Citation : 2009 Latest Caselaw 3704 Del
Judgement Date : 11 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb.P.No.69 of 2009
% Date of decision:11.09.2009
HYDERABAD POLLUTION CONTROLS LTD. ....Petitioner
Through: Ms. Nitya Rama Krishanan & Mr.
Sarim Naved, Advocates.
Versus
M/S INDURE PVT. LTD. ... Respondent
Through: Mr. Atul Nigam, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? yes
2. To be referred to the reporter or not? yes
3. Whether the judgment should be reported yes
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petition has been preferred under Section 11 (6) of the
Arbitration Act, 1996. The respondent has filed the reply. The
counsels have been heard.
2. The counsel for the respondent has not disputed that this court
is the appropriate court i.e. it has the territorial jurisdiction to
entertain this petition. The counsel for the respondent has also not
disputed that the petitioner is a party to the arbitration agreement
which has been invoked and the respondent is the other party
thereto. In fact there are two agreements between the parties one
for supplies and the other for erection. The clause relating to
settlement of disputes in one of the agreements is as under:-
"48.00 Settlement of Disputes
48.1 Any dispute(s) or differences arising out of or in connection with the contract shall, to the extent possible, be settled amicably between the parties.
48.2 All unsettled disputes(s) or difference(s) arising out of or in connection with the contract shall be decided by the Engineer whose decision shall be final and binding on the parties.
48.3 Prior to the initiation of any/or arbitration proceedings permitted by this contract to resolve disputes between them, in the event a dispute arises between the Purchaser and the contractor regarding the application or interpretation of this contract (a "Dispute"), the Purchaser's Project Incharge and the contractor's representative shall use their best efforts in good faith to reach a reasonable and equitable resolution of the matter. If the Purchaser's Project Incharge and the contractor's representative are unable to resolve the matter within 30 days, either party by written notice may refer the matter for resolution by good faith negotiation between their respective senior officers with decision making power and who shall not have had substantive involvement in the matters involved in the dispute, unless the parties otherwise agree."
49.00 Arbitration
Where any dispute is not resolved as provided for in the clause 48 then the following provisions shall apply :
a) The dispute shall be referred to arbitration at the request of either party upon written notice to that effect to the other party (a "Notice of Reference") in accordance with the Arbitration Rules of Indian Arbitration and Conciliation Act, 1996 in force at the date of the agreement. Where the rules do not deal with any issue arising in connection with the conduct and/or procedure of the arbitration such issue shall be resolved in accordance with the law of the place in which the arbitration is held and GCC clause 50 shall be construed accordingly.
b) The place of arbitration shall be Delhi and the language of the arbitration shall be English.
c) The parties agree that any arbitration award shall be final and binding upon the parties and (to the fullest extent permitted by applicable law) the parties waive their right to any form of appeal or other similar recourse to a court or law.
d) The arbitration will take place before a arbitrator who shall be nominated by the Chairman of Desein Private Limited, Desein House, Greater Kailash-II, New Delhi-48.
e) Performance of the contract shall continue during any arbitration proceedings pursuant to above clause unless the Purchaser shall order the suspension thereof pursuant to GCC clause 47."
3. The provision for settlement of disputes in the other contract
except for minor inconsequential differences is the same save for the
procedure for appointment of arbitrator which is as under:-
"The arbitration will take place before a Sole arbitrator who shall be nominated by the Chairman of Desein Private Limited, Desein House, Greater Kailash-II, New Delhi 110048 and acceptable to the Contractor/Seller."
4. Disputes are stated to have arisen between the parties relating
to both the contracts; the petitioner claims a sum of approximately
Rs.20,14,575/- to be due under the supply contract and a sum of Rs.
7,41,301/- to be due under the erection contract. It is not disputed
that the petitioner invoked the arbitration clause and the respondent
communicated to the petitioner of the appointment of Mr. Y.A.
Ismail, Vice President, Desein International Pvt. Ltd. to be the
arbitrator. The petitioner approached this court with the case that
the arbitrator so appointed was not acceptable to the petitioner,
being an employee of a sister concern of the respondent and the
petitioner having no faith in his impartiality. It is further contended
that as per the agreement in one of the contracts, the arbitrator had
to be acceptable to the petitioner and the arbitrator so appointed is
not acceptable to the petitioner. The petitioner thus seeks
appointment of an impartial arbitrator.
5. The counsel for the respondent has vehemently opposed the
petition. It is his contention that the petition is pre-mature for the
reason of the petitioner having not followed the two tier procedure
agreed to for amicable settlement of disputes i.e. first of the meeting
of their named officers and then of their senior officials for equitable
resolution of the matter. It is contended that the parties had agreed
that only if the disputes cannot be resolved in the manner aforesaid
could the petitioner invoke the arbitration. It was further urged that
the petitioner had not made out any case of bias of the appointed
arbitrator and the averments in the petition in this regard are
sketchy. It was urged that this court could not remove an arbitrator
so appointed by the appointing authority based on such
apprehensions.
6. This court had found both of the aforesaid contentions also
taken in the reply of the respondent to be baseless and for this
reason only, at the outset suggestion was made for appointment of
an independent arbitrator without taking up the time of the court.
7. The Supreme Court in M.K. Shah Engineers & Contractors
Vs. State of Madhya Pradesh AIR 1999 SC 950 though holding
the steps preceding coming into operation of the arbitration clause
to be essential, held that the same can be waived. It was held that if
one party has by its own conduct or the conduct of its officials
disabled such preceding steps being taken, it will be deemed that the
procedural pre-requisites were waived and the party at fault cannot
be permitted to set up the bar of non-performance of pre-requisite
obligation so as to exclude the applicability and operation of the
arbitration clause. Waiver in that case was found from acquiescence
in the appointment of arbitrators and participation in the arbitration.
8. I had during the hearing enquired from the counsel for the
respondent as to whether the respondent after knowing of the
disputes raised by the petitioner, invoked the amicable settlement
mechanism. The answer was in the negative. However, the counsel
for the respondent contended that since it was the petitioner which
was invoking the arbitration, it was for the petitioner to initiate the
amicable settlement procedure. However, without entering into the
said controversy, I find the respondent to have by its conduct of
appointment of the arbitrator, in any case waived the agreed
amicable settlement procedure preceding the arbitration. The
respondent cannot blow hot and cold. The respondent cannot on the
one hand appoint an arbitrator and oppose the petition on the
ground of the arbitrator having been appointed and the petitioner
being not entitled to challenge the appointment and on the other
hand contend that the petition is pre-mature. The conduct of the
respondent in this regard is found dilatory and malafide.
9. The counsel for the respondent faced with the above,
contended that there could be no waiver of right without the
respondent being aware that by appointing the arbitrator, it was
waiving the right of amicable settlement. I find the said argument to
be preposterous. The acrimony with which the petition has been
opposed in any case leads me to believe that there can be no
possibility of any amicable settlement between the parties and the
insistence by the respondent on the same appears to be dilatory.
10. Thus the petition cannot be said to be pre-mature.
11. As far as the other aspect of the matter is concerned, though
the counsel for the respondent is correct in contending that the
petitioner if had agreed to an appointment procedure cannot object
to the arbitrator so appointed, and though I further find that in such
situation the petition under Section 14 and not the petition under
Section 11 (6) is the remedy, I find that the appointment of the
arbitrator at least qua the agreement where it is provided that the
same should be acceptable to the petition is contrary to the
agreement and thus nonest.
12. The counsel for the respondent urged that this court ought to
decide whether the non-acceptance by the petitioner of the
arbitrator proposed, even under the agreement where such
appointment was subject to acceptance of the petitioner, is
reasonable or not. It was contended that in the facts of this case no
ground was made out for non-acceptance of the arbitrator. It was
however not disputed that M/s Desein International Pvt. Ltd. whose
Vice President has been appointed as the arbitrator is the sister
concern of the respondent company.
13. In my view, once it was found that under the agreed
procedure, the arbitrator proposed had to be acceptable to the
petitioner, this court need not enter into the domain of the reasons
given by the petitioner for not accepting the arbitrator proposed by
the respondent. One of the meaning of "accept" in Black's Law
Dictionary 6th Edition is "to agree to, accede to or to consent to" or
"to adopt". The nomination by the Chairman of Desein Pvt. Ltd., of
the arbitrator is in the nature of an offer which had to be accepted
by the petitioner to become an appointment of the arbitrator. The
petitioner having not accepted the said offer, no appointment of
arbitrator came into being. The clause (Supra) tantamounts to
appointment of arbitrator with mutual consent and in the absence of
such mutual consent/agreement the court becomes entitled to
appoint the arbitrator and is not required to enter into the question
of why the parties are not able to mutually agree. Again the
contentions of the respondent in this regard are found to be
farfetched.
14. Thus it is held that the appointment of the arbitrator is not in
accordance with the agreement and is in fact no appointment at all.
The court is thus entitled to appoint the arbitrator, at least qua the
contract aforesaid.
15. Undoubtedly, under the other contract the petitioner had no
say in the matter of appointment of the arbitrator and if the
petitioner has any grievance in that regard the remedy of the
petitioner is not in this petition.
16. However, considering that the claims of the petitioner under
the two contracts are not of very high value and further considering
that both contracts were with respect to the same project and there
may be certain overlapping, it was again suggested to the counsel
for the respondent that instead of the arbitrator already appointed
continuing qua one contract and an independent arbitrator being
appointed qua the other contract, as claimed by the counsel for the
petitioner, an independent arbitrator be appointed qua both
contracts. The counsel for the respondent is agreeable to the same.
Accordingly, the petition is allowed.
18. Ms. Maninder Acharya, Advocate is appointed as the arbitrator
to adjudicate the disputes, subject matter of the arbitration
agreement in both the contracts. On the basis of the claims
disclosed, the consolidated fee of the arbitrator is fixed at
Rs.40,000/- to be borne equally by the parties besides out of pocket
expenses and subject to award as to costs. The parties to appear
before the arbitrator with prior appointment on 6th October, 2009 I
was inclined to impose heavy costs on the respondent. However,
since the respondent has ultimately agreed to one arbitrator for
arbitration under both contracts and which is found economical,
expedient and in the interest of the parties, no order as to costs.
RAJIV SAHAI ENDLAW (JUDGE)
September 11th, 2009 pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!