Citation : 2009 Latest Caselaw 915 Del
Judgement Date : 20 March, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ A.A. No. 403/2007
%20.03.2009 Date of decision: 20.03.2009
M/S MODERN SUPPLIERS ....... Petitioner
Through: Mr. Gurdeep Pal Singh, Advocate
Versus
UNION OF INDIA & ANR. ....... Respondents
Through: Mr Jitendra Kumar Singh, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1. The disputes between the parties are stated to be arising out of
a works contract dated 22nd November, 1996 placed by the
respondent Railways on the petitioner. The date of completion
thereof was on 21st May, 1999. The work is stated to have been
completed by 31st March, 2002. It is the plea of the petitioner that
the respondent however delayed the preparation of the final bill,
even after the maintenance period of six months expired on 30th
September, 2002. It is, further the case of the petitioner that the
petitioner was informed that unless the petitioner was ready and
willing to sign the addendum and corrigendum and also on
supplementary agreement appended with the main agreement, the
final payment would not be released to the petitioner. The petitioner
further claims to have been informed that to be able to receive the
final payment it will have to relinquish its claims for escalation, extra
expenses, refund of recoveries etc. The petitioner claims to have
written a letter dated 16th January, 2003 to the respondent in this
regard. Though the receipt of the said letter is not denied, no reply
is stated to have been given to the same. The respondent is stated to
have prepared a payment of Rs.3,86,062/- under the final bill. The
same was released to the petitioner on 24th January, 2003, according
to the petitioner after the petitioner had signed the supplementary
agreement, addendum etc. It is further the case of the petitioner that
it wanted to sign the final bill under protest but was not permitted to
do so.
2. The petitioner after receiving payment on 24th January, 2003,
for the first time, wrote a letter dated 10th April, 2003 stating that it
was compelled to sign the final bill and other documents. The
petitioner by the said letter also invoked the arbitration clause.
3. The petitioner followed up with its letter dated 2nd December,
2003. The respondent Railways vide its letter dated 13th January,
2004 informed the petitioner that the petitioner having signed the
No Claim Certificate on its final bill and having also singed the
supplementary agreement, the arbitration clause contained in the
principal agreement had ceased to have any effect and was deemed
to be non-existent for all purposes.
4. The petitioner made representations dated 11th February,
2004, 3rd March, 2004 & 20th July, 2004. Finally, a letter dated 21st
September, 2004 was sent by the respondent stating that the matter
had been re-examined and the claims found not referable to
arbitration being excepted matter under clause of 63 of GCC1999
applicable to the contract. Reference was also made to the earlier
letter dated 13th January, 2004 which was stated to be holding good.
5. The petitioner sent another letter dated 10th November, 2004
stating that GCC1989 and not GCC1999 was applicable to the
contract and again asking the respondent to re-consider the matter.
6. The respondent vide its letter dated 3rd December, 2004 wrote
that there was a typographical error in the earlier letter dated 21st
September, 2004 and accepting that GCC 1989 was applicable. It
was further conveyed that the office letter dated 13th January, 2004
held good.
7. There is no communication on record after 3rd December,
2004. Ultimately this application under Section 11(6) of the Act
came to be filed on 10th September, 2007. The respondent Railways
filed a reply contending inter-alia that the claims made by the
petitioner for Rs.4,00,000/- for balance amount of escalation and
Rs.1,50,000/- as increased cost after expiry of original completion
date and till execution and completion of works are excepted matters
covered by clauses 21.5 and 9.2 of the special conditions of contract.
Reliance in this regard is placed on General Manager, Northern
Railways Vs. Sarvesh Chopra AIR 2002 SC 1272.
8. It is further pleaded that as many as nine extensions for
completion of work were granted to the petitioner with frozen
indices PVC as of 15th September, 2001. It is further pleaded that
the petitioner after signing the supplementary agreement and in
which it is recorded that the arbitration clause contained in the
principal agreement shall cease to have any effect and shall be non
existence for all purposes is not entitled to invoke the arbitration
clause. The other claims of the petitioners are also disputed but we
are in this application not concerned with the said disputes between
the parties.
