Citation : 2009 Latest Caselaw 4447 Del
Judgement Date : 3 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) NO. 154/2007
Date of Decision : November 03, 2009
DIN Cooperative G/H Society Ltd. .....Appellant
Through : Mr. Anil Nag,
Advocate.
versus
Sh. A.S. Rana .....Respondent
Through : Mr. B.K. Dewan,
Advocate.
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MS. JUSTICE REVA KHETRAPAL
1. Whether the Reporters of local papers
may be allowed to see the judgment? NO
2. To be referred to the Reporter or not? YES
3. Whether the judgment should be
reported in the Digest? YES
% JUDGMENT (ORAL)
MUKUL MUDGAL,J.
1. This appeal challenges the judgment of the learned Single Judge dated
19th February, 2007 by which the learned Single Judge was pleased to
dismiss the objections preferred by the appellant to the award dated 24 th
October, 2005 given by Sh. V.D. Tiwari, the Sole Arbitrator, who was
appointed by this Court, as the appellant had failed to act on the request of
the respondent to appoint an Arbitrator.
2. The appellant is a Cooperative Group Housing Society. The admitted
case of the parties is that the Society had invited offers from contractors to
construct 156 residential flats on the land allotted to the Society. The offer
of the respondent was accepted and a formal contract was executed between
the parties on 25th February, 1996. The work was to commence on 1st
March, 1996 and was to be completed within 24 months. However, disputes
arose between the parties and the work remained suspended for a long period
of time. Eventually, after negotiations, the respondent was allowed to
continue with the work and the work was completed somewhere in the year
2002. The claim of completion of work by the contractor was disputed by
the Society and Sh. V.D.Tiwari was appointed by the Court as the sole
arbitrator to adjudicate upon the disputes between the parties. The learned
Arbitrator vide his award dated 24th October, 2005 awarded a sum of
Rs.75,19,230/- to the respondent.
3. The main plea urged by Sh.Nag, the learned counsel for the appellant
is that as per Clause 17 of the contract, the appellant was entitled to
liquidated damages @ Rs.1 lakh per week for the delay caused in the
completion of the work. A perusal of the judgment of the learned Single
Judge shows that this plea has not been dealt with by the learned Single
Judge in the judgment. We have asked the learned counsel for the appellant
whether this plea was urged before the learned Single Judge, who submitted
that this plea was not dealt with by the learned Single Judge. He was then
asked to show us the pleading in the memo of appeal and also show that such
a plea though urged was not dealt with by the learned Single Judge. Apart
from showing the general pleading that the learned Single Judge erred in not
appreciating the issue of liquidated damages, the learned counsel for the
appellant was unable to demonstrate to us from the memo of appeal that such
a plea was raised. Instead, the learned counsel for the appellant submitted
that the appellant had filed a 30 page written submission before the learned
Single Judge and the issue was contained therein.
4. In our view, if a plea is not addressed before the learned Single Judge,
the learned Single Judge is not bound to deal with each and every plea taken
in the written submissions before the learned Single Judge. The mere fact
that it is taken in the written submissions is of no avail to the appellant,
particularly in view of the fact that no specific averment is made on oath
before us that the plea urged was raised before the learned Single Judge.
Accordingly, we decline to permit the appellant to raise such a plea before
us.
5. We have also perused the prolix objections preferred by the appellant
before the learned Single Judge as well as equally prolix written
submissions. A perusal of the objections and the written submissions shows
that the main thrust of the appellant was on the issue of limitation, which
issue has not been addressed before us, and the objections pertaining to the
rejection of the counter claim though raised in the objection petition were
obviously not pressed before the learned Single Judge. Even the objections
raised before the learned Single Judge are as follows: -
"5.6 BECAUSE the learned Arbitrator erred in law in over- looking the fact that out of 166 flats, the Respondent completed only 53 flats and 113 flats were left unfinished. Out of the 113 flats the Respondent, under a separate Agreement/Understanding completed 70 flats in 2001 and 43 flats still remained unfinished and the balance work was got done either by the Petitioner Society or the individual flat owner at its/his own cost."
6. The above averments made before the learned Single Judge itself show
that for the completion of the contract, a separate agreement/understanding
was required to be entered into. Such an understanding or agreement has not
been shown to us and accordingly, reliance by the appellant on the erstwhile
Clause 47 of the earlier agreement, even if permitted to be raised is of no
avail to the appellant.
7. Accordingly, we find no merit in this appeal and the same stands
disposed of. All the pending applications also stand disposed of.
(MUKUL MUDGAL) JUDGE
(REVA KHETRAPAL) JUDGE November 03, 2009 sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!