Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Delhi Development Authority vs M/S Verma Construction Company
2009 Latest Caselaw 4387 Del

Citation : 2009 Latest Caselaw 4387 Del
Judgement Date : 29 October, 2009

Delhi High Court
Delhi Development Authority vs M/S Verma Construction Company on 29 October, 2009
Author: Mukul Mudgal
*     IN THE HIGH COURT OF DELHI AT NEW DELHI


+                     FAO(OS) NO.765/2006
                                Date of Decision: 29TH October 2009

DELHI DEVELOPMENT AUTHORITY                              ...Appellant

             Through      Mr. Bhupesh Narula, Advocate



             versus



M/S VERMA CONSTRUCTION COMPANY                           .....Respondent

             Through      Mr. Mukesh Narain, Proxy counsel for

                          Mr. B. M. Sehgal, Advocate

CORAM:

HON'BLE MR. JUSTICE MUKUL MUDGAL

HON'BLE MS. JUSTICE REVA KHETRAPAL



1.    Whether the Reporters of local papers

      may be allowed to see the judgment?         No.

2.    To be referred to the Reporter or not?     Yes.

3.    Whether the judgment should be
      reported in the Digest?                    Yes.



%                               JUDGMENT(Oral)




FAO(OS) NO.765/2006                                              Page 1 of 6
 MUKUL MUDGAL,J.

1. In this appeal against the judgment of the learned Single Judge

dated 18th September 2006 we are essentially concerned with the claim

No.2 amounting to Rs.1,38,099.08 which was enhanced to that figure by

the learned Single Judge from the sum awarded by the Arbitrator.

2. The facts of the case briefly stated are as follows:

(a) By the Agreement No.29/EE/NDI/87-88 work of

construction of LIG flats in Pitampura was allotted by DDA

to M/s Verma Construction Company, the contractor.

(b) Date of commencement of work was 20th December,

1987. Date of completion was 19th June 1988. Works were

completed on 19th March 1991.

(c) The respondent contractor had 19 substantive claims.

The appellant DDA had proceeded to levy liquidated

damages under Clause 2 of the Contract. The appellant had

withheld payments due to the respondent to effect recoveries

pursuant to the liquidated damages levied.

(d) Disputes between the appellant and the respondent was

referred to the arbitrator.

3. The arbitrator, S.E. (Arbitration)-II on 17th April 1994 made the

award. The objections were filed by the appellant and the respondent.

The learned Single Judge delivered the judgment thereon on 18th

September 2006.

4. In the award dated 17th April 1994, the sum of Rs.49,216.95 was

awarded under claim No.2. The awarding of the sum of Rs.49,216.95 by

the arbitrator was recorded by the learned Single Judge in the following

finding in Paragraph 24 of the judgment:

"Recording that in view of Ex.R-95, i.e., final bill prepared by DDA, on quantities reflected as measured by DDA, a sum of Rs.1,38,099.08 was a justified payment, learned arbitrator has awarded Rs.49,216.95. While doing so, learned arbitrator has held that in view of liquidated damages levied by the competent authority, DDA was entitled to recover Rs.75,778/-."

5. We are not referring to the other claims as the appeal itself states

that the challenge is confined to the claim no.2. Even in claim no.2 we

are only concerned with the adjustment claimed by the appellant in

respect of the finding in paragraph 24. The settled position of law in

respect of the above has been summarized in the case of Delhi

Development Authority vs. Bhagat Construction Co. (P) Ltd. and Anr.,

2004 (3) Arb. LR 548 (Delhi) (DB) wherein it has been held that the

decision of the Superintending Engineer (S.E.) levying compensation

under Clause 2 is not arbitrable but that the decision of the S.E. will not

negate the power of the Arbitrator to decide the question as to who was

responsible for the delay in adjudicating upon the claims and counter

claims of the parties.

6. In another judgment of this High Court in the case of Delhi

Development Authority vs. M/s. Sudhir Brothers, 1995 (2) Arb. LR 306

(Delhi) (DB), the law has been thus summarized:-

"4. Our attention has been drawn to the arbitration clause and also the relevant clause which relates to exclusion of certain matters from the purview of arbitration. The relevant clause 2 in the arbitration agreement deals with the question of compensation and directs that the concerned engineer should decide this question and his decision is final. The arbitration clause opens with the words "Unless otherwise provided". In view of this language, it is obvious from the decision of the Supreme Court in Vishwanath Sood v. Union of India and another AIR 1989 SC 952, that the Arbitrator could not have gone into the merits of the levy of compensation by the engineer. In that view of the matter, the DDA ought not to have requested the Arbitrator to include the said amount in the arbitration award. We are told by the counsel for the appellant/DDA the Arbitrator was in fact informed that he could not go into the matter on merits. In any event, the DDA committed a blunder in requesting Arbitrator to formally include the above said amount as part of the award. Taking advantage of the said request, the contractor argued the question of levy on merits and obtained a decision from the Arbitrator in his favour." (emphasis supplied) "6. It will, therefore, be for the DDA to seek to recover the said amount of Rs.5,69,743 in whatever manner it is open to it and in case any such proceedings are taken, it will be open to the contractor to raise all defences that may be open to him in law to contend the levy is bad. In case, the DDA seeks to recover the said amount of compensation from the contractor it will be open to the contractor to file a suit and raise all such contentions as he may deem fit. We make it clear that the question of limitation will not be raised by either of the parties, in view of the above unfortunate procedure adopted by both parties."

7. Relying upon the aforesaid two judgments, this High Court in yet

another Division Bench judgment titled Delhi Development Authority vs.

Sunder Lal Khatri & Sons decided on 24th January, 2009 in FAO(OS)

No.498/2006, relying upon paragraph 6 of the judgment in Sudhir

Brothers (supra) and setting aside the award of the Arbitrator on the

counter claim pertaining to levy of compensation by the Engineer under

Clause 2 held that it will be open to the DDA to either file a suit to

recover the said amount, or upon adjustment of such amount by the DDA

from the dues of the respondent arising from the contract in question, it

will be open to the contractor to file a suit and such suit shall be disposed

of in view of the law laid down in the case of Sudhir Brothers (supra).

8. In view of the above position of law, we are of the view that out of

total amount of Rs.1,38,099.08, a sum of Rs.62,321.08 shall be released to

the respondent contractor along with the proportionate interest, and the

balance amount of Rs.75,778/- along with the proportionate interest shall

be released to the appellant DDA. The amounts so directed shall be

released to the parties not later than six weeks from today. However, it

will be open to the respondent contractor to institute civil proceedings in

accordance with law to recover the amount of Rs.75,778/-, if so advised.

We clarify that the question of limitation will not be raised by the

appellant in the event the respondent chooses to file a suit to recover the

balance amount claimed to be due to it.

9. The appeal, accordingly, stands disposed of.

MUKUL MUDGAL (Judge)

REVA KHETRAPAL (Judge) October 29, 2009 dr

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter