Citation : 2009 Latest Caselaw 944 Del
Judgement Date : 23 March, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) 197/1999 & C.M. No.2328/1999
Date of Decision: 23rd March, 2009
DELHI DEVELOPMENT AUTHORITY ..... Appellant
Through: Ms. Anusuya Salwan and Mr.
Rajesh Kumar, Advocates
versus
M/S TANTIA CONSTRUCTION COMPANY ..... Respondent
Through: Mr. George Thomas, Mr. Sanjay
Kumar Chhetry and Ms. Rajashree,
Advocates
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
% JUDGMENT (Oral)
MUKUL MUDGAL, J.
1. This appeal challenges the order of the learned Single Judge
dated 08.03.1999, by which order the objections to the award dated
09.08.1996 were dismissed and the award was made a Rule of the
Court. The order dated 30.08.1999 passed in this appeal stipulated
that the arguments shall be confined to Claim Nos.2, 3(C) and 3(D) and
the item of escalation on Claim Nos.2, 3(C) and 3(D) under Claim No.7.
It appears that the mention of Claim No.3(D) was a typographical error
in the order dated 30.8.1999, as there is no claim 3(D) awarded by the
learned Arbitrator. There was Claim No.3(d) made for "Reinforcement
for RCC Walls - Rs.7,71,050/-", but this Claim was disallowed by the
learned Arbitrator, and it has attained finality. All the aforesaid claims
arose on a fundamental premise that the water level only upto a level
of 210 mts stood accounted for under the contract and since the water
level rose above 210 mts, the work executed by the contractor was
entitled to be considered as work carried out in sub-soil for which
payment should have been made as per Delhi Schedule of Rates
(DSR), 1985. For this claim the respondent-claimant relied upon clause
13 of the agreement. The learned Arbitrator has recorded as a finding
of fact that the appellant had taken the level as per condition No.27 (at
page 89 of the agreement) and found the water level to be more than
210 mts which was also recorded. The details of claim nos. 2, 3(c) and
7, in so far as they are relevant are as follows:-
Claim No.2 This claim was made for a sum of Rs. 22 lakhs
by way of extra and substituted items. It was claimed that:-
(i) Earth work in excavation
(ii) Laying of CC
(iii) Laying of RCC pipes
(iv) Laying of stone soiling etc. were executed in or under water or liquid
Claim No.3(C) This claim was also made for carrying out the
work of centering and shuttering for foundation footing and
mass concrete in sub-soil water level condition for Rs. 11,000/-
and for carrying out RCC work in a raft by Rs.1,14,418.92.
Claim No.7 was made towards escalation payable under
clause 10(cc) of the contract, inter alia, in relation to works
carried out in sub-soil conditions.
2. The appellant had sought to rely upon clause 73 of the
agreement and on that basis had argued that the contractor/
respondent was not entitled to claim anything extra over and above
the rates provided in the schedule of quantities for execution of the
work in or under water on account of pumping and bailing out of water
by any method of lowering of sub-soil water level during the execution
of work.
3. It is agreed between the parties that since Claim Nos.3 & 7
are dependent upon the reasoning contained in Claim No.2, the
decision on the Claim No.2 will govern the pleas in respect of Claim
Nos.3 & 7 as well.
4. Having heard learned counsel and given our due
consideration, we are of the view that Clause 13 clearly shows that if
the sub-soil water level rises upto 210 meters, no extra payment was
to be made, but if it rose beyond 210 meters, then payments was to be
made as per DSR 1985. Clause No.13 reads as follows:
"13. As per the soil investigation, water table has been found at 209 mtr. as per the benchmark. No payment for working under the sub soil condition will be made if the water table rises to 210.0 mtr. during the execution of the work. If it rises above that level i.e. 210.00 mtr., payment for excavation etc. will be governed by the item of working
under sub-soil as per DSR 1985."
(emphasis supplied)
5. Clause 73 of the contract reads as follows:
"73. Nothing extra over and above the rates provided in the schedule of quantities for execution in/or under water shall be paid for pumping and bailing out water i/c by any method lowering of sub-soil water level during execution of work."
6. In our view Clause 13 secifically deals with the situation where
the water table rises above 210 mts during the execution of the work.
In that situation the Contractor is entitled to payment for excavation
etc for working under sub-soil conditions as per DSR 1985. Clause 73
only puts a limitation on extra charging for pumping and bailing out
the water or lowering of water including by any method lowering of
sub-soil water level during execution of work. This only means that if
the water table is below 210 mts, the Contractor would not be entitled
to claim anything extra over and above the rates provided for in the
schedule of quantities for execution of the work, including for pumping
and bailing out water by any method of lowering the sub-soil water
level during the execution of the work. This clause cannot be
interpretated to mean that if the water level rises above 210 mts, the
Contractor would not be entitled to claim payment for excavation etc
at the rates applicable for carrying out sub-soil items of work as per
DSR 1985. Both clauses 13 and 73 have to be harmoniously construed
and we see no contradiction in that. If the interpretation of the
appellant were to be accepted, clause 13 would be rendered nugatory,
which could not have been the intention of the parties. In our view the
arbitrator correctly considered the above provisions and as the
appellant itself had found that the water level is more than 210
meters, awarded the amount to the respondent-claimant. The
interpretation given by the learned Arbitrator to the agreement clauses
is reasonable and plausible. That is another reason not to interfere
with the same.
7. No doubt the learned Single Judge had not analyzed the
above proposition but the conclusion of the learned Single Judge is
correct and since we have ourselves analyzed the clauses, we find no
merit in the challenge to the award of Claim No.2. On the same basis
claim no.3(C) as awarded by the Arbitrator as also escalation on claim
nos. 2 and 3(c) awarded under Claim No.7 cannot be faulted.
Accordingly we dismiss the present appeal.
8. The Registry is directed to release the amount deposited in
this Court to the respondent along with interest accrued thereon by
08th May, 2009. In case the respondent is able to satisfy that the
amount received by it does not satisfy the decretal amount, it is open
to the respondent to recover the balance amount in execution after
taking into account the amount withdrawn from this Court.
MUKUL MUDGAL, J.
VIPIN SANGHI, J.
MARCH 23, 2009 RSK
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!