9. I have recently in M/s S.K. Sharma Vs. Union of India
MANU/DE/0147/2009 dealt with the plea of maintainability of
arbitration after signing such an agreement. Relying upon National
Insurance Co. Ltd. Vs. Boghra Polyfab Pvt. Ltd.
MANU/SC/4056/2008 it was concluded that depending upon the
facts of each case and conduct of the parties it has to be determined
whether the full and final settlement discharges the arbitration
agreement in the original contract or not.
10. As far as the present case is concerned, admittedly the
petitioner, prior to signing the agreement rescinding the arbitration
clause, had vide letter dated 16th January, 2003 written that it was
being coerced to sign the said documents to be able to receive the
amounts due according to the respondent also to the petitioner
under the final bill. The petitioner had in the said letter also
informed the respondent that it will be entitled to invoke the
arbitration clause even after signing such documents. It is not
disputed that the final payment was released to the petitioner only
after it signed the said documents. The petitioner within a month of
receiving the final payment invoked the arbitration clause on 10 th
April, 2003. All these factors show that the full and final settlement
and/or recession of contract was not consensual and there was an
element of coercion in the same, which has been deprecated by the
Apex Court in Boghra Polyfab (supra).
11. The respondent Railways, however, vide letter dated 13th
January, 2004 rightly or wrongly refused the request of the
petitioner for arbitration. What is of significance is that the petition
has been filed after more than three years thereof, on 10th
September, 2007. Of course, the respondent even after 13th January,
2004, on 21st September, 2004 and 3rd December, 2004 both within
three years prior to the institution of the petition again refused the
request of the petitioner for arbitration, however, relying upon the
earlier letter dated 13th January, 2004 and also stating therein that
two of the claims fell within excepted matters. The petitioner even
after the last letter waited for two years and nine months to file the
petition.
12. In my view, the petitioner is not entitled to succeed on this
ground alone. The petitioner has allowed the matter to become stale.
The Apex court in SBP & Co. Vs. Patel Engineering Ltd. (2005) 8
SCC 618 has held that while exercising the power under Section
11(6) the question whether the claim was a dead one or a long
barred claim that was sought to be resurrected and whether the
parties had concluded the transaction by recording satisfaction of
their mutual rights and applications or by receiving the final
payment without objection has to be adjudicated. I find the claim in
the present case in the entirety of the facts and circumstances to be
such.
13. There was an element of finality to the letter dated 13th
January, 2004 of the respondent. The petitioner merely by making
repeated representations cannot revive a claim which has become
time barred. The record does not show that there was anything in
the conduct of the respondent to lead the petitioner to believe that
his claims were being considered. Merely because the respondent
Railways wrote letters dated 21st September, 2004 and 3rd
December, 2004 reiterating the stand taken in the letter dated 13th
January, 2004 and also adding thereto would not revive a claim
which had become time barred.
14. The nature of the claim of the petitioner is also relevant in this
regard. For the petitioner to succeed on the plea of coercion, there
has to be an element of urgency. The petitioner could have invoked
the arbitration clause at the time of writing the letter dated 16th
January, 2003 i.e., before signing full and final settlement; but the
petitioner did not do so because it had the urgency to receive the
monies due and which according to the petitioner were being denied
to it. If that be the position, then the petitioner ought to have acted
in right earnest after receiving the payments. The conduct of the
petitioner of having slept over its rights, if any, for a period over
three years disentitles the petitioner from after such long lapse of
time approaching this Hon'ble court for under Section 11(6) of the
Act. The petitioner by such long lapse of time has lost the right to
agitate coercion in the matter of signing of the supplementary
agreement, rescinding the arbitration agreement and full and final
settlement and has allowed the said documents to attain finality.
15. This court in Rajesh Kumar Garg Vs MCD 149 (2008) DLT
343 held the limitation for applying under Section 11(6) to be three
years from the accrual of cause of action. I find the cause of action
to have accrued to the petitioner in the present case, in any case on
13th January, 2004. The petition is barred by time.
16. Having held so, there is no need to adjudicate the plea of the
respondent of two of the claims falling in excepted matter.
17. The petition/application is dismissed. No costs.
RAJIV SAHAI ENDLAW JUDGE March 20, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!