Citation : 2009 Latest Caselaw 4183 Del
Judgement Date : 15 October, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve : 3rd September, 2009
Date of Order: October 15, 2009
R.P. No. 160/2009 in CS(OS) No. 1650/2007
% 15.10.2009
Rani Parvati Devi ... Petitioner
Through: Ms. Shyamlaha Pappu, Sr. Advocate with
Mr. Krishna Moorthy & Mr. K.K.Singh, Advocates
Versus
Turner Morrison Ltd. ... Respondents
Through: Mr. Lalit Gupta, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
ORDER
1. This application has been made by the applicants (defendants No.1 & 2)
for review of order dated 6th March, 2009 whereby it is stated by the applicants that para
03 of the order passed by this Court was contrary to the facts as reflected by the
pleadings of the parties. It is stated that this Court in para 03 of the order observed that
as per defendants, on the construction of building, an amount of Rs.6.9 crore was spent
by the defendants, whereas this was the plea of the plaintiff that an amount of Rs.6.9
crore was spent on the building by the defendants and it was not the plea of the
defendants that an amount of Rs.6.9 crore was spent on the building by the defendants,
rather the defendants had denied this plea taken by the plaintiff in the plaint.
2. Para 03 of the order dated 6th March, 2009 reads as under:
3. The entire amount on the construction of the building was spent by the defendants from their own pocket and as per defendants, the defendants had spent around Rs.6,90,00,000/- on the construction of the building.
3. I have perused the record. The record shows that in the plaint, plaintiff
had stated in para 09 that an amount of Rs.6.9 crore was spent by the defendant on the
construction of the building and this expenditure was shown by the defendant in its
balance-sheet. The defendant (review applicant) in WS denied this assertion and stated
that the contents of para 09 of the plaint were wrong. It was specifically denied that the
total cost of construction was Rs.6.9 crore. It was asserted that cost of construction
worked out to be more than Rs.2000/- per sq. foot which was agreed rate of recovery of
cost of construction from plaintiff. In para 11 of the plaint, the plaintiff had again
asserted that cost of construction was Rs.6.9 crore and in para 11 (Reply on merits) of
the WS defendant again denied that cost of construction was Rs.6.9 crore.
4. It is obvious that the order has an error apparent on record wherein it is
recorded as per defendants that the defendants had spent around Rs.6.9 crore on
construction of building.
5. The learned Counsel for the non-applicant submitted that the order
passed by this Court amounted to a decree and it has become final and the Court
cannot review this judgment. It is also submitted that since by the order the Court has
disposed of an application under Section 8 of the Arbitration & Conciliation Act, 1996 the
provisions of the Arbitration & Conciliation Act, 1996 would apply and there was no
power of review under the Arbitration & Conciliation Act, 1996.
6. Both the arguments are fallacious. This Court was dealing with an
application under Section 8 of the Arbitration & Conciliation Act, 1996, filed in a civil suit.
The proceedings carried out by this Court and the order passed by this Court would be
governed by CPC since they were orders in a civil suit. The proceedings being carried
by this Court were proceedings in a civil suit and not in proceedings under the Arbitration
& Conciliation Act. Merely because an application under Section 8 of the Arbitration &
Conciliation Act was made by the defendants in the pending suit would not mean that
the proceedings carried out by this Court were under the Arbitration & Conciliation Act.
A Civil Court while handling the suit has power to decide an application under Section 8
and the powers and jurisdiction of Civil Court are to be construed in accordance with
CPC. The other argument that the order amounted to decree is also a baseless
argument. By order dated 6th March 2009 the Court had allowed an application under
Section 8 of the Arbitration & Conciliation Act and appointed an Arbitrator for
adjudicating the disputes between the parties thus, the order does not amount to
passing a decree in favour of the plaintiff. The observations made in the order
regarding pleadings of parties had to be based on the facts stated therein. If there is an
error in the observations and the observations made in the order are contrary to the
pleadings such observations in the order can always be corrected.
7. The applicant has successfully been able to show that there was an error
apparent on the face of the order regarding averments of the parties made in the
pleadings. I, therefore allow this review petition. Para 03 of the order dated 6 th March,
2009 be read as under:
"The entire amount on the construction of building was spent by the
defendants from their own pocket. As per the plaintiff, the
defendants had spent around Rs.6.9 crore on the construction of the
building."
The review application is allowed in above terms.
October 15, 2009 SHIV NARAYAN DHINGRA, J. vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!