Citation : 2009 Latest Caselaw 3850 Del
Judgement Date : 18 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb.P.118 of 2007
% Date of decision:-18.09.2009
M/S JAI PRAKASH ASSOCIATES LTD. ....Petitioner
Through: Mr. S.B. Upadhyay, Sr. Advocate with
Mr. Ashish Bansal, Mr. Pawan
Upadhyay, Mr. A.K. Singh & Mr. S.K.
Singh, Advocates
Versus
M/S NATIONAL HYDROELECTRIC POWER
CORPORATON LTD. ... Respondent
Through: Mr. Kailash Vasudeva, Sr. Advocate
with Mr. Ajit Pudussery, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported YES
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition under Section 11 of the Arbitration Act, 1996 is
for consideration. Notice of the petition was issued to the respondent
first on 20th April, 2007 for 24th July, 2007. The respondent did not
file any reply to the petition and on 24th July, 2007 sought time for
filing the reply. The request of the respondent for filing the reply was
declined and the counsels heard. The opposition orally made to the
petition was not successful and this court allowed the petition and
appointed a retired judge of this court as the arbitrator. The
respondent preferred SLP Civil No.17785/2007 to the Supreme
Court and vide order dated 11th November, 2008 the same was
allowed and the order of this court appointing the arbitrator was set
aside and the matter remitted to this court for passing a fresh order
on the petition under Section 11(6) of the Act after giving an
opportunity to the respondent herein to file its counter affidavit and
after hearing the parties. The respondent has since filed its counter
affidavit. The senior counsels for the parties were heard at length on
11th September, 2009 and by order of that date the petition was
dismissed with reasons to follow and which are recorded herein
below.
2. In the petition as preferred, there is a reference only to the
agreement dated 18th July, 1999 between the parties and along with
the petition, a copy of the said agreement only along with General
Conditions of contract containing an arbitration clause was annexed.
In the said agreement between the petitioner and the respondent, it
is inter-alia mentioned that the petitioner along with three other
parties described in the agreement as "other contracting parties"
had submitted a coordinated bid for execution of the Chamera
Hydroelectric Project Stage-II in District Chamba, Himachal Pradesh
of the respondent on turnkey basis; that pursuant to post bid
discussions, clarifications, negotiations, the respondent had agreed
to award the contract for execution of the project to the petitioner
and the other contracting parties and at the request of the petitioner
and the other contracting parties, the respondent had further agreed
that the project shall be executed on a coordinated basis, inter-alia
through three separate contracts to be signed by each contracting
party which shall be directly responsible for the supplies and/or the
portion of the works covered by each contract. The contract dated
18th July, 1999 between the petitioner and the respondent was for
the civil and certain other works. During the course of hearing, it
was informed that on the same date separate contracts were entered
by the respondent with the other three contracting parties for other
works in relation to the said project.
3. Clause 38.2 of the General Conditions of contract appended to
the aforesaid agreement is as under:-
"Any dispute or difference which may arise between the parties out of or in connection with this Contract which the parties are unable to settle amicably, shall be settled by reference to arbitration by three arbitrators. Each party shall appoint one arbitrator and the third shall be appointed by the Court of Arbitration of the International Chamber of Commerce, Paris (ICC) in accordance with the provisions of the Rules of Arbitration of the International Chamber of Commerce, Paris (ICC). The rules governing the proceedings before the arbitrators shall be those of the ICC. Save as above, the Indian Arbitration and Conciliation Act, 1996 shall govern the arbitration. The venue of arbitration proceedings shall be New Delhi, India."
4. It is further the case of the petitioner in the petition that
subsequent to the aforesaid contract, a letter dated 9thApril, 2003
was written by the respondent to the petitioner whereunder the
respondent agreed to, in the event of commissioning of the project
earlier to the agreed date, to pay incentive of the total sum of Rs.30
crores. Disputes and differences were alleged to have arisen with
respect to the payment of the said incentive. In this regard, it may
also be mentioned that out of the agreed incentive of Rs.30 crores, a
sum of Rs.10 crores was released to the petitioner as advance, to be
refunded in the event of the incentive ultimately not being due.
During the hearing, it was informed that it is the case of the
respondent that the petitioner did not become entitled to the
incentive and the respondent claimed refund of the said sum of Rs.10
cores from the petitioner. In fact, it is the contention of the senior
counsel for the respondent that this petition was filed as an
afterthought and with a malafide intention only to ward off/delay the
refund of the said sum of Rs.10 crores, when the same was
demanded by the respondent from the petitioner and the petitioner
had prior thereto neither claimed to be entitled to the incentive nor
raised any other dispute.
5. Having noticed the facts leading to the filing of the petition,
and before considering the defense/opposition of the respondent, the
scope of enquiry in a proceeding under Section 11 may be noticed.
The Supreme Court in National Insurance Co. Ltd. Vs. Boghara
Polyfab Pvt. Ltd. AIR 2009 SC 170 has held that the Chief
Justice/his designate in exercise of powers under Section 11 will
have to necessarily decide; (a) whether the party making the
application has approached the appropriate High Court; (b) whether
there is a arbitration agreement and whether the party who has
applied under Section 11 of the Act is a party to such an agreement.
It was further held that the Chief Justice/his designate may choose to
decide or leave the same for the decision of the Arbitral Tribunal; (a)
whether the claim is a dead (long barred) claim or a live claim; (b)
whether the parties have concluded the contract/transactions by
recording satisfaction of their mutual rights and obligations or by
receiving the final payment without objection. It was further held
that the Chief Justice or his designate should exclusively leave for
the decision of the Tribunal; (1) whether the claim may fall within
the arbitration clause; (2) merits of any claim involved in the
arbitration. The scope of enquiry being limited as aforesaid, it is
deemed appropriate to notice the defense raised in this context.
6. The senior counsel for the respondent has contested the
petition on three grounds. Firstly, this court being not the
appropriate court i.e. not having territorial jurisdiction to entertain
the petition. Secondly, on the ground of there being no agreement
for arbitration of the disputes as to the incentive aforesaid. Thirdly, it
is contended that the petitioner is not competent to alone invoke the
arbitration clause or to approach this court.
Re. Territorial Jurisdiction.
7. The senior counsel for the petitioner has referred to Clause 5
of the General Conditions of contract, a complete copy whereof was
handed over in the court during the hearing. Sub Clause 5.2 provides
that in respect of all matters or actions arising out of the contract
the courts at Delhi/Chandigarh shall have exclusive jurisdiction.
Attention was invited to Rajasthan State Electricity Board Vs.
Universal Petrol Chemicals Ltd. (2009) 3 SCC 107 in support of
the proposition that where two or more courts have jurisdiction, the
parties can agree to vest the jurisdiction in one such court only. It
was contended that in the present case the parties had vested the
said jurisdiction in the courts either at Delhi or Chandigarh and thus
the petitioner could in its discretion invoke the jurisdiction of either
of the said two courts. It being admitted that the works to be
executed under the contract were outside the territorial jurisdiction
of this court, it was enquired as to where the contract was executed.
It was informed that the contract was executed at Faridabad. It was
put to the senior counsel for the petitioner that the parties could not
by consent vest jurisdiction in this court if it otherwise had none
under the law. The senior counsel while agreeing with the
proposition contended that the contract for payment of incentive was
"an independent contract" contained in the letter dated 9th April,
2003 (Supra) of the respondent and the same was addressed to the
petitioner at New Delhi. It was stated that certain other
correspondence also from the respondent to the petitioner was at
New Delhi and thus the cause of action had partly accrued to the
petitioner at Delhi. Reliance was also placed on Telephone Cables
Ltd. Vs. Chief General Manager, Haryana Telecom Circle
(2005) 10 SCC 294. However, in that case it was not disputed that
formal acceptance of the contract was at Chandigarh and the
payment under the contract was paid and was payable at Chandigarh
and it was in that context that it was held that the courts at
Chandigarh had jurisdiction.
8. Per contra, the senior counsel for the respondent has drawn
attention to the letter dated 23rd April, 2003 of the petitioner to the
respondent in response to the letter dated 9th April, 2003 (Supra). It
was urged that the petitioner had concealed the said letter from this
court and in fact was not entitled to any relief on this ground alone.
The said letter dated 23rd April, 2003 is addressed from the
petitioner at Chamba to the respondent at Chamba. It is contended
that the agreement with respect to the payment of incentive came
into being only on acceptance by the petitioner on 23rd April, 2003 of
the proposal of the respondent contained in the letter dated 9th April,
2003. The said acceptance was outside the jurisdiction of this court.
Reliance in this regard was placed on Bhagwandas Goverdhandas
Kedia Vs. M/s Girdharilal Parshottamdas & Co. (1966) 1 SCR
656 laying down that it was the place of the acceptance of the offer
and not of the place of making of the offer which formed part of the
cause of action. A.B.C. Laminart Pvt. Ltd. Vs. A.P. Agencies
(1989) 2 SCC 163 was also cited to contend that the parties could
not by consent vest jurisdiction in a court which under the law had
none. Reference was also made to Shree Ram Mills Ltd. Vs.
Utility Premises (P) Ltd. (2007) 4 SCC 599 to contend that the
question of territorial jurisdiction has to be gone into at this stage.
9. A reading of the letters dated 9th April, 2003 & 23rd April, 2003
would show that though the proposal for payment of incentive had
emanated from the petitioner but the terms & conditions on which
the respondent had agreed to pay commission were listed out in the
letter dated 9th April, 2003. One of the conditions stipulated therein
for advancing incentive of Rs.10 crores as demanded by the
petitioner was submission of a bank guarantee for the said amount in
favour of the respondent. The respondent by the said letter also
called upon the petitioner to contact the Engineer Incharge "for
further needful in this regard". Thus the letter dated 9th April, 2003
was a proposal only and which was accepted by the petitioner vide
letter dated 23rd April, 2003. The fact that such acceptance of the
petitioner was necessary is evident from the language of the letter
conveying the irrevocable unconditional acceptance of the petitioner
to the terms for payment of incentive. The said acceptance had
become necessary because the petitioner had first, after receipt of
letter dated 9th April, 2003 sought variation of its terms and which
was not acceptable to the respondent. The said acceptance having
been issued from and delivered outside the jurisdiction of this court,
the contention of the senior counsel for the petitioner that the
"independent contract contained in the letter dated 9th April, 2003"
fructified within the territorial jurisdiction of this court giving this
court jurisdiction to entertain this petition is meritless.
10. As far as the argument of certain correspondence having been
exchanged at Delhi, in my view the same cannot constitute the cause
of action. Each and every dealing between the parties is not part of
or constitutes cause of action. It is only such bundle of facts which it
is necessary for petitioner to prove to be entitled to relief, which
constitute a cause of action. The senior counsel for the petitioner has
not shown anything of the nature having happened in Delhi or being
required to happen in Delhi, within the territorial jurisdiction of this
court, from which it can be said that cause of action had accrued to
the petitioner against the respondent at Delhi. Reference may also
be made to the letter dated 9th May, 2006 of the respondent to the
petitioner denying the arbitrability of the petitioner's claim for
incentive. The said letter undoubtedly has been issued by the
respondent from Faridabad to the petitioner at Delhi. The contention
of the senior counsel for the petitioner was that on this account this
court would have territorial jurisdiction. However, merely because
such a letter has been issued at Delhi, perhaps owing to the same
being in response to the letter issued by the petitioner from Delhi
would again in my opinion remain a triviality not forming part of the
cause of action. I may also notice that the only averment in the
petition for invoking the territorial jurisdiction of this court is, the
venue of arbitration clause being Delhi. It is settled law that the
venue of arbitration does not govern the "court" within the meaning
of Section 2 (e) of the Act.
