Citation : 2009 Latest Caselaw 3597 Del
Judgement Date : 7 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: September 01, 2009
Date of Order: September 07, 2009
+ OMP 139/2009
% 07.09.2009
M/S. SHIVA CONSTRUCTION .... Petitioner
Through : Mr. Rahul Sharma, Adv.
Versus
HINDUSTAN PERTROLEUM CONRPORATION Ltd.
... Respondent
Through: Mr. Anil Kumar Mishra with
Ms. Rashmi Sinha, Advs. for R.1
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. In this petition under Section 34 respondent has raised an
issue that the petition was barred by limitation. The arguments have
been heard only on this limited issue. The contention of the petitioner
is that the petitioner was not informed about the passing of the award
and no copy of the award as required under Section 31(5) of the
Arbitration and Conciliation Act 1996 was sent by the Arbitrator to the
petitioner and till 28th April, 2008, the petitioner was unaware of the
passing of the impugned award. The petitioner learnt about the
passing of the award only in reply to its RTI application when the
petitioner received a letter along with copy of the award dated 18th
July, 2007 on 28th April, 2008. It is submitted by the petitioner that the
petition has been filed within a period prescribed under Section 34(3)
counting it from 28th April, 2008 and is within limitation.
2. The respondent has submitted that the award was passed
by the Arbitrator on 18th July, 2007 and copy of award was sent to both
the parties by the Arbitrator. He submitted the documents of the
petitioner itself show that the petitioner was very much aware of the
award and plea of the petitioner that he learnt about the award only on
28th April, 2008 was false. The respondent pointed out to a letter
dated 5th January, 2008 written by attorney of the petitioner which
reads as under:
"Dear Sir,
You have not furnished the documents to Anguri Devi, the Partner of the firm, as per the requirements of the RTI Act, and you have written in the letter that you have passed an order on 18-07-2007. It is not true that you have sent copy of the arbitration proceedings.
The role of the arbitration should not biased/partial towards any one party. But it has been observed that you have been acting with partiality right from the beginning and also you have been acting controversially. Since you are in HPCL, you have been favouring HPCL which is wrong as per arbitration rules. You are once again requested to provide me a copy of the order immediately so that I can initiate subsequent legal action on this. You will be held responsible for any kind of delay.
Thanking you,
BL Bansal"
3. The petitioner had made query about the award on 7th
December, 2007 and in response to that query vide letter dated 28 th
December, 2007, the petitioner was informed that copy of the award
has been sent by mail to the general power of attorney, Sh.Brij Lal
Bansal by the Arbitrator under covering letter dated 18th July, 2007. It
is after this letter that the petitioner had written a letter dated 5th
January, 2008 to the respondent, corporation. The respondent,
corporation again replied to the petitioner that the learned Arbitrator
had sent the award to the petitioner on 18th July, 2007, but under Right
to Information Act another copy of the award was being sent to the
petitioner.
4. Counsel for the respondent argued that the petitioner
deliberately had been delaying the matter. The award was sent to the
petitioner, but he did not prefer objections and rather resorted to Right
to Information Act and obtained another copy of the award under Right
to Information Act and thereafter preferred objections. He submitted
that RTI application seemed to be a plan of the petitioner because the
petitioner did not file objections within time and in order to cover up
this delay, he took resort to Right to Information Act.
5. Counsel for the petitioner, on the other hand, submitted
that the petitioner was more interested in early passing of the award
and approached the High Court for change of the Arbitrator since the
Arbitrator was delaying the matter. An order was passed by this Court
on 24th October, 2007 whereby this Court refused to change the
Arbitrator and gave directions that the Arbitrator shall continue with
the arbitration proceedings without further delay. This order was
passed on 24th October, 2007 in presence of both the parties and in
case, the respondent had been aware of the passing of award by the
Arbitrator on 18th July, 2007, the respondent would have informed the
Court about passing of award. The very fact that this Court was not
informed about passing of the award shows that the petitioner and the
respondent both were not aware of the passing of the award.
6. Section 34(3) provides that the application for setting aside
an award can be made within 3 months from the date of which the
party had received the arbitral award. So the Court has to see whether
the petitioner in this case had received the arbitral award as is stated
by the learned Arbitrator. For this purpose record of the Arbitrator was
called and seen. A perusal of record would show that the stamp paper
on which the award has been typed was purchased from the treasury
on 3rd July, 2007 and was issued by the Stamp Vendor on 12th July,
2007. It is obvious that the award is not a pre-dated award. The
award is dated 18th July, 2007 and on the same day, the sole Arbitrator
posted the award to both the parties, i.e., the petitioner at its address
of 88, Jagriti Enclave, Delhi and to the respondent at its address of
Laxmi Nagar, Delhi. The Arbitrator had posted the award through
courier service DTDC on 18th July, 2007 itself and the courier receipt
has been pasted on record showing proof of dispatch. However, a
perusal of record would show that all earlier correspondence between
the parties and the Arbitrator is only through registered post with
acknowledgement due. There is no proof on record to show that the
courier was delivered to the respondent. The address in the courier
receipt is also not complete and only Shiva Construction, Delhi-92 has
been mentioned. The earlier courier receipt gives complete address of
the petitioner. Under these circumstances, a doubt arises about the
proper service of this award on the petitioner. This fact also fortified
from the order passed by the Court on 23rd October, 2007. If either of
the parties had received the award it would have been brought to the
notice of the Court that the award has already been passed. Counsel
for the respondent also did not inform the Court that the award had
been passed by the Arbitrator. It is quite possible that the petitioner
had not received the award due to incomplete address mentioned on
the envelop or due to some other reason. Though, the petitioner came
to know about the passing of the award in response to RTI application
moved by the petitioner sometime in December but the certified copy
of award was received by the petitioner only on 28th April, 2008. I
therefore consider that the period of limitation will have to be counted
form 28th April, 2008 and not from 18th July, 2007. If the period for
filing of objections by the petitioner is counted from 28th April, 2008,
the objections filed by the petitioner are within limitation. It is
therefore held that objections have been filed within period of
limitation.
7. List this matter now for arguments on maintainability of
the objections on merits on 25th November, 2009.
September 07, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!