Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Naryanan Consultancy vs Indian Oil Corporation Ltd. And ...
2009 Latest Caselaw 946 Del

Citation : 2009 Latest Caselaw 946 Del
Judgement Date : 23 March, 2009

Delhi High Court
M/S Naryanan Consultancy vs Indian Oil Corporation Ltd. And ... on 23 March, 2009
Author: S.Ravindra Bhat
*     IN THE HIGH COURT OF DELHI AT NEW DELHI
                                              Reserved on: 24.02.2009
                                           Pronounced on: 23.03.2009

+                      W.P. (C) 18968/2006


M/S NARYANAN CONSULTANCY                              ..... Petitioner
                       Through: Mr. R.P. Bhatt, Sr. Advocate with
                       Mr. S. Udaya Kr. Sagar and Mr. Venayagam,
                       Advocates.

                  versus


INDIAN OIL CORPORATION LTD. AND ORS.                 ..... Respondents
                       Through: Mr. Prabhat K. Srivastava &
                       Ms. Shweta Mishra, Advocates.
                       Ms. Geetanjali Mohan & Ms. Vaishnavi,
                       Advocates for Resp-3-4.
                       Ms. Ruchi Gaur Narula, Advocate.
      CORAM:
      HON'BLE MR. JUSTICE S. RAVINDRA BHAT

1.    Whether the Reporters of local papers          Yes
      may be allowed to see the judgment?

2.    To be referred to Reporter or not?             Yes

3.    Whether the judgment should be                 Yes
      reported in the Digest?

S.RAVINDRA BHAT, J.

%

1. The Writ Petitioner in these proceedings under Article 226 of the

Constitution of India seeks various directions against the first respondent

(Indian Oil Corporation Ltd, hereafter called "IOC") to pay service charge of

Rs.15,69,597/- with interest and also pay further service charge amounting

to Rs. 2,00,70,000/- and settle its bill dated 9.9.2004. Similar directions to

settle the petitioner's claim towards payments are also sought.

2. Briefly the necessary facts are that the IOC erected a link line (chord

line) between Baroda - E Cabin to Chhaya Puri Railway Station of Western

Railways in 1971. This line was used by the IOC to transport rakes booked

from Bajwa to north of Vadodra and were directly dispatched thus reducing

11 Kms. Apparently, in spite of this, the Western Railways incorrectly

continued to charge more freight by including the 11 Kms. distance. The

question of refund of excess freight charges had been engaging the attention

of IOC and the Western Railways. The petitioner claims that being aggrieved

by Railway's inaction in regard to refund of such excess payments, the IOC

entered into contract with it for consultancy service to secure settlement of

such outstanding claims. The consultancy contract, entered into on 1.7.2001

was valid for one year and extendable with mutual consent of the parties.

Clause 2 of the contract defined the scope of service; the petitioner as

Consultant was responsible for pursuing the matter with the Railways and

getting IOC's claims settled. The petitioner was entitled to charges for the

service rendered, in accordance with the Schedule - A to the contract; the

same is in the following terms: -

Sr. No.           Items of Works                       Schedule of Charges
1                 Claim     for   compensation    of     (c) Rupees One Thousand
                  missing     tank   wagons      and           per Tank Wagon.
                  shortage/leakage claims.               (d) Rupees Seven Hundred



                                                                   per Tank Wagon.
                       (a) Cases beyond and upto
                            31.03.1997
                       (b) Cases after 31.03.1997
2                 Reduction/Abolition/Refund        of   (a) i)    9   %     of     amount
                  freight charges from Railways                   realized    from         the
                  on -                                            Railways        within    4
                                                                  months.
                       (a) Regular Claims                         (ii) 8% of amount
                                                                  realized from the
                                                                  Railways beyond 4
                                                                  months but less than
                                                                  7 months.
                                                                  (iii)7% of amount
                                                                  realized from the
                                                                  Railways beyond
                                                                   7 months.
                       (b) Repudiated    and     Time    (b) 15% of amount realized
                            Bar/Suit Bar Claim.                   from the Railways.


3                 Refund     of   amount       wrongly 15% of the amount realized

recovered by the Railways or or abolished or withdrawn or any debit raised by the adjusted/credited by the Railways for various services Railways and accepted by the such as siding charges/shunting IOC.

                  charges/To pay surcharge/cost
                  of      Railway       staff/penalty
                  overloading/wagon
                  registration/shunting-siding
                  charges/Electrification/overhead



                   maintenance                   etc./debit
                  raised/recovered         on     various
                  grounds       by    the       Railways
                  including      reconciliation        of
                  accounts etc.
4                 Freight     audit   of    dispatching 15% of the amount realized
                  locations       under          Western from the Railways.
                  Region/IOC.



3. The petitioner claims to have followed up and "chased" 38,305 claims

for the period 20.10.1996 to August, 2002. The initial term of the contract,

which ended in end of June, 2001 was extended by mutual consent by a

year. It is asserted that out of the 38,305 claims pursued, the petitioner was

able to successfully secure settlements of 14,348 claims; 23,957 such claims

continued to be pending. It is further alleged that IOC was beneficiary to the

extent that Rs.14.7 Crores were settled out of a total quantum of Rs.33.92

Crores. The petitioner, therefore, claims that having regard to the progress

achieved, the IOC should have ensured that its dues were paid.

4. The petitioner has filed copies of statements showing claims for refund

for various periods when the consultancy contract subsisted between the

parties. It also has placed reliance upon tabulated claim statements and

several documents in support of its demand that the dues should be properly

paid. It refers to and relies upon letters dated 28.9.2004, 1.11.2004,

3.1.2005, 18.1.2005, 31.3.2005 & 24.11.2005 etc. in support of the

allegation that by its efforts IOC benefitted to the tune of Rs.15.32 Crores

despite which, its proper dues have not been paid.

5. The petitioner contends through its senior counsel, Shri R.P. Bhat, that

all the facts necessary to afford relief in these proceedings exist with records

and though facially the dispute pertains to facts in reality the IOC cannot

deny having benefitted from the efforts exerted by it. It is contended that

having availed all the services and obtained the refund of substantial

amount, the IOC cannot refuse to honour the petitioner's bills dated 1.9.2003

and 9.9.2004 for Rs.15,69,597/- and Rs.2,00,70,000/-, respectively.

6. Reliance is placed upon the decision of the Supreme Court in ABL

International v. Export Credit Guarantee Corporation of India Ltd. 2004 (3)

SCC 553 to say that whenever a State or State agency acts unreasonably,

and contrary to public good in any aspect of its functioning including in the

contractual domain, it does so contrary to the mandate of Article 14 of the

Constitution of India. The Court, under Article 226 of the Constitution, can in

such cases make appropriate orders to mould the relief and secure ends of

justice. Reliance is also placed on the judgment reported as Mahabir Auto

Industries v. Indian Oil Corporation 1990 (3) SCC 752, to contend that every

facet of state functioning has to be informed by reasons and free from the

vice of arbitrariness.

7. The IOC in its return, does not dispute entering into a consultancy

contract with the petitioner on 14.6.2001 or that its terms were extended. It,

however, states that out of the claims to an extent of Rs.33.92 Crores,

Rs.1,31,95,854/- were realized during April-May, 2003. The IOC contends

having paid Rs.19,79,378/- to the petitioner in June, towards consultancy

charges. It submits that a further amount of Rs. 1,04,63,983/- was realized

in September, 2003 after expiry of the consultancy contract. According to

the IOC, the railway authorities informed it (the IOC) on 23.7.2004 that

claims to the extent of Rs.14.7 Crores had been processed for adjustment,

yet no such amount was disbursed and the IOC was constrained to prefer

claims. This amount has not been realized till date. As a result, the IOC did

not pay consultancy charges to the petitioner. It is further submitted that

the amounts realized, especially after the consultancy contract ended, were

through the independent efforts of the IOC with the Western Railways and

the petitioner, therefore, cannot claim credit.

8. The IOC points to the Clause 1 of the agreement, which spells out the

tenure i.e. one year. During the period the IOC was entitled to terminate the

contract after giving 30 days notice. It is contended that such being the

case, the entitlement of the petitioner has to be proved in regard to the

amounts realized after the contract ended.

9. The Western Railways too has filed the counter affidavit. Apart from

generally denying the facts, it states that disputes between the IOC and itself

towards refund of alleged excess claims are sub judice and pending before

the Railway Claims Tribunal, Ahmedabad and that the said Tribunal is the

most appropriate forum to adjudicate the dispute. It has produced the copy

of the claim filed before the Tribunal, whereby the IOC has claimed a

direction for payment of Rs.18,36,25,964/- as refund for the period 20.10.96

to 30.9.99 with interest. It is contended that this Court should not take

cognizance of the disputes sought to be raised since writ proceedings are not

appropriate for adjudication of the facts.

10. The above discussion would show that there is no serious dispute

about facts pertaining to the consultancy contract or its terms. The

petitioner's mandate was to follow up with the claims for refund lodged by

the IOC with the Western Railways. The IOC admits having received some

refund. It concedes paying a sum of Rs. 19,79,378/- as consultancy charges,

to the petitioner. However, its contention is that, vis-à-vis amounts received

after the expiry of the consultancy period/contract, the petitioner cannot

lodge any claim towards such fees or charges. It avers, besides, that as

regards the other claims that were allegedly processed by the petitioner,

disputes are pending adjudication before the Railway Claims Tribunal.

11. Now, the jurisdiction of the Courts under Article 226 is recognized to be

of wide amplitude. Long ago in Dwarka Nath v. I.T.O. AIR 1966 SC 81, the

Supreme Court held that Article 226 confers a wide power on the High Courts

to reach out to injustice, wherever it is found. The court held that High Courts

can also issue directions, orders or writs in the nature of prerogative writs

and that the provision enables the High Courts to mould the reliefs to meet

the peculiar and complicated requirements of this country.

12. The Courts have further expanded the scope of the writ remedy by

holding that wherever an agency performs a public function or a part of its

functions are relatable what are termed as "public law duties" regardless of

the origin of such duties i.e. statutory or non statutory, such actions can be

scrutinized by judicial review under Article 226 of the Constitution (see Binny

Ltd. v. V.V. Sadashivan & Ors. 2005 (6) SCC 657). In the decision of the

Supreme Court in ABL International cited by the petitioner, the Court no

doubt stated that where essential facts are capable of adjudication by the

High Court under Article 226, it would be inequitable to relegate the

aggrieved party to the remedy of a Suit or civil proceedings. The Court also

relied upon certain previous decisions.

13. This Court is, of course, mindful of the authority of the Supreme Court

in ABL International (supra) and Mahabir Auto Industries - also cited on

behalf of the petitioner. Yet the facts of this case disclose that the question

of what is payable to the petitioner is not admitted by the respondents.

Concededly 38,305 claims were preferred by it. The Railways does not admit

to having allowed all of them; even the IOC does not concede to the Railways

having settled even the claims mentioned by the petitioner. It only admits to

having received a small part of the total claim of Rs.33.92 Crores. Further

disputes between the IOC and the Western Railways are pending

adjudication before the Railways Claims Tribunal. There, is therefore, dispute

on the essential facts.

14. In these circumstances, it would be imprudent and inexpedient for this

Court to examine the feasibility and soundness of the petitioner's claim.

Besides, assuming that the Court can consider the dispute, it would be also

at some stage necessary to delve into the facts particularly as to the

petitioner's claim for entitlement of the amounts received after the contract

with IOC ended. The IOC has entirely disputed the petitioner's right to

receive any consultancy charges or the amounts received after its contract

ended. According to the IOC such amounts were received by independent

initiative exerted on its part. It is evident that though this Court's jurisdiction

to examine and decide on questions of facts may not be entirely ousted and

in given circumstances if deemed appropriate, relief can be granted, yet the

facts presented in these proceedings are not such that they can be

appropriately or conveniently examined. They would necessarily involve

recording of evidence and consideration of arguably voluminous documents

and materials, for which Article 226 proceedings would be inappropriate.

Lastly, the petitioner has approached this Court after a considerable delay.

Even according to its averments, the payments were due sometime in

October-November, 2002; yet it has chosen to prefer the present

proceedings in December, 2006. In the circumstances, this is not an

appropriate case for exercise of jurisdiction under Article 226 of the

Constitution of India.

15. For the above reasons, the Writ Petition cannot succeed; it is,

therefore, dismissed. There shall, however, be no order as to costs.

S. RAVINDRA BHAT (JUDGE)

MARCH 23, 2009 /vd/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter