Citation : 2009 Latest Caselaw 3546 Del
Judgement Date : 3 September, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 23, 2009
Date of Order: September 03, 2009
+ OMP No.21/2009
% 03.09.2009
M/S NATIONAL AGRICULTURAL COOPERATIVE
MARKETING FEDERATION OF INDIA LTD.(NAFED)
... Petitioner
Through : Mr. A.K. Singh with Ms. Gitanjli Suraj
& Mr. S.K. Singh, Advocates
Versus
M/S ROJ ENTERPRISES (P) LTD & ORS. .... Respondents
Through: Mr. Krishnam Venugopal with
Mr. Abir Phukan, Advocates
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
ORDER
1. By this application under Section 9 of the Arbitration and
Conciliation Act, petitioner has sought an injunction against
respondents no. 1 and 2 restraining them from selling, alienating,
transferring or creating third party interest in property no. A-8,
Saket, 45/1+2/A, Karve Nagar, Opposite Patwardhan Baug, Pune
and property of respondent no. 2 bearing house no. R-II, 8/8A,
Swapna Nagar, Pune, Maharashtra. The petitioner has submitted
that the petitioner and respondent had signed an agreement dated
23rd March, 2004 which was followed by a subsequent agreement
dated 30th April, 2004 whereunder the petitioner had advanced a
loan/financial assistance of Rs.21.02 crores to the respondent and
the respondent committed breach of the agreement by not adhering
to the terms of the agreement and an arbitral dispute had arisen
within the terms of Clause 13 of the agreement dated 24 th March,
2004 which the petitioner has invoked and the petitioner is claiming
interim relief under this petition.
2. The respondent in reply has stated that this Court has
no jurisdiction to entertain the petition since the material agreement
between the parties was dated 30th April, 2004. The MOU signed
between the parties on 28th March, 2004 in Delhi was followed by
the agreement dated 30th April, 2004 and it was this agreement
under which the financial assistance was given to the respondent
and parties acted and proceeded on the basis of this agreement.
MOU had become irrelevant. The agreement dated 30 th April, 2004
was signed at Pune. The financial assistance was given to the
respondent at Pune. The entire cause of action had taken place at
Pune and in view of Section 2(1)(e) of the Arbitration and
Conciliation Act, the petition under Section 9 was not maintainable
before this Court. It is also submitted that the respondent had filed
the petition under Section 9 before the District Judge, Pune, seeking
certain interim reliefs against the petitioner. The petitioner had filed
reply to that petition of the respondent and in view of Section 42 of
the Arbitration and Conciliation Act, the Court in Pune alone would
have the jurisdiction to entertain the subsequent petition.
3. It is not disputed that the initial MOU dated 28th March,
2004 executed between the parties was succeeded by a specific
agreement dated 30th April, 2004 executed at Pune between the
petitioner and the respondent and under this agreement, the
petitioner had agreed to finance the purchases made by the
respondent. The agreement contains detailed terms and conditions
of these finances. It is also not disputed that the money was
provided under this agreement to the respondent at Pune. No doubt
the arbitration clause even in the agreement dated 30th April, 2004
provides that in case of any dispute and differences between the
parties, the same shall be referred to Indian Arbitration Council in
New Delhi. However, a petition under Section 9 is maintainable
before a Court as defined under Section 2(1)(e) and as per Section
2(1)(e) only that Court can entertain an application under Section 9
if all the facts stated in the application were considered as facts of
the suit, the suit had been maintainable before the Court. In this
case the agreement was executed at Pune, the respondent is based
at Pune, the finance was provided to the respondent at Pune, the
breach of the agreement had taken place at Pune and the
attachment of property situated in Maharashtra is sought, thus the
entire cause of action in this case had taken place in Pune. Even if a
fraction of cause of action has taken place in Delhi, the Court of
jurisdiction under Section 2(1)(e) would be the Court at Pune and
the Court at Delhi is not the proper Court for entertaining the
application under Section 9 of the Arbitration and Conciliation Act.
4. It is also not disputed that the respondent had filed an
application under Section 9 before the District Judge at Pune on 29 th
August, 2008 much prior to the present application and this
application was entertained by the Court at Pune. It is also not
disputed that because of the dishonour of the cheque issued by the
respondent, the petitioner initiated proceedings against the
respondent under Section 138 of the Negotiable Instruments Act
before Judicial Magistrate Ist Class of Pune. Under these
circumstances, I consider that in view of Section 42 of the
Arbitration and Conciliation Act, 1996 only the Court at Pune would
have jurisdiction to entertain this petition and the Court at Delhi is
not the Court of competent jurisdiction. This petition under Section
9 is therefore hereby dismissed for want of jurisdiction. The
petitioner however, would be at liberty to prefer an appropriate
petition before the Court at Pune.
September 03, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!