Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Hotel Corpn. Of India Ltd. vs M/S. Continental Furnishers, New
2009 Latest Caselaw 975 Del

Citation : 2009 Latest Caselaw 975 Del
Judgement Date : 25 March, 2009

Delhi High Court
Hotel Corpn. Of India Ltd. vs M/S. Continental Furnishers, New on 25 March, 2009
Author: Mukul Mudgal
*      IN THE HIGH COURT OF DELHI AT NEW DELHI

+                           FAO(OS) 46/2003


                                  Date of Decision: 25rd March, 2009


HOTEL CORPN. OF INDIA LTD.                           ..... Appellant
                    Through:        Ms. Padma Priya, Advocate.

                   versus

M/S. CONTINENTAL FURNISHERS, NEW             ..... Respondent
                    Through: Mr. Sandeep Sharma, Advocate.


       CORAM:
       HON'BLE MR. JUSTICE MUKUL MUDGAL
       HON'BLE MR. JUSTICE VIPIN SANGHI

       1. Whether the Reporters of local papers may
          be allowed to see the judgment?                   No

       2. To be referred to Reporter or not?                Yes

       3. Whether the judgment should be reported
          in the Digest?                                    Yes

%                           JUDGMENT (Oral)


MUKUL MUDGAL, J.

1. This appeal is directed against the orders dated 3.10.2001 and

31.10.2001 passed by the learned Single Judge setting aside the

awards dated 31.5.1995 made and published by the Arbitrator and

appointing a new Arbitrator. The learned Arbitrator rejected the claims

of the respondent as being barred by time on the ground that the

notice asking for reference of disputes to arbitration had not been

given by the respondent within 28 days of the issuance of the

Architects Certificate as provided in Clause 48 of the agreement. The

learned Single Judge, by relying upon the decision in 77 (1999) DLT

165 M/s. Hindustan Construction Corporation Vs. DDA set aside

the award on the ground that the reference cannot be rejected merely

because the arbitration was not invoked within the time stipulated by

such a clause.

2. The appeal is preferred on the ground of violation of Clause 48 of

the agreement between the parties. Clause 48 of the agreement reads

as under:

48. SETTLEMENT OF DISPUTES:

All disputes and differences of any kind whatever arising out of or in connection with the contract or carrying out of the works (whether during the progress of the works or after their completion, and whether before or after the determination, abandonment or breach o the contract) shall be referred to and settled by the Architects, who shall state his decision, in written. Such decisions may be in the form of a final certificate or otherwise. The decisions of the Architects with respect to any or all of the following matters shall be final and without appeal:

(a) The variation or modification of the design;

(b) The quality or quantity of works or the additions/alterations, omissions, or substitutions of any work;

(c) Any discrepancy in the drawings or between the drawings and/or specifications, and schedule of quantities;

(d) The removal and/or re-execution of any works executed by the contractor;

(e) The dismissal from the works of any person employed thereupon;

(f) The opening up for inspection of any work covered up;

(g) The amending and making good of any defects under defects liability period;

(h) Acceptability of materials, equipment and workmanship;

(i) Materials, labour, tools, equipment, and appurtenances necessary for the proper execution of work;

(j) Assignment of sub-letting;

(k) Delay and extension of work;

(l) Termination of contract by the Employer.

But if either the Employer or the contractor be dis-satisfied with the decision of the Architects or any matter, question or dispute of any kind except the matters listed above, then and in any such case, either party (the Employer or the contractor) may within twenty eight (28) days, after receiving notice to such decision, give a written notice to other party through the Architects requiring that such matters which are in dispute or difference of which such written notice has been given and no other shall be and is hereby referred to the Arbitration and final decision of a single Arbitrator being a person who is a Professional Engineer/Chartered Architect/Chartered Surveyor (Building and Quantities/Land Surveying), to be agreed upon and appointed by both the parties or in the case of disagreement as to the appointment of a single Arbitrator to the arbitration of two Arbitrators both being persons who are professional Engineers/Chartered Architects/Chartered Surveyors (Building and Quantities/Land Surveying), one to be appointed by each party, which Arbitrators shall, before taking upon themselves the burden or reference appoint an Umpire, who must also be Professional Engineer/Chartered

Architect/Chartered surveyor, as described earlier.

The Arbitrator, the Arbitrators or the Umpire shall have power to open up, review and revise any certificate, opinion, decision, requisition or notice pertaining to the matters referred to them, and to determine the same by his/their award. Upon every or any such references the cost of and incidental to the reference and award respectively shall be at the discretion of the Arbitrator or Arbitrators or Umpire, who may determine the amount thereof, or direct the same to be taxed as between Attorney and Client or as between party and party, and shall direct by whom and to whom and in what manner the same shall be borne and paid. This submission shall be deemed to be submission to Arbitrator within the meaning of the Indian Arbitration Act, 1940 or any statutory modifications thereof. The award of the Arbitrator or Arbitrators or the Umpire shall be final and binding on the parties. The Employer and the Contractor hereby also agree that the Arbitration under this clause shall be a condition precedent to any right of action under the contract."

3. It is contended that the certificate of the architect was

questioned only on 12.05.1992, whereas the architect's certificate was

issued on 22.09.1986. For this purpose reliance has been placed on

the judgment of the Hon'ble Supreme Court titled as R. Reddy &

Bros. Vs. Maharashtra Krishna Valley Development Corporation

And Others (2009) 2 SCC 494 in which reliance has been placed on

Clause 54 in the Contract before the Hon'ble Supreme Court which was

in terms para materia with present Clause 48. The above decision

holds that for purposes of invocation of arbitration, the contractual

term binds the parties.

4. Mr. Sharma, who appears on behalf of the respondent, submits

that in the facts of the present case the decision of the Hon'ble

Supreme Court has no application, as aforesaid, the architects

certificate dated 22.09.1986 was indeed questioned and arbitration

invoked on 18.10.1986 i.e. within 28 days.

5. A perusal of the record of the Arbitrator demonstrates that it was

the appellant who had admitted before the Arbitrator the fact that the

notice dated 18.10.1986 was issued by the respondent. Now from a

perusal of the letter dated 18.10.1986 it is evident that the arbitration

was indeed invoked by the respondent and the arbitration commenced

upon issuance of the said notice by virtue of Section 37 of the

Arbitration Act, 1940. The judgment relied upon by the appellant is not

applicable in the facts and circumstances of the present case and the

appeal accordingly stands dismissed.

MUKUL MUDGAL, J.

VIPIN SANGHI, J.

MARCH 25, 2009 dp

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter