Citation : 2009 Latest Caselaw 3989 Del
Judgement Date : 5 October, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: September 01, 2009
Date of Order: October 05, 2009
+CS(OS) 1088/1994
% 05.10.2009
DDA ...Plaintiff
Through: Ms. Geeta Mehrotra, Advocate
Versus
Cement Corporation of India ...Respondent
Through: Ms. Sunanda Roy, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this order, I shall dispose of the objections filed by DDA/ objector
against an award dated 12th October, 1993 passed by the sole arbitrator.
2. DDA had entered into a contract with respondent (Cement Corp. of
India) on 23rd December 1989. As per this contract, the supply was to be
made within six months from the 10th day of issuance of the contract. Two
qualities of cement, viz. Pozolana Portland Cement and Ordinary Portland
Cement were to be supplied by Cement Corporation of India to DDA at the
rates of Rs.1293 and Rs.1305 PMT respectively. The price was inclusive of
packaging charges and current taxes. However, if subsequent to date of
contract the taxes increased or decreased affecting the price, the same was
the liability of DDA and the price was to rise or fall accordingly. Respondent
did not supply the agreed quantity and the petitioner filed a claim against
respondent before the arbitrator in view of the arbitration clause that all
CS(OS) 1088 of 1994 DDA vs. Cement Corp. of India Page 1 Of 3 disputes between the parties were to be resolved through arbitration. The
first claim was in respect of levy of compensation of Rs.26,04,000/-. The
second claim was regarding risk purchase whereby DDA had claimed Rs.60
lac as difference in costs of material to be procured at the risk and costs of
respondent. The third claim was for Rs.20,000/- for expenditure incurred for
recalling the tender under R/P clause. The learned arbitrator allowed the first
claim of Rs.26,04,900/- which was the compensation levied by DDA under
clause 2 of the agreement. However, the learned arbitrator disallowed the
second and third claim on the ground that the claimant could have done risk
purchase only within the stipulated period and claimed the rate difference
prevalent during the supply period. The learned arbitrator observed that DDA
entered into an agreement with other party much after the supply period and
not at the market rate prevalent during the supply period therefore the
claimant was not entitled to the claim.
3. It is submitted by counsel for DDA that the claim no.1 was covered
under the excepted matter and the arbitrator passed this award in favour of
claimant DDA without jurisdiction and therefore the DDA had filed a suit for
this amount. Even otherwise, I do not find alleged clause 2 in the agreement
under which DDA could levy penalty in case of non delivery of cement. Since
counsel for DDA has stated that this part of award was covered under the
excepted matter, and DDA was not asking claim No.1 to be made rule of law,
this claim though allowed by the arbitrator shall not form part of the award.
4. As far as claim no.2 is concerned, I find nothing wrong with the award.
The delivery period as stated in the contract between the parties was only
two months and the first supply was to start within seven days of the
issuance. In case the delivery was not received within two months, DDA
CS(OS) 1088 of 1994 DDA vs. Cement Corp. of India Page 2 Of 3 would have procured cement from the market within this period at the price
prevalent during this period. The quotations on which reliance is placed by
DDA are not of this period. The delivery period ended in June, 1990. The
supply were stopped by CCI much prior to delivery period and the quotations
relied upon by the DDA were of February, 1991. The cement price used to
fluctuate during this period. DDA could have made purchase of cement only
during the supply period or immediately after the expiry of the supply period
in order to claim the price difference.
5. I also find that there is no clause in the contract between the parties
entitling DDA to do risk purchase at the cost of respondent and to claim price
difference. Rather the offer submitted by respondent specifically provides
that respondent was a wholly owned government enterprises and was
entitled to price preference of 10%. It was also specifically provided that the
risk purchase would not be applicable to respondent. The contract was
entered into between the parties in view of this offer of respondent. I consider
that the arbitrator rightly rejected the claims 2 and 3 raised by DDA.
6. Claim no.4 is in respect of cost of proceedings and interest. Since no
amount is payable under the award to DDA, DDA would not have been
entitled to costs of proceedings and interest. I, therefore, find no infirmity in
the award. The award except in respect of claim no.1, which comes under
excepted items, is hereby made a rule of the Court. The suit stands disposed
of.
October 05, 2009 SHIV NARAYAN DHINGRA J. rd CS(OS) 1088 of 1994 DDA vs. Cement Corp. of India Page 3 Of 3
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!