11. Thus it is found that this court is not appropriate court or the
court within the meaning of Section 2 (e) of the Act or the
appropriate court to entertain this petition.
12. Though the petition can be disposed of on this aspect alone but
it is deemed appropriate to deal with the other oppositions raised as
well.
Re. Arbitrability of the claim for incentive.
13. The contention of the senior counsel for the respondent is that
payment of incentive was not a part of the agreement containing an
arbitration clause; thus the dispute with respect thereto could not be
covered by the arbitration clause in the agreement. It was further
argued with reference to the clauses of the contract that the same
provided for the time for completion of the project and the letter
dated 9th April, 2003 does not vary/alter any of the terms or
conditions of the agreement containing an arbitration clause for the
letter dated 9th April, 2003 to form part/subject matter of the said
agreement.
14. Per contra, the senior counsel for the petitioner has urged that
the arbitration clause as set out herein above is very wide containing
the expressions "out of", "in connection with" and the claim for
incentive was in connection with the contract and thus was
arbitrable. Reliance was placed on Olympus Superstructures Pvt.
Ltd. Vs. Meena Vijay Khetan (1999) 5 SCC 651 (para 30) where
the Supreme Court held the matters connected with the subject
matter of the main agreement to be also arbitrable in terms of the
arbitration clause contained in the main agreement. Attention was
also invited to Clause 2.5 of the General Conditions of contract
whereunder the Engineer Incharge is entitled to issue instructions
directing the manner in which the works are to be carried out. It was
urged that it cannot be argued that the disputes arising out of such
directions of the Engineer Incharge would not be arbitrable.
15. The senior counsel for the respondent contended that the
reliance by the petitioner on Olympus Superstructures Pvt. Ltd.
(Supra) is misconceived. Attention was invited to the arbitration
clause and the facts in that case to contend that therein arbitration
was agreed not only of disputes by virtue of the agreement but even
otherwise as to any other matter in any way connected with or in
relation to the subject matter of the agreement. It was further urged
that the court had in that case found the disputes and payments to
be integrally connected and overlapping with the main agreement.
It was urged that it is not so in the present case.
16. The expression "out of" or "in connection with this contract"
used in Clause 38.2 (supra) of the General Conditions of Contract
can only refer to a dispute of difference arising out of or in
connection with the contract executed between the parties. The said
contract admittedly did not provide for any incentive for
commissioning of the project before the agreed date. Thus it cannot
be urged that the aforesaid expression in the arbitration clause
would apply to all disputes which may arise between the parties with
respect to the project. The same can have reference/relevance only
to the disputes arising out of the terms and conditions of that
contract. That contract did not at all provide for any incentive for
commissioning before the scheduled date and thus it cannot be said
that the dispute between the parties as to the entitlement, if any, of
the petitioner to incentive could have been agreed by the parties to
be referred to arbitration. The principles of interpretation of an
arbitration agreement are the same as of any other contract. What
has to be determined is whether the parties can be said to have been
ad idem. In the absence of anything in the contract as signed on 18 th
July, 1999, qua incentive, it cannot possibly be said that the parties
could have intended to arbitrate on the claims qua incentive.
17. The agreement for incentive came into being between the
parties only pursuant to letters dated 9th April, 2003 & 23rd April,
2003 (supra). The Agreement for incentive is thus an independent
agreement, as also repeatedly urged by the counsel for the
petitioner, i.e. independent from the contract signed in 1999. What
has to be thus determined is whether the parties intended to
incorporate the arbitration clause contained in their agreement of
1999 in their agreement of 2003 qua incentive, relating to the same
project.
18. The first thing to be noticed is that the terms and conditions
contained in the letters dated 19th April, 2003 and 23rd April, 2003
are self contained agreement qua incentive and are not dependent
upon the agreement of 1999. In fact in the letter dated 9 th April,
2003 of the respondent it is expressly stated that the proposal for
incentive was "without altering the terms of the contract" of 1999.
The parties in the agreement of incentive contained in the aforesaid
letters did not even depend upon the agreement of 1999 for defining
the scheduled date of completion. The said letters contain the dates
also, on achieving completion whereon the incentive would be
payable. The manner of payment of incentive is also contained in the
said letters and an independent bank guarantee was sought to be
furnished for the advance against the incentive. The agreement
borne out of the said letters is a supplementary or additional, or
subsidiary or subsequent or later contract to the contract of 1999
providing for arbitration. There is no statement in any of the said
letters that "other terms and conditions shall be as per the
agreement of 1999". I thus do not find any intention of the parties to
incorporate the arbitration clause in the main contract in such
supplementary contract.
19. A similar question had arisen in Seth Thawardas Pherumal
Vs. Union of India AIR 1955 SC 468. There also the claim was
grounded not on any clauses of the contract nor implied in the
contract but on a collateral promise evidenced not by the contract
but by two letters written by the department. The Supreme Court
held that the claim on such a subsidiary contract could not be said to
be arising out of a contract to which the arbitration clause applied.
Lord Macmillan in Heyman Vs. Darwins Ltd. 1942 AC 356 was
referred to in support of the proposition that if the parties chose to
add a fresh contract in addition to the old then the arbitration clause
cannot cover the new contract.
20. In Umraosingh & Co. Vs. State of Madhya Pradesh AIR
1976 MP 126 the facts also were identical. In that case also after the
execution of the agreement, a bonus was agreed to be paid for
completing the works within the stipulated time. The Division Bench
held that since in the original contract there was no provision for
bonus and since in the supplementary agreement relating to bonus
there was no provision for arbitration, the arbitration clause in the
original contract was not applicable for resolving the disputes
relating to bonus. It was held that the agreement pertaining to bonus
was an entirely independent agreement and there was nothing to
show that the arbitration clause in the original agreement got
incorporated in the agreement for bonus.
21. Even though the aforesaid two judgments are of prior to the
1996 Act, in my view the position remains the same. Section 7(5) of
the 1996 Act lays down the same test. The reference in a contract to
a document containing an arbitration clause constitutes an
arbitration agreement only if reference is such as to make that
arbitration clause part of the contract. In the present case, neither
do I find any reference in the supplementary contract qua incentive,
to the main contract nor any intent to make the arbitration clause in
the main contract part of the contract qua incentive.
22. The Supreme court recently in M.R. Engineers & Contractors Pvt Ltd Vs Som Datt Builders Ltd.
MANU/SC/1150/2009 has held that even though the contract
between the parties does not contain a provision for arbitration, an
arbitration clause contained in an independent document will be
imported and engrafted in the contract between the parties, by
reference to such independent document in the contract, if the
reference is such as to make the arbitration clause in such document
a part of the contract i.e., it must be evident that the parties
intended to incorporate the arbitration clause contained in the
document into the contract. Russell on Arbitration was quoted to
the effect that general words of incorporation are not sufficient,
rather particular reference to the arbitration clause needs to be
made to comply with the provisions unless special circumstances
exist. It was held that an arbitration clause in other document, would
get incorporated into a contract by reference only when the contract
contains a clear reference to the documents containing the
arbitration clause; the reference to the other document should
clearly indicate an intention to incorporate the arbitration clause
into the contract and the arbitration clause should be appropriate,
i.e. capable of application in respect of the disputes under the
contract and should not be repugnant to any term of the contract. It
was further held that when a contract between the parties provides
that the execution or performance of that contract shall be in terms
of another contract (which contains the terms and conditions
relating to performance and a provision for settlement of disputes by
arbitration), then the terms of the referred contract in regard to the
execution/performance alone will apply and not the arbitration
agreement in the referred contract unless there is special reference
to the arbitration clause also. Though certain other parameters were
also laid down by the Supreme Court in that case but the same are
not found relevant for the present case.
23. Russell on Arbitration, 21st Edition (i.e. of prior to the English
Arbitration Act, 1996) while dealing with a situation where a
contract is varied and disputes have arisen about whether the
contract as varied includes or excludes the original arbitration
agreement cites; i) EB Aaby's Rederi A/S Vs Union of India
(1974) 2 Lloyd's Rep 57 where the arbitration clause was held to be
not incorporated in the variation to the agreement for the reason of
the claims under the original arbitration agreement being required
to be made within 12 months and the variation requiring many years;
and ii) Faghirzadeh Vs Rudolf Woolf SA (PTI) Limited (1977) 1
Lloyd's Rep 630 where the arbitration clause was held to apply to
variations also for the reason of the variation being unintelligible
without reference back to the original agreement.
24. Mustill and Boyd in their work on Commercial Arbitration, 2nd
Edition opine that where one contract operates by variation or
replacement of another and only one of them contains an arbitration
clause, it is a question of construction whether disputes under both
contracts or only under one fall within the clause.
25. Applying the aforesaid tests, neither can it be said that the
subsequent agreement qua incentive is unintelligible without
reference back to the main contract, nor is the arbitration clause in
the main contract consistent with the subsequent agreement qua
incentive. The main agreement on the basis whereof the petition
under Section 11 of the Arbitration Act is filed, is between the
petitioner (in its individual capacity) and the respondent only and
relating only to the works which the petitioner alone, as one of the
members of the consortium aforesaid, was to carry out for the
project. However, the agreement qua incentive is between the
petitioner, as leader of the consortium and for and on behalf of itself
as well as other members of the consortium on the one hand and the
respondent on the other hand. Also, while the main agreement is
concerned only with the works which the petitioner was to carry out
in the entire project (and not the works which other consortium
members were required to do with respect to same project but under
different agreements with the respondent), the subsequent
agreement qua incentive is concerned with commissioning of the
project, which could only be on completion of works by other
consortium members also under their respective contracts with the
respondent. Yet also, while payments under the main agreement on
basis whereof petition is filed, were to be made by respondent to
petitioner only and were to be received by petitioner on its own
behalf only, the payment of incentive under the subsequent
agreement was to be made by respondent to all the consortium
members and advance incentive was received by the petitioner on
behalf of itself as well as other consortium members and under
authority from them.
26. For the aforesaid differences, there cannot be said to be any
intent to make the arbitration clause in the main agreement on basis
whereof petition is filed, a part of the agreement qua incentive
described by senior counsel for petitioner also during arguments as
"independent".
27. I do not thus find the dispute arising from agreement qua
incentive to be arbitrable.
Re. Locus of the petitioner.
28. The senior counsel for the petitioner in his opening
submissions had in response to a query from the court categorically
stated that the agreement for payment of incentive (disputes with
respect whereto had arisen) was between the petitioner and the
respondent only and the other contracting parties referred to in the
agreement (Supra) between the petitioner and the respondent (on
basis whereof petition is filed) were not concerned with the same.
This query was raised since the arbitration provided in the General
Conditions of contract is of International Chamber of Commerce. It
was felt strange as to why the petitioner and the respondent with no
foreign party involved would for their said dispute of incentive
provide for arbitration of International Chamber of Commerce, Paris
(ICC). In fact this query was made in the context of finding out
whether it could have been the intention of the parties that the
disputes qua payment of incentive with which the other consortium
members being foreigners were not stated to be concerned, could be
intended to be covered by arbitration of ICC.
29. However, subsequently during hearing, when letters dated 9th
April, 2003 & 23rd April, 2003 containing agreement qua incentive
were read and it was found that the same was of all the consortium
members with the respondent, it was again enquired as to how the
disputes therefrom could be covered by arbitration agreement
between petitioner & respondent only, on the contract on basis
whereof petition was filed. The senior counsel for petitioner then
drew attention to an "overall agreement" dated 18th July, 1999, i.e. of
the same day as the agreement between petitioner and respondent
and on basis whereof petition is filed and to which not only the
petitioner and the respondent but the other consortium members are
also a party. A copy of the said agreement was filed not with the
petition but along with the rejoinder to reply of respondent. The
same also provides for settlement of disputes in Clause 11 thereof as
under:-
"11.0 SETTLEMENT OF DISPUTES Any dispute or difference which may arise between the parties out of or in connection with the Agreement which the parties are unable to settle amicably, shall be settled in accordance with the provisions of Article 38 (Settlement of Disputes) of the GENERAL CONDITIONS provided that for the purposes of this Agreement in the said Article 38 of the GENERAL CONDTIONS the Owner shall be one party and all the Contracting Parties collectively acting through the leader, shall be other party. "
This agreement is signed by other consortium members also.
However the same also does not cover incentive.
30. The scheme for appointment of an arbitrator framed by this
court in 1996 requires a request under Section 11(4) or (5) or (6) to
be accompanied by the original arbitration agreement or true copy
thereof. The only agreement copy whereof was filed along with the
request in this petition was the agreement between the petitioner
and respondent only. Thus the plea/request of the petitioner is for
arbitration under that agreement only and not under the overall
agreement which surfaced for the first time in rejoinder.
31. The agreement qua incentive is found to be between parties
other than the petitioner & respondent also and who are not parties
to the arbitration agreement on basis whereof petition is filed. The
said parties are also not parties to this petition. The senior counsel
for the petitioner at this stage admitted that other consortium
members are also parties to agreement qua incentive and the overall
agreement was relied upon in this regard only. Even then the other
consortium members, even if admitted to be parties to agreement
qua incentive and contended to be arbitrable, ought to have been
impleaded as parties to this petition. They have not been so
impleaded. Neither were their particulars given in the petition as
required to be given under the scheme aforesaid. After the judgment
in SBP & Co. Vs. Patel Engineering Ltd. AIR 2006 SC 450 notice
is required to be given to all parties to arbitration and they are to be
heard.
32. Moreover, the claim for incentive if any is under an agreement
made jointly by petitioner and other consortium members, with the
respondent. The petitioner alone cannot claim under the said
agreement. The petitioner thus does not have the locus to alone
make a request under Section 11 of the Act, under such agreement.
33. I have also considered the effect of the petition, under the
arbitration clause aforesaid in the overall agreement (on basis
whereof though petition is not filed) being entitled to act as a leader
of the consortium to appoint the arbitrator. However, in my view the
same would not obviate all parties to the dispute being before this
court. The respondent can be considered to be at best an agent of
the other consortium members. An agent of a disclosed principal,
under Section 230 of the Contract Act, cannot be sued. Thus for the
petition to be covered by the arbitration clause in the overall
agreement also, the other contracting parties were required to be a
party hereto.
34. Faced with this situation, the senior counsel for the petitioner
stated that an opportunity be given to him to implead the other
contracting parties as parties hereto. No ground was found for
giving such opportunity. This court cannot guide the petitioner,
especially when the petitioner is found to have taken inconsistent
stand i.e. in the opening submissions urged that the petitioner alone
and not the other consortium members was party to the agreement
qua incentive and upon failing in the said submission wanting to
implead the other parties. It is the contention of the senior counsel
for the respondent that the petitioner had suppressed the "overall
agreement" also from this court and by such suppression in the first
round had managed to obtain an order for appointment of arbitrator.
35. There is yet another aspect of the matter. The correspondence
required under Section 11 of the Act to precede a request to Chief
Justice/his designate, is also by petitioner for itself only and not on
behalf of other consortium members. There is nothing to show that
they were in any way concerned with the dispute.
35. I, therefore, do not find any merit in the petition. Though the
order of dismissal of petition was announced in court itself on
conclusion of hearing, the senior counsel for the respondent had
pressed for costs and order with respect thereto also was reserved.
In the facts and circumstances aforesaid, costs of these proceedings
of Rs.1 lac are also awarded to the respondent against the petitioner.
RAJIV SAHAI ENDLAW (JUDGE)
September 18th, 2009 M/PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!