time, by Green Delhi, in December, 2008, when the obligation to postpone or re-schedule the monthly payments was requested, not on the ground of unavailability of the 17 airport sites, but the economic downturn. Thus, submits DTC, Green Delhi is citing a reason that had never been voiced at the contract formation stage, nor when its terms were substantially worked out, and both the parties had committed themselves to it. In these circumstances, the Court would be assuming that

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 15 handing over of such sites was an essential condition for DTC's performance of the contract, which is not so in reality, as such conclusion is unsupported by any material on the record.

17. DTC submits that Green Delhi accepted the conditions in the contract, and constructed 248 BQS, which stands established from the record. The feasibility or otherwise of the 17 airport sites, was considered before the acceptance of the alternative sites. Therefore, its argument that handing over of such sites were essential to the performance of the contract, cannot be accepted by the Court, much less in furtherance of a claim for temporary injunction restraining the encashment of an unconditional guarantee.

18. In support of the submission that the Court cannot re-write a commercial agreement entered into between the parties, DTC relies on the judgments reported as Citbank v. Standard Chartered Bank, 2004 (1) SCC 12; Polymat India v. National Insurance Co. Ltd., 2005 (9) SCC 174 and Central Bank of India v. The Hatford Fire Insurance Co. Ltd., AIR 1965 SC 1288. It is submitted that the decisions in State of Haryana v. Jage Ram 1980 (3) SCC 599 and New Bihar Biri Leaves Co v. State of Bihar, AIR 1981 SC 679 have ruled that a contracting party is not absolved of its obligations under the bargain, due to commercial difficulty or inconvenience. It is also submitted that the Concession Agreement being a commercial contract, can always be terminated, even in the absence of a specific clause or condition, authorizing one party to do so; reliance is placed on the decisions reported as Indian Oil Corporation v. Amritsar Gas Service & Ors., 1991 (1) SCC 533.

19. The following undisputed facts may be noticed, from the above discussion:

(1) Green Delhi and DTC entered into a contract on 26.07.2007. In terms of the agreement, Green Delhi contracted to build and operate 225 BQS. The agreement spelt out, exhaustively, the rights and obligations of the parties, and also contemplated various contingencies, including the situations when DTC could terminate the contract, or direct Green Delhi to take remedial action.

(2) Green Delhi had to pay Rs. 93,800/- per month as concession fee, in respect of each BQS.

(3) In terms of the Agreement, DTC had the option of increasing the project size. It is not disputed that this option was exercised.

(4) The total number of BQS sites handed over to Green Delhi was 248.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                          Page 16
 (5)     Green Delhi built and handed over 200 BQS;

(6)     Green Delhi argues that further operation of BQS, after development of the balance 48

sites, is premised on the DTC handing (to it) 17 airport sites, which are vital to the commercial viability of the entire project;

(7) DTC, on the other hand, contends that having accepted the 248 sites, Green Delhi cannot insist that such 17 sites should be handed over to it, and that it (Green Delhi) is bound by the terms of the contract to pay the agreed concession fee in respect of each BQS.

20. The controversy as to whether the handing over the seventeen airport sites, is vital and an essential condition of the contract, has to be viewed from the overall perspective. The definition clause in the contract mentions about the project site; they are listed in Schedule A. The various stipulations clarify that Green Delhi is only given the right to use and share the revenue from the BQS (with the DTC) for 10 years; under no circumstance did the parties agree that the concessionaire was to have any interest in the property. Interestingly, clause 2.6 explicitly mentioned that DTC gave "information about the Project Site set out in Schedule „A‟"...in good faith and with due regard to the matters for which such information is required by the Concessionaire." No warranty of any kind was assured. Likewise, Green Delhi has not pointed out any stipulation in the agreement, which adverts to the project report and other materials relied on by it (and submitted by it to its banker). Clause 1.3 lists out the contract, as including the Notice Inviting Tender; Request for Proposal; Bid submitted by the tenderer; Notice of award; letter of acceptance and concession agreement. It does not include any other term, or contents of any other document, which is not the subject of inter se exchange between the contracting parties. Nor does the Green Delhi establish, prima facie that at the contract formation stage, or when the Concession Agreement was signed, the parties had any understanding that some of the sites were important, and had to be delivered, to it, under any circumstance, or that their handing over was of the essence, or an essential part, of the contract. The other aspect, which the Court cannot ignore, is that the contract contains a fairly exhaustive force majure stipulation in Clause 15, which lists out various different contingencies, the happening of which would relieve parties of their obligations; it also put in a place a mechanism in this regard. In the circumstances, where the rights and obligations of the parties were clarified exhaustively by them, and they had envisioned every contingency, an argument that the fulfillment of some

