Citation : 2009 Latest Caselaw 3610 Del
Judgement Date : 7 September, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.470/2009.
% Date of decision:07.09.2009
SHRI S.K. GARG ....Petitioner
Through: Mr. Man Mohan Singh, Advocate for
the Petitioner.
Versus
M/S SKY CITY HOTELS (P) LTD. ... Respondent
Through: Mr. Sangram Patnaik, Mr. Shante
Pandey & Ms. Bimola Irom, Advocates
for the Respondent.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? NO
2. To be referred to the reporter or not? NO
3. Whether the judgment should be reported NO
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The petitioner claiming to be a building contractor engaged by
the respondent for carrying out the construction work has filed this
application for interim measures of restraining the respondent from
getting the balance construction work done from any third party till
the measurement of the work done by the petitioner are recorded.
The counsel for the petitioner, on enquiry, had on the last date
stated that the construction works were carried out till 15th
November, 2008. Since this petition was preferred after over ten
months from the cessation of the works, no ex-parte order against
the respondent was granted.
2. The counsel for the respondent has appeared today and though
states that reply can be filed, has stated that the contract with the
petitioner was terminated on 22nd April, 2008 and w.e.f. 13th April,
2008. He also states that the construction work has since been
completed and the Haryana Urban Development Authority has on 6 th
April, 2009 already issued the Completion Certificate. The transcript
of the e-mail dated 22nd April, 2008 of termination of contract and
the photocopy of the Completion Certificate dated 6th April, 2009 are
handed over in the court and are taken on record.
3. The counsel for the petitioner on enquiry states that the
petitioner had done the work of construction till the upper ground
floor only. Though, the counsel for the respondent controverts the
aforesaid statement but from the Completion Certificate handed
over, it is borne out that the same is till the stage of laying of the
roof of the 8th floor. Thus, it appears that no purpose would be served
in directing any measurements at this stage when substantial work
has already been carried out at site.
4. The petitioner has also sought the relief of restraining the
respondent from interfering with the petitioner removing his tools,
machinery, plants, material lying at site. The counsel for the
respondent, on instructions, states that none of the machinery, tools,
plants, material of the petitioner are lying at site. In these
proceedings under Section 9 of the Act, such disputed questions
cannot be adjudicated and in view of the stand of the respondent and
long lapse of time and intervening events, this relief also cannot be
granted. It shall however be open to the petitioner to, if permissible
in law, in the arbitration proceedings claim relief in this regard
and/or as to the value of any machinery, tools, plants, material left at
site.
5. With the aforesaid observations, the petition is dismissed.
However, in the circumstances, parties are left to bear their own
costs.
RAJIV SAHAI ENDLAW (JUDGE)
September 7th, 2009 pp
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!