Citation : 2009 Latest Caselaw 4445 Del
Judgement Date : 3 November, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: September 04, 2009
Date of Order: November 03, 2009
+OMP No.308/2009
% 03.11.2009
M/S. RAVI BUILDERS ..... Petitioner
Through: Ms. Manmeet Arora & Mr. Abhijeet, Advs.
versus
UNION OF INDIA ..... Respondent
Through: Nemo
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
ORDER
1. By this petition under Section 34 of the Arbitration and Conciliation
Act, the petitioner has sought setting aside of the award dated 27th
August, 2008 passed by the learned Arbitrator in respect of those claims
for which the award had gone against the petitioner.
2. A dispute between the petitioner and the respondent regarding
construction of 'Road Under Bridge' at Patparganj Road near Madhuban
Chowk was referred to the Arbitral Tribunal. The petitioner filed a
statement of claims containing 17 claims totaling to Rs.85,36,259/-. During
pendency of arbitration, petitioner modified statement of claims and
withdrew some of the claims. He withdrew claim no. 2 regarding 'cost
bank protection', claim no. 4 regarding 'idling of labour', claim no. 6(i) and
6(ii). Against claim no. 6(iv) claimant had mentioned no amount. Thus nil
award was given.
3. The Tribunal considered rest of the claims which were not
withdrawn and were pressed before the Arbitral Tribunal. After
considering evidence of both the sides and the material placed before it,
the Arbitral Tribunal came to conclusion that the claimant and the
respondent both equally contributed to the delays. Considering claim no.
1 for Rs.23,37,373/- Tribunal observed that similar claim, during pendency
of the contract, was referred to the previous Arbitral Tribunal and the
previous Arbitral Tribunal had awarded a sum of Rs.7,48,500/- as the extra
costs to the claimant for lowering the water table by 'well point system'
for a six months period despite observing that during normal period of
execution of work, de-watering by 'well point system' was an essential
activity in the non-schedule item no.1. However, since the claimant was
allowed extra payment by earlier interim award on the basis of contract
extending beyond the specified contractual period, the Tribunal adopted
the same logic and considering that since both the petitioner and the
respondent were equally liable for delay, allowed 50% of the claim made
by the petitioner. The Tribunal also allowed claim no. 5 in full to the tune
of Rs.9,000/-. The Tribunal allowed claim no. 6(vi) in full to the of
Rs.1,58,000/- and claim no. 6(vii and ix) therefore were allowed to the
tune of 50%. Cost of arbitration was also directed to be shared by the
parties equally. Thus, the Tribunal allowed the claim of claimant to the
tune of Rs.16,10,950/-. The Tribunal did not allow pendent lite and future
interest.
4. A perusal of objections against the award would show that the
petitioner has assailed all disallowed claims or partly allowed claims on
merits. The contention of the petitioner is that the Tribunal allowed 50%
amount of the claim no. 1 by misreading earlier interim award and
committed an error in allowing only partial costs of lowering water table,
instead of full cost by holding that petitioner and the respondent both
were equally responsible for the delay. It is further submitted that the
Tribunal committed an error by not compensating the petitioner for losses
caused due to increase overhead cost and Tribunal wrongly held that
certain claims of the petitioner were not supported by conditions of
contract. The Tribunal wrongly rejected the claim no. 6 (iii) and 6(v) of the
claimant and the decision of Tribunal was contrary to the material placed
on record.
5. It is settled law that while considering objections under Section 34
of the Arbitration and Conciliation Act, this Court does not sit as a Court of
appeal and cannot re-appreciate the evidence and come to a different
conclusion. The Court cannot pass a fresh award instead of the award
passed by the learned Arbitrator by holding that the claims were not
properly decided by the Tribunal. Under Section 34 of the Arbitration and
Conciliation Act, 1996 an award can be set aside on the following grounds
as laid down by the Supreme Court in DDA vs. R.S.Sharma & Company,
New Delhi JT 2008 (9) SC 362:
"(a) An Award, which is
(i) contrary to substantive provisions of law; or
(ii) the provisions of the Arbitration and Conciliation Act, 1996; or
(iii) against the terms of the respective contract; or
(iv) patently illegal, or
(v) prejudicial to the rights of the parties, is open to interference by the Court under Section 34(2) of the Act.
(b) Award could be set aside if it is contrary to :
(a) fundamental policy of Indian Law; or
(b) the interest of India, or
(c) justice or morality:
(c)The Award could also be set aside if it is so unfair and unreasonable that it shocks the conscience of the Court.
(d) It is open to the Court to consider whether the Award is against the specific terms of contract and if so, interfere with it on the ground that it is patently illegal and opposed to the public policy of India."
6. The petitioner has failed to make out any of the above grounds. I
find no force in this petition. The petition is hereby dismissed.
November 03 , 2009 SHIV NARAYAN DHINGRA, J ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!