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 17 conditions - to wit, the handing over of some specific sites being an essential part, or integral to the contract, is unfeasible. The Court is un-persuaded by the submission of Green Delhi that advertisement revenue from the 17 airport sites, or any others had been estimated to be so high (by it) that not handing over of such sites constituted a fundamental breach, relieving it of the rest of the obligations under the contract, with DTC. If such were the position, it could have been clearly provisioned in the contract; also, the document or report or some part of it, disclosing the estimated earnings from the BQS, site wise, could have been classified and made part of the contract, (by including it under Clause 1.3 or through some other device). In fact, none of the contemporaneous correspondence for the period November 2008 to March 2009 disclose that such document was adverted to.

21. It would be relevant here to recollect some of the salient facts pertaining to Green Delhi's contention. As noticed earlier, none of the contract terms mentions about the essentiality of the 17 airport sites, or other sites. It is common ground that the contract project size was increased; though the Green Delhi says that it was increased by DTC availing itself of powers under Clauses 13 and 14, to swell the BQS numbers to 310, all correspondence (save the November 2007 letter) indicate that the project size was increased to 248 sites (or 10% over 225 sites), clearly pointing to recourse to Clause 13. Green Delhi's position in its correspondence till November 2008 was that 200 sites had been developed and operated; it had also concurred for the shifting of some sites to alternative locales. All this while, there was no mention about the omission to hand over 17 sites. Indeed, the two letters of Green Delhi (in November and December, 2008) mention about other reasons, but significantly do not advert to the DTC's default or omission to hand over the said 17 airport sites. In these circumstances, a meeting (on 09.03.2009) was held, the minutes of which were drawn - a copy of which is placed on the record. Here, Green Delhi asserted that without the DTC handing over the said 17 sites, it was not prepared to pay the outstanding liability towards the concession fees. DTC's position was that there was no question of Green Delhi defaulting in such payment, or stating that such sites were to be handed over as a precondition for payment of the concession fee liabilities. Further inter se correspondence appear to emphasize these positions.

22. An important principle of interpretation of documents is that if parties enter into written agreements, that contain express stipulations, the Court would ordinarily desist from extending

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 18 them (such conditions) through implication. The general presumption in such cases is that having expressed some terms explicitly, the parties have expressed all conditions by, which they intend to be bound under the instrument. (Aspdin v. Austin) 1944(5) QB 671. It was held in Luxor(Eastbourne) Ltd. v. Cooper, 1941 AC 108 that there is a presumption against adding to terms in a contract or other documents drawn up containing several subject matters. It was held:

"the general presumption is that the parties have expressed every material term which they intended should govern the agreement, whether oral or in writing."

23. Another rule applied by English Courts while interpreting documents is that a term should not be implied if it is inconsistent with express terms of the instruments or its general tenor. This rule is because the implication of a term rests upon the presumed intention of the parties and that it is unlikely that they would have intended to incorporate, by implication a term which was inconsistent with one they have incorporated expressly. It was held in Lynch v. Thorne, 1956(1) WLR that:-

"...a term prima facie to be implied must, according to well-settled principles, always yield to the express letter of the bargain."

In India, in relation to functioning of companies, it was held (Ref. A. Lakshmanaswami Mudaliar v. LIC of India, AIR 1963 SC 1185) that where a particular activity has not been provided for in the Memorandum of Association, the directors cannot seek recourse to the Articles of Association to imply that such business falls within its objects.

24. In the opinion of this Court, the absence of any internal indication in the contract that some sites were to be treated as more important than others, on account of their revenue generating potential, estimated by Green Delhi, such a conclusion cannot be arrived at its mere asking. This conclusion is fortified by the circumstance that the record discloses that such a position was articulated apparently for the first time, in January, 2009; indeed when Green Delhi sought accommodation from DTC in regard to discharge of its liability towards payment of its concession fee dues, it cited the prevalent economic slowdown as the reason for such treatment, not because some sites at particular locales had not been handed over to it by DTC. The question about the said sites being essential was articulated in a letter, for the first time, on 06.02.2009. Relevant extracts of the said letter are as follows:

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 19

25. The Court is of the opinion that acceptance of such a submission, when all indications from the record are that 248 sites had been handed over to it, and 200 had been developed, would virtually result in re-writing the terms of the contract. This is the more so, since Green Delhi's argument is that since such argument would result in scaling down its liability, proportionately, having regard to the notional opportunity loss in revenue collection, entailed by the denial to hand over such 17 sites, to about Rs. 33,000/- per month, per BQS. The court does not discern any power to warrant such a direction.

26. The other argument of Green Delhi is that it had expended considerable amounts (above Rs. 80 crores) for setting up the BQS, and denial of a temporary injunction would result in irretrievable hardship not only to itself, but to third parties, particularly the travelling public. Here, the Court is mindful that Green Delhi had expressly agreed by Clause 11.2 to pay the IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 20 concession fee, in a timely manner, regardless of any dispute that may subsist or arise with the DTC. The documents on record indicate that its request to DTC to scale down, or reduce the amount of monthly concession fee, was rejected more than once. In the circumstances, prima facie, the DTC is within its rights to treat Green Delhi as in breach of the agreement (Ref Clause 16.1 (16) of the Concession Agreement), which says that non-payment of concession fee, in a timely manner, amounts to an event of default. Green Delhi does not attack this clause, or any other term in the contract. For this reason too, the Court is of the opinion that the decisions relied upon by Green Delhi, for its contention that there is a negative covenant restricting DTC from terminating the contract, for reasons other than clause 16, has no substance. There is an express condition, which authorizes the DTC to treat Green Delhi in breach if the latter delays or does not pay concession fee- a contingency which is not disputed, by it (Green Delhi) in this case. Further, the holding, in Amritsar Gas (by the Supreme Court), in the opinion of the court prima facie clarifies that such contracts are determinable, in which case, the relief of injunction would be untenable, and inappropriate. The reliance placed on Old World Hospitality and, Pioneer Publicity, in this Court's view, is inapt. In the former, the Court undoubtedly made certain general observations that the remedy of injunction is available to enjoin a party in breach from taking precipitate action in termination of the contract. In the latter decision, the Court went by the understanding that one of the contracting parties was a state agency, and therefore bound by higher standards, not to terminate a contract. These decisions have to be read in the context of the peculiar facts, and treated as informative rather than persuasive. It has been held by the Supreme Court, in Life Insurance Corporation v. Escorts Ltd., 1986 (1) SCC 264 that if the state or its agencies don the mantle of a trader, they have all the options available to those performing similar activities, in making commercial choices. Such choices would include deciding whether a contractor was in breach of his or its terms, and deserved to be treated so. Imposing additional conditions of fairness standards, available in public law, at the stage of contract performance, more so in the case of contracts of service would be subjecting the state agency to an unwarranted disability, akin to asking it to trade, with its hands tied by additional conditions - something unacceptable, as the Court would then be importing public law standards, into what are concededly private law relationships.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 21

27. The law relating to bank guarantees is well settled. In U.P. State Sugar Corporation v. Sumac International Ltd., AIR 1997 SC 1644, the Supreme Court, after reviewing the previous judgments, and the settled position in law for about two decades, reiterated that injunction can be granted only in rare and exceptional circumstances, in the following terms:

"The courts have carved out only two exceptions. A fraud in connection with such a bank guarantee would vitiate the very foundation of such a bank guarantee. Hence if there is such a fraud of which the beneficiary seeks to take advantage, he can be restrained from doing so. The second exception relates to cases where allowing the encashment of an unconditional bank guarantee would result in irretrievable harm or injustice to one of the parties concerned.

xxxxxxxx xxxx xxxx

On the question of irretrievable injury which is the second exception to the rule against granting of injunctions when unconditional bank guarantees are sought to be realised the court said in the above case that the irretrievable injury must be of the kind which was the subject matter of the decision in the Itek Corpn. Case.

xxxxxxxx xxxx xxxx

Before us, however, in the course of argument, the learned advocate for the respondent urged for the first time in this case there would be irretrievable injustice to the respondent if the bank guarantees are allowed to be realised because the appellant is a sick industrial company in respect of which a reference is pending before the board for industrial and financial reconstruction under the Sick Industrial Companies (Special Provisions) Act, 1985. The respondent contends that even if it succeeds before the arbitrator it will not be able to realise his claim from the appellant. The mere fact that a reference under the Sick Industrial Companies (Special Provisions) Act, 1985 is pending before the Board, is, in our view, not sufficient to bring the case in the ambit of the "irretrievable injustice" exception.... There can, therefore, be no presumption that the company will, in no circumstance, be able to discharge its obligations..."

28. In a previous judgment, reported as General Electric Technical Services Company Inc. v. Punj sons (P) Ltd. and Anr., [1991] 4 SCC 230, it was held that:

"20. In our considered opinion if the bank guarantee furnished is an unconditional and irrevocable one, it is not open to the bank to raise any objection whatsoever to pay the amounts under the guarantee. The person in whose favour the guarantee is furnished by the bank cannot be prevented by way of an injunction in enforcing the guarantee on the pretext that the condition for enforcing the bank guarantee in terms of the agreement entered between the parties has not been fulfilled. Such a course is impermissible. The seller cannot raise the dispute of whatsoever nature and prevent the purchaser from

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 22 enforcing the bank guarantee by way of injunction except on the ground of fraud and irretrievable injury.."

29. In U.P. Cooperative Federation Ltd. v. Singh Consultants and Engineers (P) Ltd., [1988]1SCR1124, the Supreme Court had emphasized that apart from fraud, if there was to be irretrievable injustice, injunction could be granted:

"...commitments of banks must be honoured free from interference by the courts. Otherwise, trust in commerce internal and international would be irreparably damaged. It is only in exception case that is to say in case of fraud or in case or irretrievable injustice be done, the could should interfere.."

In State of Maharashtra v. National Construction Co., [1996] 1 SCR 293, the Supreme Court

clarified the position on this aspect in the following words:

"The rule is well settled that a bank issuing a guarantee is not concerned with the underlying contract between the parties to the contract. The duty of the bank under a performance guarantee is created by the document itself. Once the documents are in order the bank giving the guarantee must honour the same and make payment ordinarily unless there is an allegation of fraud or the like. The courts will not interfere directly or indirectly to withhold payment, otherwise trust in commerce internal and international would be irreparably damaged. But that does not mean that the parties to the underlying contract cannot settle the disputes with respect to allegations of breach by resorting to litigation or arbitration as stipulated in the contract. The remedy arising ex contractu is not barred and the cause of action for the same is independent of enforcement of the guarantee.."

30. Recently, Himadri Chemicals Ltd. v Coal Tar Refining Co., 2007 (8) SCC 110, re-stated the law as follows:

"...we find that the following principles should be noted in the matter of injunction to restrain the encashment of a Bank Guarantee or a Letter of Credit:

(i) While dealing with an application for injunction in the course of commercial dealings, and when an unconditional Bank Guarantee or Letter of Credit is given or accepted, the Beneficiary is entitled to realize such a Bank Guarantee or a Letter of Credit in terms thereof irrespective of any pending disputes relating to the terms of the contract.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 23

(ii) The Bank giving such guarantee is bound to honour it as per its terms irrespective of any dispute raised by its customer.

(iii) The Courts should be slow in granting an order of injunction to restrain the realization of a Bank Guarantee or a Letter of Credit.

(iv) Since a Bank Guarantee or a Letter of Credit is an independent and a separate contract and is absolute in nature, the existence of any dispute between the parties to the contract is not a ground for issuing an order of injunction to restrain enforcement of Bank Guarantees or Letters of Credit.

(v) Fraud of an egregious nature which would vitiate the very foundation of such a Bank Guarantee or Letter of Credit and the beneficiary seeks to take advantage of the situation.

