Citation : 2009 Latest Caselaw 4632 Del
Judgement Date : 12 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ I.A. No.1294/1996 in C.S. (OS) No. 2519A/1995
12th November, 2009.
M/s S.K. Grover & Co. ..Petitioner
Through: Mr. D.Moitra, Advocate
VERSUS
Union of India ...Respondent
Through: None.
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
1. Whether the Reporters of local papers may be allowed to see
the judgment?
2. To be referred to the Reporter or not?
3. Whether the judgment should be reported in the Digest?
%
JUDGMENT (ORAL)
I.A. No.1294/1996 in CS(OS) No.2519-A/1995
1. These objections have been filed against the Award dated
28.9.1995 under Sections 30 and 33 of the Arbitration Act, 1940 by
the contractor whose claims have been either rejected or only partly
allowed.
C.S(OS)No.2519-A/1995 Page 1
2. Mr. Moitra who appears for the objector has pressed objections
as regards Claim Nos.1, 3, 6, 7 and 10.
3. As regards Claim No.1 in which nominal amounts have already
been awarded (and in fact which claims were also for negligible
amounts only) on account of the fact that no proofs were given with
respect to these claims. After arguing this claim, Mr. Moitra says that
he does not press the objection with respect to Claim No.1.
4. Claim No.3 was also argued and thereafter Mr. Moitra has said
that he will not press this claim as this claim was based on clause 10CC
of the agreement and there is a factual finding of the Arbitrator that
clause 10CC does not even form part of the contract. During the
course of the arguments, I asked Mr. Moitra to show anything from
the contract as to how clause 10CC forms a part of the contract. Mr.
Moitra however was unable to do so. No fault can therefore in any
case be found with this portion of the Award.
5. Claim No.6 in the Award is with respect to loss of business profit
for not being given the complete amount of work. The arbitrator has
arrived at finding of fact that the deviation limit i.e. lower work
C.S(OS)No.2519-A/1995 Page 2 awarded is within the deviation limit permissible as per clause 12.
Again, I put to Mr. Moitra to show me from the contractual
documents how much was the work given against which deviation
was permitted and also the value of the work, however, Mr. Moitra
was not able to show any factual basis to challenge the finding of the
Arbitrator that the balance work reduced was not within the deviation
limit. Accordingly, this objection also fails.
6. Claim No.7 is based on charges towards idle labour, tools and
plants. In this regard, the Arbitrator has arrived at a finding of fact
and held that during the stipulated period of contract, no tangible
breaches were attributable to the non-objector/respondent before the
Arbitrator. This is a finding of fact and the Objector had to show
perversity for this Court to interfere under Sections 30 & 33. Again,
Mr. Moitra has not been able to refer to anything at all to show that
this finding is in any manner perverse. I am, therefore, unable to
agree with this objection.
7. That takes me to the final objection with respect to Claim
No.10. This claim is a claim for Rs.90,000/- on account of 20%
C.S(OS)No.2519-A/1995 Page 3 additional enhancement for the work done after the stipulated date of
completion. In this regard, the Arbitrator has clearly noted that the
extended period of work (which was just of about 3 months) was as
per the consent of the parties meaning thereby the objector never
objected or claimed any rights for delay when the contract was being
performed and which is a legal requirement under Section 55 of the
Contract Act 1872. This claim, therefore, was also misconceived and
therefore, the Arbitrator was justified in rejecting the same.
8. Before I conclude I must record that this case has been regularly
and repeatedly coming up for arguments before this court right from
4.10.2009. Mr. Moitra has however been taking adjournments.
Firstly, adjournment was taken on the ground that he did not have
the proper file. Thereafter, Mr. Moitra said that these are objections
are of a widow (as the contractor has died) and, therefore, he sought
further accommodation. This case was thereafter called out when no
one was present and has now been taken up today. Ordinarily,
considering that this is a very old case of the year 1995 and since
repeated adjournments have been granted at the request of the
C.S(OS)No.2519-A/1995 Page 4 objector, I would have, indeed imposed very heavy costs, however,
on the plea of the counsel for the objector that the widow of the
contractor is not in a sound financial condition, I am not imposing
costs in the matter. Accordingly, with the above observations, the
objections and also the suit stand disposed of. The Award dated
28.9.1995 is made rule of the Court.
VALMIKI J.MEHTA, J
November 12, 2009
ib
C.S(OS)No.2519-A/1995 Page 5
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!