Citation : 2009 Latest Caselaw 3934 Del
Judgement Date : 24 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.APPL.84 /2009
% Date of decision: 24th September, 2009
NARESH GUPTA ....Petitioner
Through: Mr. Raman Kapur, Advocate
Versus
MUNICIPAL CORPORATION OF DELHI ... Respondent
Through: Mr Himanshu Upadhyaya with Mr Nitin
Kumar, Advocates.
AND
ARB.APPL.99/2009
SHRI ROHTAS ....Petitioner
Through: Mr. Raman Kapur, Advocate
Versus
MUNICIPAL CORPORATION OF DELHI ... Respondent
Through: Mr Himanshu Upadhyaya with Mr Nitin
Kumar, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? NO
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported NO
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. Notices of these petitions under Section 11 of the Arbitration
Act, 1996 were issued to the respondent/MCD on 3rd March 2009 and
13th March 2009 respectively. In spite of several dates, no reply has
been filed till date. In fact, on the last date i.e. 18th September 2009,
none appeared for the MCD and though the counsel for the
petitioner in both the petitions was heard, in the interest of justice,
orders were deferred. The counsel for the respondent has today
informed that he has not received the documents from the MCD as
yet and as such the replies could not be filed. Considering the nature
of the petitions, it is not deemed appropriate to defer the matters
further.
2. On a reading of the averments in the petitions, the claims, for
adjudication whereof arbitration is sought, appear to be time barred
and long dead ones. However, counsel for the petitioners has
contended that as per the agreement between the parties, the
petitioner was to make a demand for arbitration within 90 days of
"receiving the intimation from the Corporation or any officer
authorized in this behalf that the Bill is ready for payment." It is
contended that no intimation was given to the petitioner of the Bill
being ready for payment and as such the petitions are not barred by
time. Reliance in this regard is placed on Major (Retd.) Inder
Singh Rekhi Vs. Delhi Development Authority, (1988) 2 SCC 338
and on EN Veeka Construction Co. Vs. DDA 1999 (1) Arb. LR 298
(Delhi) as well as on Avinash Sharma Vs. Municipal Corporation
of Delhi 2007 (4) Arb. LR 147 (Delhi). Attention is also invited to
Section 25 (3) of the Contract Act. It is contended that the promise
by the respondent to make payment to the petitioner is found in the
Noting dated 6th September 2007 of the Executive Engineer (DEMS)
Narela Zone of the respondent to the Director CSE of the MCD,
Narela Zone. Though the said noting is not addressed to the
petitioners, it is contended that the same was in response to the
representation made by the petitioners, as recorded in the said
noting also.
3. Counsel for the respondent has contended that the petitioners
cannot sleep over their rights and that from the letter of September
2008 of the Advocate for the petitioner in both cases to the
Commissioner MCD and from letter dated 21.07.2006 of petitioner in
AA 84/2009 to the Director/CSE/MCD Narela Zone, it is evident that
the final bill had been prepared and the petitioner was aware of the
same. He has also contended that the noting dated 6th September
2007 cannot be construed as a promise by the respondent to the
petitioner. He has contended that the claims are time barred.
4. In view of the aforesaid controversy, it appears that the
question as to whether the claims are within time or not requires
investigation. The Supreme Court has in National Insurance Co.
Ltd. Vs. Boghara Polyfab Pvt. Ltd. AIR 2009 SC 170 held that the
issue of whether the claim is a dead/long barred claim or a live claim
is one which the Chief Justice/his designate may choose to decide or
leave to the decision of the arbitral tribunal. In the facts and
circumstances aforesaid of these two cases, the issue cannot be
decided without further investigation and is as such left for decision
of arbitral tribunal. The respondent shall be at liberty to set up
defence of the claims of the petitioner being barred by time before
the Arbitral Tribunal.
5. The agreement of the parties was for arbitration by the
nominee of the Commissioner, MCD. However the Commissioner
MCD has forfeited the right to appoint the arbitrator. The Petitioners
have become entitled to appointment of an arbitrator by the Chief
Justice/his designate. Mr. S.M. Chopra, Retd. Additional District
Judge is appointed as the Arbitrator to adjudicate the disputes
subject matter of both petitions. Since the claims in both the
petitions are small, the consolidated fee of the Arbitrator in both the
petitions is fixed at Rs. 30,000/- besides out of pocket expenses and
to be borne initially by the petitioner, subject to award as to costs.
The parties to appear before Arbitrator with prior appointment on
23rd October 2009.
Order be given Dasti as prayed for.
RAJIV SAHAI ENDLAW (JUDGE)
September 24th, 2009 neelam
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!