(vi) Allowing encashment of an unconditional Bank Guarantee or a Letter of Credit would result in irretrievable harm or injustice to one of the parties concerned...."

31. In this case, the bank guarantee is an unconditional one. The plaintiff's contention is that the invocation was not in accordance with the terms of the guarantee. The relevant part of the invocation is as follows:

"C. That the concessionaire is not making the payment of concession fee in respect of 200 nos. bus queue shelters for which provisional COD has been granted and the concessionaire is also not offering 48 nos. bus queue shelters for COD and as such an amount of approximately Rs. 11.50 cores has become outstanding. The above acts on the part of concessionaire amounts to default as per the terms of the agreement. Preliminary notice to this effect has been issued by DTC to the concessionaire under Clause No.16.2(i) of the concession agreement. The concessionaire was requested to cure the default within 30 days of preliminary notice issued by DTC and received by the concessionaire on 31.03.09.

D. Since the period of 30 days within which the concessionaire was required to cure the default has already expired and the concessionaire has not taken any steps to cure the default, the notice for encashment of Bank Guarantee has been issued to concessionaire under Article 16.2(1)a of the concession agreement.

In view of the above, you are requested to pay the sum of Rs.6,22,15,000/- through demand draft in favour of CMD, Delhi Transport Corporation immediately, as per the concessionaire has failed to discharge his obligation under the concession agreement."

The relevant condition about invocation in the guarantee, reads as follows:

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 24 "...The guarantor shall, pay without demur pay to DTC....within five (5) days of receipt of a written demand thereof from DTC, stating that the Company has failed to meet its performance obligations under the Concession Agreement during the operation period. The Guarantor shall not go into the veracity so made by the DTC and shall pay the amount specified in the demand notwithstanding any direction to the contrary given or any dispute whatsoever raised by the concessionaire/ company or any other person."

As noticed earlier, clause 11.2 of the contract states that the concessionaire has to pay the concession fee agreed, without reference to any dispute: clause 16 specifically mentions that the non-payment of concession fee is an event of default. Having regard to these, the Court is of opinion that the invocation in this case, cannot be said to be contrary to terms of the guarantee. As regards the question of who has invoked the guarantee is concerned, that can, prima facie, be hardly a ground for granting temporary injunction. The DTC has in fact supported the invocation during the proceedings.

32. "Irretrievable injustice" contextually would mean a ground comparable with fraud - of the kind which would vitiate the underlying contract. It cannot mean the mere possibility of pecuniary loss, to the plaintiff, in a given case. The parties here envisioned a lot of contingencies, which were factored into the Concession Agreement. One such was that the withholding of agreed amounts of concession fee by the concessionaire (i.e. Green Delhi), was an event of default on its part. In this case, Green Delhi has been unable to establish that handing over of the airport sites was an essential condition of the contract. It argues, again unsuccessfully, that the Court should scale down the concession agreed to be paid under the contract. The terms of contract have not been shown to be oppressive, nor prima facie, the result of mistake or misrepresentation. Therefore, that payment of such concession fee amounts to a serious business inconvenience or economic hardship would not transform the situation into one of irretrievable hardship, for the plaintiff Green Delhi.

33. In view of the above conclusions - of necessity, the prima facie kind, since parties are yet to adduce evidence, the Court is of opinion that the temporary injunction sought by Green Delhi cannot be granted. The interim order subsisting till date is hereby vacated; Green Delhi shall ensure that the balance amount constituting the difference between the amounts paid in terms of the interim orders of this Court, and what is payable to DTC, under the contract, are paid to the latter, as a measure of restitution, within eight weeks from today. The applications, I.A. No.

IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009 Page 25 5773/2009, 5999/2009 are dismissed, but subject to compliance by Green Delhi, of the above terms. IA. 7333/2009, is, for the same reasons, allowed.

A copy of this judgment be given Dasti.

CS (OS) No.790/2009

List the suit for further proceedings on 14th July, 2010.

5th April, 2010                                              (S.RAVINDRA BHAT)

                                                                   JUDGE




IA Nos. 5773, 5895 & 7333/2009 in CS(OS) 790/2009                                 Page 26
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter