Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India vs M/S Kashind Roller Floor
2009 Latest Caselaw 960 Del

Citation : 2009 Latest Caselaw 960 Del
Judgement Date : 24 March, 2009

Delhi High Court
Union Of India vs M/S Kashind Roller Floor on 24 March, 2009
Author: Vipin Sanghi
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

+                           FAO(OS) 351/1999


                                   Date of Decision: 24rd March, 2009


      UNION OF INDIA                                     ..... Appellant
                        Through:      NEMO.

                  versus


      M/S KASHIND ROLLER FLOOR                ..... Respondent
                    Through: Mr. Shiv Khurana, Advocate.


      CORAM:
      HON'BLE MR. JUSTICE MUKUL MUDGAL
      HON'BLE MR. JUSTICE VIPIN SANGHI


      1. Whether the Reporters of local papers may             No
         be allowed to see the judgment?

      2. To be referred to Reporter or not?                    No

      3. Whether the judgment should be reported               No
         in the Digest?


%                           JUDGMENT (Oral)

VIPIN SANGHI, J.

1. The present appeal is directed against the order dated

01.11.1999 passed by the learned Single Judge whereby the

appellant's application being I.A. No. 10658/98 under Section 34 (3) of

the Arbitration and Conciliation Act (the Act) seeking condonation of

delay in filing objections (under Section 34 of the Act) to the arbitral

award dated 21.05.1998 has been dismissed, and consequently OMP

No. 267/98 being objections under Section 34 of the Act have also

been dismissed.

2. The award itself records that the parties agreed that the

proceedings to be treated as under the Act.

3. The impugned order reveals that none appeared for the

petitioner when the application for condonation of delay of 21 days

was taken up for consideration by the Court. Once again, none has

appeared for the appellant. Since the delay was less than 30 days

which is condonable by the Court, we have proceeded to examine the

award on our own on merits by condoning the delay and setting aside

the order of the learned Single Judge of dismissal for default.

4. The respondent was engaged as a milling contractor for

conversion of wheat into atta, flour, suji and gram by the appellant

vide agreement dated 2.8.1991 for a period of three years w.e.f.

30.11.1991. A large quantity of brans, jute bags and gunny wrappings

in which wheat was being supplied and its products was to be

packaged was supplied to the respondent. These got accumulated at

the respondent's premises for which the respondent was made

responsible under Clause 9 (a) of the agreement. The appellant was

not taking back these bags and it continued to remain stored at

premises of the respondent. Despite repeated notices, these bags

were not taken back. Evidently, the respondent disposed of these

bags. The appellants made a claim towards cost of the bags for

Rs.33,28,934/-. The learned Arbitrator after taking note of the notices

sent by the respondent calling upon the appellant to remove the bags

lying at their mill and the fact that these bags were disposed of for Rs.

1,33,600/- by the respondent, allowed the claim of the appellant only

to the extent of Rs. 1,33,600/-. The following counter-claims of the

respondent were also allowed:

"2. The claim of the Respondent for Rs. 21 lacs for closure of mill from 1.12.94 upto 30.6.95 because of non-lifting of stock is allowed for Rs. 2.5 lacs per month from 1.1.95 till 30.5.95 aggregating Rs. Fifteen lacs for the aforesaid reasons.

3. The claim of the Respondent for security staff for watch and ward of claimant's stock at Rs. 12,000/- per month is allowed for the period claimed and therefore allows the sum of Rs. 84,000/- as claimed by the Respondent.

4. The rent claimed by the Respondent for keeping in their godown for the period from 1.12.94 till 30.10.95 at Rs. 50,000/- per month is allowed for the aforesaid reason but since Respondent has only claimed Rs. 3,50,000/- I allow only Rs. 3,50,000/-.

5. The claim of the Respondent for insurance stock is allowed for Rs. 6,000/- as claimed by the Respondent and proved by the Respondent.

8. The cost of jute twine malethene and celphose tablets provided by the Respondent on loan basis is allowed and claim of Respondent for Rs. 2,95,000/- in this regard is payable by the claimant as admitted by the Claimant.

9. The claim of Respondent of refund of earnest money of Rs. 1 lac and last bill of Rs. 1,83,464/- is allowed an being payable by the

claimant and not denied by the claimant during hearing."

5. The learned Arbitrator also awarded interest at the rate of 18

per cent from 1.7.1995 when notice was issued to the appellant till the

actual payment.

6. The award shows that the learned Arbitrator has returned a

finding of fact that the respondent had put the appellant to repeated

notice for removal of the bags and despite these notices, bags were

not removed. The respondent was not obliged to continue to store the

bags at its premises for an indefinite period as the contract was for

milling and not for storing bags which was only incidental to milling

and once the milling contract was over the question of keeping these

bags did not arise. They were required to be lifted by the appellant as

soon as possible. On the facts and circumstances the learned

Arbitrator thought it fit that it was reasonable for the respondent to

store the goods for one month only. According to him no explanation

was furnished by the claimant as to why the stores were not removed

immediately even after notice dated 16.07.1995 served upon them.

For these reasons the counter-claims of the respondent were allowed.

7. It is not clear how the appellant could state that the Arbitrator

has erred in allowing the claim of the appellant to the extent of Rs.

1,33,600/- and how the Arbitrator has erred in allowing the aforesaid

counter-claims of the respondent. Consequently, we find no merit in

this appeal, which we have proceeded to consider on merits on the

assumption that the delay of 14 days should have been condoned by

the learned Single Judge. Dismissed.

VIPIN SANGHI, J.

MUKUL MUDGAL, J.

MARCH 24, 2009 DP

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter