Citation : 2009 Latest Caselaw 3532 Del
Judgement Date : 3 September, 2009
IN THE HIGH COURT OF DELHI AT NEW DELHI
CS(OS) 2477/1991
NATIONAL HYDRO ELECTRIC POWER
CORPN. LTD. ..... Plaintiff
Through: Mr. V.P. Dewan, Advocate.
versus
PUNJAB & SIND BANK AND ANR. ..... Defendants
Through: Mr. Pallav Saxena, Advocate for D-1.
CORAM:
HON'BLE DR. JUSTICE S. MURALIDHAR
1.Whether reporters of the local news papers
be allowed to see the judgment? No
2.To be referred to the Reporter or not ? Yes
3. Whether the judgment should be reported in the Digest? Yes
ORDER
03.09.2009
1. This suit by the National Hydro Electric Power Corporation Ltd.
(„NHPCL‟) has been filed against the Punjab & Sind Bank („Bank‟) and
M/s. Bhasin Associates Limited („BAL‟) for recovery of a sum of
Rs.29,18,850/- with pendente lite interest and future interest at the rate of
18% per annum till the recovery of the decretal amount, together with costs.
2. NHPCL awarded a contract dated 30th March 1988 in favour of Defendant
No.2 BAL for the construction of silt ejector and power channel including
escape channel at Tanakpur Hydro Electric Power Project, Nainital.
According to the Plaintiff for the smooth performance of the contract,
Defendant No.2 BAL requested its banker Defendant No.1 Bank to furnish
to the NHPCL five bank guarantees the details of which are as under:
"Bank Guarantee No. Dated Amount
(1) 24/90170/89 12.08.89 6,00,000
(2) 24/90177/89 21.10.89 3,00,000
(3) 24/90008/90 24.01.90 4,00,000
(4) 24/90082/90 06.07.90 11,00,000
(5) 24/90179/90 15.11.90 5,00,000"
3. It is stated that when BAL committed defaults in the performance of the
contract and stopped work unilaterally on 6th July 1991, a letter dated 10th
July 1991 was written by the Plaintiff to the Bank calling upon it to encash
the bank guarantees. The Bank, however, did not immediately encash the
bank guarantees within 48 hours as stipulated in Clause 2 of each of the
bank guarantees. Instead the bank wrote to the Plaintiff on 24 th July 1991
stating that they had referred the matter to their advocate for opinion. After
awaiting for 15 days, NHPCL filed the present suit under Order XXXVII
CPC on 26th July 1991 seeking the above reliefs.
4. The Defendant No.1 Bank entered appearance on 22nd October 1991 and
filed IA No. 11031 of 1991 under Order XXXVII Rule 3 for condonation of
delay in entering appearance. By this time, Defendant No.2 BAL had filed
Suit No.146 of 1991 in the Court of the learned Civil Judge, Nainital praying
inter alia for an injunction restraining the Bank from encashing the bank
guarantees in question. On 1st August 1991 the following order was passed
by the learned Civil Judge, Nainital:
"1.8.91 Case called out.
Present: Shri Bupinder Singh, Advocate.
Shri R.K. Mehrotra, Advocate For the Plaintiff.
Shri L.M. Bhatt
Shri K.C. Upraiti For defendants.
Objection 27/C alongwith affidavit 28/C filed at 3.30 p.m. Learned counsel for the plaintiff requested that status quo in respect of encashment of bank guarantee be maintained. Learned counsel for defendant stated that bank guarantees have been encashed to the best of his knowledge.
Fix 6.8.91 for disposal. Meanwhile parties shall maintain status quo in respect of bank guarantees."
5. It is not in dispute that the above suit was filed by BAL against the
Plaintiff herein as well as the Bank. Defendant No.2 BAL filed another suit
being Suit No.158 of 1991 in the court of learned Civil Judge, Nainital in
which an order dated 20th August 1991 was passed restraining NHPCL from
using the machinery and equipment belonging to BAL. Aggrieved by the
said interim order dated 20th August 1991 NHPCL filed a revision petition in
the High Court of Judicature at Allahabad which came to be dismissed on
30th August 1991. Aggrieved by the dismissal of its revision petition by the
High Court, NHPCL filed Special Leave Petition (Civil) 24807 of 1991 in
the Supreme Court. In the said case the following order was passed by the
Supreme Court on 18th September 1991:
"Special leave granted.
