Citation : 2009 Latest Caselaw 3886 Del
Judgement Date : 22 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: September 10, 2009
Date of Order: September 22, 2009
+ Arb.P.451/2008
% 22.09.2009
Engineering Development Corporation ...Petitioner
Through: Ms. Anusuya Salwan, Advocate
Versus
Municipal Corporation of Delhi & Anr. ...Respondent
Through: Ms. Divya Kapur and Ms. Shifel Trehan, Advocates
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this petition under Section 11 of the Arbitration & Conciliation Act,
1996 ("the Act", for short), the petitioner has prayed for appointment of an
arbitrator alleging that disputes arose between the parties to the contract and
by a letter dated 12th August, 2008, the petitioner invoked the arbitration
clause. This letter was duly served upon respondent but respondent did not
take any action in pursuance of this letter. It is submitted that the original
agreement containing arbitration clause was in power and possession of
respondent, however, a copy of the arbitration clause has been produced.
2. Respondent has taken the stand that the petition was not maintainable
since there was no arbitration agreement between the parties. The
relationship between the parties was governed by the work order
No.WOEE(PR)SZ/TC/2005-0/132 dated 30th September 2005 and this work
Arb.P.451 of 2008 Engineering Development Corp. v. MCD & Anr. Page 1 Of 5 order does not contain any arbitration clause. It is stated that petitioner was
directed to attend the office of respondent and complete execution of formal
agreement within seven days of receipt of work order. The petitioner did not
comply with the conditions and the present petition was not maintainable.
3. Brief facts relevant for the purpose of deciding this petition are that the
petitioner was the successful bidder in respect of work regarding construction
of outfall drain for disposal of storm water/ waste in Devli Village in South
Zone. After petitioner became successful bidder, the work order dated 30th
September 2005 was placed on the petitioner and the petitioner was asked to
execute a formal agreement within seven days of receipt of letter awarding
the work. It is not disputed that no formal agreement was executed between
the parties. It seems that there was some stay granted by the Court in
respect of the site and the work did not proceed at all. The time period for
execution of work was extended by respondent in view of the stay from this
Court. However, petitioner did not execute formal agreement either at the
initial stage or later on. On 30th March, 2006, respondent wrote a letter to the
petitioner informing that this Court while disposing of a PIL being WP(C)
12408 of 2004 titled as Jeet Ram JNCT v JNCTD & Ors. has directed MCD to
start the work of construction of the said drain via Raju Park Sainik Farm
route. The petitioner was asked to make necessary arrangements like
mobilization of T&P, procurement of materials, etc. so that the work may be
started at site at the earliest possible as per the direction of the High Court,
Delhi. In response to this letter, petitioner wrote back to respondent that the
time stipulated for the work was over and during the course of the contract
period the petitioner suffered losses on various counts. The petitioner
informed respondent that respondent has lost right under clause 2 of the
Arb.P.451 of 2008 Engineering Development Corp. v. MCD & Anr. Page 2 Of 5 agreement for extension of time or for renewal of the contract since the
stipulated date of completion of work was over. The petitioner however stated
in its letter that it was ready to start the work only if the rates were increased
by 25%. Thus, this contract did not take off. Respondent did not agree for
enhancement of the rates and the petitioner did not start the work.
4. It is submitted by counsel for petitioner that it was not necessary that a
formal agreement should have been executed. The tender document which
was filled up by the petitioner contained an arbitration clause. Since the work
order was executed in favour of petitioner, respondent was bound by
arbitration clause as contained in the tender document. The petitioner placed
reliance on UNISSI (India) Pvt. Ltd. v Post Graduate Institute of Medical
Education & Research (2009 ) 1 SCC 107. In this case, the Supreme Court
observed that where a tender document contained an arbitration clause, by
reasons of acceptance of tender, a valid arbitration agreement is said to be
executed between the parties.
5. The arbitration clause as relied upon by petitioner has been annexed
by the petitioner along with this petition as Annexure-A. This arbitration
clause provides that it was the terms of the contract that a party invoking the
arbitration clause shall give a list of disputes with amount claimed in respect
of each disputes with the notice for appointment of arbitrator giving a
reference to the rejection by the Chief Engineer. The arbitration clause further
provides that it was a term of the contract that no person other than the
person appointed by Commissioner MCD should act as an Arbitrator. If for any
reason that is not possible the matter should not be referred for arbitration at
all.
Arb.P.451 of 2008 Engineering Development Corp. v. MCD & Anr. Page 3 Of 5
6. A perusal of letter dated 23rd April 2006 written by petitioner to
respondent shows that the petitioner told respondent to close the contract
and refund the earnest money and release the bank guarantee given for
performance of the contract. The petitioner had not raised a dispute in
respect of losses suffered by the petitioner. It is apparent that the petitioner
did not comply with the terms of the arbitration clause relied upon by the
petitioner which specifically provides that every notice of arbitration shall
specify the quantum of amount claimed and specify the list of disputes that
the amount claimed in respect of each dispute. Moreover, the arbitration
clause provides that if for any reason appointment of an arbitrator was not
done by MCD, the matter shall not be referred to arbitration at all. This clause
had come for consideration of this Court in Arbitration Petition 219 of 2008
M/s Arvind Construction Company Pvt. Ltd. Versus Union of India & Ors and
this Court observed that the parties are bound by the contract entered into
between them, including the arbitration clause and if the clause provides that
the arbitration proceedings shall be conducted only by a particular arbitrator
failing which there shall not be no arbitration, the dispute can be taken up
before ordinary civil Court and the petitioner does not have a right to get the
an arbitrator appointed through the Court under Section 11 of the Act. The
Supreme Court in Indian Oil Corporation Limited and others v Raja Transport
Private Limited (2009) 11 Scale 672 held as under:
"It is quite common for governments, statutory corporation and PSUs' while entering into contracts, to provide for settlement of disputes by arbitration and further provide that the Arbitrator will be one of its senior officers. If a party, with open eyes and full knowledge and comprehension of the said provision enters into a contract
Arb.P.451 of 2008 Engineering Development Corp. v. MCD & Anr. Page 4 Of 5 with a Govt./statutory corporation/PSU containing an arbitration agreement providing that one of its Secretaries/ Directors shall be arbitrator, he cannot subsequently turn around and contend that he is agreeable for settlement of disputes by arbitration, but not by the named arbitrator who is an employee of the other party. No party can say he will be bound by only one part of the agreement and not the other part, unless such other part is impossible of performance or is void being contrary to the provisions of the Act.
A party to the contract cannot claim the benefit of arbitration under the arbitration clause, but ignore the appointment produces relating to the named arbitrator contained in the Arbitration clause."
7. I, therefore, consider that in view of peculiar arbitration clause in case
of non appointment of arbitrator by respondent, the petitioner can approach
the civil court and this Court cannot appoint an arbitrator under Section 11 of
the Act. The arbitration clause exhausted itself the moment respondent failed
to or refused to appoint the arbitrator. The petition is hereby dismissed. No
orders as to costs.
September 22, 2009 SHIV NARAYAN DHINGRA J. rd Arb.P.451 of 2008 Engineering Development Corp. v. MCD & Anr. Page 5 Of 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!