Heard counsel for the parties.
We are of the view that the order made by the Allahabad High Court which is impugned has to be vacated. We accordingly allow this appeal and vacate the order of the High Court.
The dispute which the respondent now raises on account of the termination of the contract has to be referred to Arbitration but we are inclined to agree with Mr. Salve that the Arbitrator should not be one contemplated in this agreement but should be a retired Judge.
We accordingly appoint Mr. Justice H.N. Seth, a retired Chief Justice of Punjab & Haryana High Court as an Arbitrator.
The Arbitrator will hear parties and make orders as to measurement of the work done by the contractor, if possible, with the assistance of a capable engineer. The work at the site shall continue without any interference and the arbitration proceedings will also continue simulatenously.
Injunction granted against the use of the Contractor‟s machinery shall be sustained as Mr. Dutta for the appellant does not want to use the same. The dispute which shall be referred would be the entire one relating to the contract and not to termination only.
No costs."
6. It appears that after the aforementioned order was passed by the Supreme
Court, BAL filed an application (No.42-C) in Suit No. 146 of 1991 in the
court of the Civil Judge, Nainital seeking stay of further proceedings in the
suit on the ground that all disputes between BAL and NHPCL, including the
issue relating to encashment of bank guarantees, had been referred to the
Arbitrator. It was prayed that the civil court should stay its proceedings till
such time the Award was not passed by the learned Arbitrator. NHPCL
opposed this application by filing an objection (numbered as 46-C). An
order dated 15th February 1992 was passed by the learned Civil Judge in the
said application in which it was noticed that the Supreme Court had referred
all the disputes between the parties to arbitration and that the arbitration
proceedings were not confined to the disputes arising in Suit No. 158 of
1991. Before the learned Civil Judge it was urged by the Plaintiff herein that
in view of the settled law explained by the Supreme Court the withholding
of the bank guarantees was not justified. However, this plea was not
accepted. The learned Civil Judge noted that the order dated 1 st August 1991
passed by the Civil Court staying the encashment of bank guarantees had not
been challenged by the NHPCL in the High Court and, therefore, remained
in force. Further, in view of the fact all the disputes between NHPCL and
BAL had been referred to arbitration, the civil court had to await the award
of the Sole Arbitrator and till such time the proceedings in Suit No.146 of
1991 was stayed. The objection petition filed by the Plaintiff herein i.e.
NHPCL was dismissed. This order dated 15th February 1992 passed by the
learned Civil Judge was not challenged by the NHPCL thereafter.
7. It appears that the proceedings before the Sole Arbitrator, Justice H.N.
Seth, the retired Chief Justice of the High Court of Punjab & Haryana, did
not conclude within the stipulated time. This led to the Supreme Court being
again approached by way of IA No. 4-6 in Civil Appeal No.6372 of 1991
seeking extension of time for the conclusion of the arbitration proceedings
and passing an Award. These applications were dismissed by the Supreme
Court on 27th August 2004. As a result, the arbitration proceedings came to
an end.
8. As far as the present suit is concerned, IA No. 2721 of 1994 being the
application for leave to defence filed by the Bank was allowed
unconditionally by this Court by an order dated 4th May 2000. The grounds
on which leave to defend was sought by the Bank were that the Civil Judge,
Nainital had by an order dated 1st August 1991 in Suit No.146 of 1991
stayed the encashment of the bank guarantees; that all the disputes between
the NHPCL and BAL including the dispute concerning the encashment of
the bank guarantees had been referred to a Sole Arbitrator, Justice H.N.
Seth; the arbitration proceedings had not concluded and lastly, by the order
dated 15th February 1992 the learned Civil Judge had stayed the further
proceedings in Suit No. 146 of 1991 till such time the Award was not made.
This Court in the order dated 4th May 2000 noted that: "there was a stay of
encashment of bank guarantees even on the date of filing of the suit and till
such time the stay is vacated the Plaintiff, in my view, is not entitled to
receive any money from Defendant No.1. This itself is sufficient to entitle
Defendant No.1 to the grant of leave to defend the suit." The order dated 4 th
May 2000 was not challenged by the Defendant.
9. As far as Defendant No.2 BAL is concerned, by an order dated 26th
February 2001 its right to file a written statement was closed. It has not been
appearing in the suit since.
10. The stand taken in the written statement filed by the Defendant No.1
Bank is a reiteration of the grounds urged by it in its application for leave to
defend. In addition, it is contended that the bank guarantees in question were
not issued by the bank in consideration of any contract between NHPCL and
BAL. It is contended that they were not performance guarantees. It was
urged that even when the first bank guarantee was issued by the bank, BAL
had carried out work to the tune of Rs.9,18,87,179/- as against the total value
of Rs.8,58,99,500. Since the value of the contract executed had exceeded
the value of the contract there was no occasion for the Bank to issue and the
NHPCL to expect any bank guarantee for "the smooth performance of the
contract." Further it is contended that the bank guarantees had not been
invoked in terms thereof. Reliance is placed on Clause 1 of the bank
guarantees where it is stated that the bank guarantee had been issued to
indemnify the NHPCL on behalf of BAL "in view of equal cash amount of
security deposited by the said contractor and/or deducted by the said
Corporation from the bills of the said contractor and which the said
Corporation had agreed to convert against the bank guarantees as therein."
According to the bank it was the duty and obligation of the Plaintiff to
disclose the reasons for invoking the bank guarantee and unless the Plaintiff
was able to show any actual loss or damage sustained by it due to the return
of the deposit to BAL, the bank guarantees could not be invoked.
11. A replication was filed by the Plaintiff reiterating its claims in the plaint.
It was contended that inasmuch as there was no mention of the extension of
the interim stay granted on 1st August 1991 by the learned Civil Judge in the
order dated 15th February 1992 it could not be said that the stay was still
operative. It was further urged that the contract between the Plaintiff and the
Bank as evidenced in the bank guarantees was independent of the contract
between BAL and NHPCL and that there was no justifiable ground for the
Bank not to honour the bank guarantees and pay the money on demand by
the Plaintiff.
12. On the basis of the pleadings and the documents on record the following
issues were framed by this Court by the order dated 8th August 2005:
"1. Whether the suit of the Plaintiff is signed, verified and instituted by a duly authorised person? OPP
2. Whether the defendant No.1 is not bound to encash the Bank Guantee received from the Plaintiff for a total amount of Rs.29 lakhs as alleged in the written statement?OPD
3. To what amount, interest, Plaintiff is entitled? If so, at what rate and for what period? OPP
4. Relief."
13. On behalf of the Plaintiff Shri P.B. Jain (PW-1), Chief Engineer, Civil
Contract filed his affidavit by way of evidence. Another affidavit was filed
by Shri Vijay Gupta (PW-2). On behalf of the Defendants, the affidavit by
way of evidence was filed by Shri Rajesh Malhotra working in the
Defendant No.1 Bank.
14. Issue No.1: Whether the suit of the Plaintiff is signed, verified and
instituted by a duly authorised person?
In order to prove that the plaint has been signed, verified and instituted by a
duly authorised person, Shri P.B. Jain has placed on record the general
power of attorney (Ex. PW1/1) dated 26th July 1991 executed by the
Chairman-cum-Managing Director of NHPCL nominating and appointing
Shri S.K. Sharma, Manager (CC) as attorney for and on behalf of the
NHPCL to do all acts necessary for filing a suit for recovery against the
Bank and BAL. Also placed on record is the general power of attorney dated
13th February 2006 executed by the then Chairman-cum-Managing Director
of NHPCL authorising P.B.Jain to file documents in the present suit and to
appear on behalf of the Plaintiff verifying the applications, plaints, pleadings
and affidavits.
15. The Defendant No.1 Bank has contended that the power of attorney
dated 26th July 1991 is beyond the powers of sub-delegation conferred upon
the Chairman and Managing Director and that PW-2 in his cross-
examination did not recognise the signatories of the plaint.
16. Having examined the documents on record and having considered the
submissions of counsel, this Court finds no merit in the objections raised by
the Defendant Bank. The clauses of the power of attorney dated 26 th July
1991 give sufficient authority to the concerned official of the Plaintiff to
sign the plaint and institute the suit on behalf of NHPCL. Accordingly,
Issue No.1 is answered in favour of the Plaintiff and against the Defendants.
17. Issue No.2: Whether the defendant No.1 is not bound to encash the Bank
Guarantee received from the Plaintiff for a total amount of Rs.29 lakhs as alleged in the written statement?
The onus to prove the above issue was on the Defendant Bank. The stand
taken by the Defendant Bank in the affidavit by way of evidence of its
witness is a reiteration of the stand taken in the application for leave to
defend and the written statement the contents of which have already been
noticed hereinbefore. Learned counsel for the Defendant reiterated that
Clause 1 of the bank guarantee had to be read along with Clauses 2 and 3
and if so read, it would indicate that unless the Plaintiff satisfied the Bank
that it had actually suffered some loss on account of the refund by it to BAL
of the security deposit or any portion thereof, the Bank was not obliged to
honour the bank guarantees. According to him the letter invoking the bank
guarantees was silent on the reasons for invocation and therefore the Bank
was justified in not honouring the bank guarantees within a period of 48
hours.
18. The stand taken in the written statement which is repeated in para 11 of
the affidavit by way of evidence of the Defendant Bank is that the contractor
BAL had already performed work to the extent of Rs.9.18 crores which was
in excess of total contract value of Rs.8.58 crores and therefore no bank
guarantee should have been issued for any performance of the contract as
contended by the Plaintiff. Learned counsel for the Defendant Bank was
however unable to point out any document placed on record by the
Defendant Bank which would go to show that within 48 hours from the
invocation of the bank guarantees by the Plaintiff, the opinion not to honour
the bank guarantees on the basis of the grounds now urged, was formed by
the advocate or the Bank. Even DW-1 makes no mention as to the time and
date on which such opinion was formed by the Bank. Even as of 24th July
1991 the Bank had only informed the Plaintiff that it had referred the matter
to its advocate for an opinion. Clearly, therefore, despite Clause 2 of the
bank guarantees requiring the bank to "pay unequivocally and
unconditionally within 48 hours of demand in writing from the said
Corporation of any amount up to and not exceeding Rs.6 lakhs" no such
opinion had been formed by the Bank within 48 hours not to honour the
bank guarantees for any reason.
19. In order to appreciate the contention of learned counsel for the
Defendant that the Bank was not obliged to honour the bank guarantees
unless the letter invoking the bank guarantees gave the reason why the bank
guarantees was not to be invoked a reference was made to clauses 1, 2 and 3
of the bank guarantees which read as under:
"1. We, the Punjab & Sind Bank, IBD, 6 Scindia House, New Delhi (hereinafter referred to as "the said Bank") and having our registered office at Rajindra Place, New Delhi do hereby undertake and agree to indemnify and keep indemnified the National Hydroelectric Power Corporation Limited; represented by Chief Engineer (hereinafter referred to as "the said Corporation" which expression shall, unless repugnant to the subject or context, include its administrators, successors and assigns) to the extent of Rs.6,00,000/- (Rupees Six Lakhs only) on behalf of Bhasin Associates Limited in lieu of an equal cash amount of security deposit deposited by the said contractor
and/or deducted by the said Corporation from the bills of the said contractor and which the said Corporation has agreed to convert against a bank guarantee as hereunder, under the provisions of Contract No.NH/Contracts/CCII/TP 07 dated.... which the said contractor has entered into with the said Corporation in connection with the construction of Power Channel & Silt Ejector from RD 250 M to 1437.5 M including Escape Channel for Tanakpur Hydroelectric Project at a total cost of Rs.8,58,99,500/- (Rupees Eight Crores Fifty Eight Lakhs Ninety Nine Thousand Five Hundred only) (hereinafter called the „said contract‟).
2. We, the said Bank also do hereby agree to pay unequivocably and unconditionally within 48 hours on demand, in writing, from the said Corporation, of any amount upto and not exceeding Rs.6,00,000/- (Rupees Six Lakhs Only) to the said Corporation for any purpose or cause or on any account whatsoever under the provisions of the said contract in which respect the decision of the said Corporation shall be final and binding on us.
3. Provided that it shall not be necessary for the said Corporation to proceed against the said contractor before proceeding against us and the guarantee herein contained shall be enforceable against us, notwithstanding any security which the Corporation may have obtained or obtain from the said contractor shall, at the time when proceedings are taken against us as hereunder, be outstanding or unrealised."
20. It is not possible to accept the submissions of learned counsel for the
Defendant Bank that a collective reading of the above clauses obligates the
Plaintiff to explain to the Bank the reasons why it was invoking the bank
guarantees. In the view of this Court, Clause 2 is unambiguous when it states
that the demand made by the Corporation would have to be met
unconditionally by the Bank within 48 hours and that such invocation "for
any purpose or cause or on any account whatsoever under the provisions of
the said contract" would be not questioned as is evident from the words "in
which respect the decision of the said Corporation shall be final and binding
on us." In other words, the language of the bank guarantees does not admit
of the construction that is sought to be placed on it by the Defendant Bank.
21. The law in respect of honouring of bank guarantees is well settled. A
reference may be made to the decision in National Thermal Power
Corporation Ltd. v. Flowmore Private Ltd. II (1995) BC 221 (SC) and
Hindustan Steelworks Construction Ltd. v. Tarapore & Co. 1996 III AD
SC (C) 153. Therefore this Court rejects the plea of the Defendant Bank that
it was justified in not honouring the bank guarantee since the letter sent to it
by the Plaintiff invoking the bank guarantee did not give the reasons why the
bank guarantees were being invoked.
22. The other reasons given by the Bank for not honouring the bank
guarantees is the pendency of the Suit No.146 of 1991 in the court of the
learned Civil Judge, Nainital and the continuation of the order dated 1st
August 1991 staying the encashment of the bank guarantees. As far as this
ground is concerned, it is seen that the order dated 15 th February 1992
passed by the learned Civil Judge confirming the stay of further proceedings
in Suit No.146 of 1991 awaiting the Award of the learned Arbitrator
continues to remain in force. Where the arbitration proceedings are closed
without any Award being pronounced, the suit would naturally revive.
However no attempt appears to have been made either by the Plaintiff
NHPCL or the other parties to Suit No.146 of 1991 to approach the learned
Civil Judge, Nainital with an application to have the proceedings revived.
As of today therefore the position is that Suit No. 146 of 1991 is pending
and so is the order dated 1st August 1991 passed by that court staying
encashment of the bank guarantees is operative. The said stay order has not
been modified or varied till date. Therefore the Defendant Bank as of today
is justified in not honouring the bank guarantees on the ground that there is a
stay operating against such encashment.
23. The only ground on which the Bank can seek to justify not honouring the
bank guarantees as of date is the stay order passed by the learned Civil
Judge, Nainital. Once the said stay order is vacated or comes to an end by
any subsequent order or with the disposal of the suit, then the Bank would
have no justification to not honour the bank guarantees.
24. Accordingly, issue is answered by holding that the Defendant Bank
would be bound to honour the bank guarantees for a total amount of Rs.29
lakhs as and when the learned Civil Judge, Nainital either vacates the stay
order dated 1st August 1991 or the said stay order comes to an end by any
further orders passed by that court.
25. Issue No.3: To what amount, interest, Plaintiff is entitled? If so,
at what rate and for what period?
The case of the Plaintiff is that it is entitled to recover the amount due to it
together with the interest at the bank rate prevalent at the time the bank
guarantees were given by Defendant No.1 Bank in its favour. However in
view of the facts narrated hereinbefore, the Bank was justified in not
honouring the bank guarantees during the period of the pendency of the Suit
No. 146 of 1991 and till such time the stay order dated 1st August 1991
passed by the learned Civil Judge, Nainital remains in force. That position
remains unchanged till date. It would therefore appear that if the Defendant
Bank fails to honour the bank guarantees even after the vacation of the stay
order by the learned Civil Judge in the manner indicated hereinbefore then
from such date till the date of payment of the amount due under the bank
guarantees to the Plaintiff the Defendant Bank would be liable to pay
interest. This will be at the bank rate prevalent on the date of such vacation
of stay. The issue is answered accordingly.
26. In view of the above determination of the issues, no relief can be granted
to the Plaintiff at the present stage except by clarifying the position as has
been done hereinbefore.
27. The suit is disposed of.
S. MURALIDHAR, J.
SEPTEMBER 03, 2009 dn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!