Citation : 2009 Latest Caselaw 895 Del
Judgement Date : 19 March, 2009
IN THE HIGH COURT OF DELHI AT NEW DELHI
FAO (OS) 287 of 1994 & CM APPL Nos. 3799/94,
1335/95, 186/95, 386/2002
Date of decision : March 19, 2009
INTERNATIONAL AIRPORT AUTHORITY
OF INDIA ..... APPELLANT
Through: Mr. J.P. Sengh, Senior
Advocate with Mr. Krishan Kumar,
Mr. Mukesh Kumar and Mr. Sumit,
Advocates
versus
M/S. M.L. DALMIYA & CO. LTD ..... RESPONDENT
Through: Mr. R.K. Watel, Advocate
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE DR. JUSTICE S. MURALIDHAR
1. Whether Reporters of local papers may be
allowed to see the judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be reported Yes
in Digest?
JUDGMENT
19.03.2009
S. MURALIDHAR, J.
1. This appeal is directed against the impugned order dated 7 th
October 1994 passed by the learned Single Judge in Suit No.
1465 of 1991 and IA Nos. 8060 of 1991 and 296 of 1992.
2. The facts leading to the present appeal are that in December
1977, a global tender was invited by the Republic of Maldives
to upgrade the existing airport of Hulule Island. The Appellant,
International Airport Authority of India („IAAI‟), submitted its
tender to the Government of Maldives on 12 th December 1977.
On 28th February 1978 the Government of Maldives decided to
award the tender to the IAAI for a sum of US $1,07,43,881.92.
The site was handed over to the IAAI on 22nd March 1978. In
terms of the contract the site installation including mobilization
of plant, machinery and material, tools etc. and also
construction of temporary structures had to be completed by
21st July 1978 so that the entire work could commence on the
very next date i.e. 22nd July 1978. In terms of the agreed time
schedule the work had to be completed by 21st December 1979.
3. On 8th March 1978 a back to back agreement was entered
into between IAAI and the Respondent M/s. M.L. Dalmiya &
Co. Limited (MLD) whereunder MLD was to be the
"Construction Associate" to IAAI and had to execute the whole
work for a total sum of US $ 96,82,931.92. On 2nd May 1979 a
sum of US $ 13,43,367.39 was paid by the Appellant IAAI to
MLD as mobilization advance. A sum of US $ 1,79,500 was
paid to MLD as bridging finance. It is the case of MLD that the
fact that it was to execute the whole work on behalf of IAAI
was not disclosed by IAAI to the Government of Maldives. In
terms of the contract MLD was to receive 93.11% of each
running bill and final bill raised by IAAI to the Government of
Maldives. The work of construction of the terminal building
was also awarded to MLD on 21st August 1998. This had to
commence within 30 days of the delivery of the site and be
completed within 24 months. The site was delivered on 22nd
March 1978 and the work had to therefore be completed by 21 st
April 1980.
4. According to MLD out of the mobilisation advance of US $
16,11,559 received by IAAI from the Government of Maldives,
US $ 11,92,801 was given by IAAI to MLD on 2nd June 1978
and US $1,37,000 on 6th September 1978. The bridging finance
of US $ 8,00,000 received by IAAI from the Government of
Maldives was not released to MLD. However, admittedly IAAI
incurred an expenditure of US $ 1,99,956 on behalf of MLD.
The site mobilisation, barring a few pieces of machinery, could
be completed by MLD only on 31st October 1978. According to
IAAI the delay in releasing the mobilisation advance to MLD
was on account of MLD‟s failure to obtain ECGC cover. On the
other hand the case of MLD was that IAAI had to obtain ECGC
cover in a manner that advantage of the same could be taken by
MLD. Further according to MLD although it supplied the
sample of the concrete work to the IAAI in April 1978, six
weeks before the starting of the work, the approval of IAAI was
conveyed to it only on 11th October 1978. The approval for the
Bitumen was not given even up to 10th January 1979, the date
on which the contract was terminated by IAAI. The causeway
for facilitating off loading of machinery brought by ships was
not provided by the Government of Maldives even till the
termination of the contract. As a result ships carrying
machinery for the project had to be anchored five miles away
from the shore and the cargo had to be loaded on to smaller
crafts to be brought ashore. This severely affected the progress
of the work. IAAI had to arrange, at the instance of MLD, to
airlift some of the machinery for fear of the contract being
terminated by the Government of Maldives on account of the
time overrun. Work on the runway to be completed in three
phases made little progress. The resident engineer furnished to
MLD the revised design of the first phase of the runway only on
16th August 1978.
5. On account of the above disputes between the parties, the
agreement was terminated by the IAAI on 10th January 1979.
The project was thereafter completed by the IAAI on 30th
September 1981 at the risk and cost of the Respondent.
Contending that it had incurred a loss of Rs.63,14,541.02 the
IAAI raised a claim in that sum against the Respondent. IAAI
further claimed an amount of US $ 8,55,903.80 being the
balance of the sum advanced to MLD for purchase of plant and
machinery. IAAI filed an application being Suit No.122-A of
1979 in this Court under Section 20 of the Arbitration Act 1940
(„Act‟). By an order dated 18th March 1982, this Court directed
IAAI and MLD to appoint one Arbitrator each. IAAI appointed
Sri V.R Vaish and MLD appointed Shri M.S.Iyengar as
Arbitrator. The said Arbitrators appointed Shri K.B.Asthana, a
retired Chief Justice of the High Court of Allahabad as Umpire.
While IAAI made 8 heads of claims, MLD made 16 heads of
claims before the Arbitrators. The Arbitrators could not reach
an agreement between themselves in respect of the Award and
the matter was referred by them to the Umpire. An Award was
given by the Umpire on 15th April 1991. MLD‟s claims were
accepted in part whereas those of the IAAI were rejected.
6. MLD then filed a Suit No. 1465 of 1991 in this Court under
Section 14 of the Act in which pursuant to the notice issued the
learned Umpire filed the Award in Court. Both parties filed
their objections to the Award and the following issues were
framed by the learned Single Judge:
(i) Whether the Award is liable to be set aside or modified in view of the objections filed by the parties.
(ii) Relief.
By the impugned order dated 7th October 1994 the learned
Single Judge dismissed the objections filed by the IAAI and
directed the Award to be made rule of the Court. Aggrieved by
the impugned order of the learned Single Judge the IAAI has
filed the present appeal.
7. We have heard submissions of Mr. J.P. Sengh, learned Senior
counsel appearing for the Appellant and Mr. R.K. Watel,
learned counsel appearing for the Respondent.
8. One of the objections raised by IAAI is that the reasons given
by MLD for the delay, which were accepted by the Umpire,
were unsustainable as these were not supported by the
documents on record. According to the Appellant, the finding in
this regard is either based on no evidence or is an error apparent
on the face of the Award.
9. The above submissions have been considered by this Court.
It is noticed that the dredging channel that had to be provided
by the Government of Maldives was in fact provided only in
April 1980, after the termination of the contract. The delay in
this regard was not due to the fault of MLD but that of the
Government of Maldives. Therefore, it is not possible to take
the view that the Umpire had committed an illegality in coming
into conclusion that the delay was not on account of MLD. The
finding of the Umpire is based on a correct appreciation of the
documents on record. This court concurs with the learned
Single Judge that there is no provision in the contract which
indicates that time is the essence of the contract. This Court
further agrees that even if there was any delay attributable to
MLD in the execution of the contract, that was not a justifiable
ground for the IAAI to terminate the contract.
10. The next ground urged by the IAAI concerned the release of
the mobilization advance obtained by MLD without obtaining
ECGC cover. The learned Single Judge held that the Umpire
has dealt with this aspect in detail by referring to the relevant
documents and held that there was no ground made to interfere
with the said finding. We are also unable to find any perversity
in the impugned order of the learned Single Judge on this aspect
that calls for interference.
11. Mr. Sengh advanced extensive arguments as regards MLD‟s
Claims 2, 4, 6 and 7. Claim No.2 was for a sum of US $ 58,255
being the cost of furniture, jeeps, equipments etc., which was
purchased by MLD as per the orders of IAAI for which no
payment was made by the latter to MLD. It was urged by IAAI
that some of the items of claim covered by Claim No.2 are
already covered in Claim No.1. This was disputed by Mr. R. K.
Watel, learned counsel for the Respondent MLD who pointed
out that such a contention was never raised by IAAI before the
Arbitrators. According to him factually also this contention is
untenable since Claim No.1 was restricted to works executed
and materials supplied for construction whereas Claim No.2
covers 15 items directed by IAAI to be purchased by MLD
towards building a lab and an office. He referred to the original
purchase vouchers in support of the 15 items of furniture which
MLD placed in support of its Claim No.2 before the Arbitrators
and for which no evidence in rebuttal was led by IAAI.
12. There appears to be merit in the submission of the learned
counsel for the Respondent MLD. This Court finds that in their
reply to MLD‟s Claim No.2, the IAAI took the following stand
before the learned Arbitrators and Umpire:
"The claimant further submits that in so far as Respondent‟s Claim No.2 is concerned, the same relates to the payment of certain items alleged to have been ordered by the Claimant for purchase on their behalf. The Respondents have furnished details of this claim at Pages 91 and 92 - Annexure „B‟ of the statement of facts. The Claimants do not dispute the same in so far as all the 15 items and the quantity of each item as considered by the Respondents in the said Annexure 'B'. The dispute is only regarding the valuation for which the Claimants will make separate submissions." (emphasis supplied)
Clearly therefore the issue was not in respect of „duplication‟ of
claims but their valuation. The learned Umpire has at internal
page 44 of the Award held that MLD‟s Claims 2,5,6 and 7
"stand independently on their own merits as decided hereafter."
The Single Judge has dealt with this contention in a great detail
and has concurred with the view taken by the Umpire. Having
considered the documents on record, we are not inclined to
interfere with the concurrent findings of the learned Umpire and
the learned Single Judge.
13. Arguments were next addressed in respect of MLD‟s Claim
No. 4 in the sum of US $ 85,29,300 being the alleged loss/
damage suffered by MLD with regard to the non-return of the
MLD‟s machinery, tools, plant etc. which were owned by and
brought to the site by MLD. Claim No.4 was later limited by
MLD to US $ 62,45,1000 by restricting the hire charges (for 24
of the 47 items) from 28th April 1980, which was the stipulated
date of completion, till 10th January 1984. Under Claim No.7,
MLD had claimed US $25 lakhs being the depreciated value of
the 47 items of plant and machinery owned by it and brought to
the site but not returned by the IAAI inclusive of interest @18%
per annum from 22nd April 1980 till 21st October 1988. The
learned Umpire allowed Claim No.4 to the extent of awarding
hire charges for 24 items for the period 1 st October 1981 till 1st
January 1984 treating the same as non-operational period and at
50% of the contract rates, in the sum of US $4,78,467. As
regards Claim No.7, he awarded MLD a sum of US $5,94,162.
The contention of the learned Senior counsel for the IAAI was
that the Umpire had allowed hire charges as well as full cost for
the same items under Claim No.7 and therefore MLD was being
paid much more than what it is entitled to. Learned counsel for
the Respondent on the other hand submitted that IAAI never
informed MLD that it was appropriating the machinery and this
was why MLD asked for damages in the form of hire charges
and return of machinery. In the alternative it claimed damages
and the depreciated cost of the machinery on the date of filing
its claims.
14. To this Court it appears that the reasons given by the
Umpire for partly allowing the Claims 4 and 7 are cogent.
During the period the contract was in force, and till its
subsequent completion by the IAAI, the machinery was under
IAAI‟s possession and not in control of MLD although
admittedly they belonged to MLD. Award of the 50% of the
contractual hire charges for 24 of the 47 items and that too
restricted to the non-operational period as damages cannot be
said to be illegal or unreasonable. Likewise the award of the
depreciated value of the said machinery and plant under Claim
7 cannot be said to be a duplication as they pertain to the fact of
non-return of the machinery even after the completion of the
contract period. The conclusion of the learned Single Judge
accepting the award in this regard cannot therefore be faulted.
15. MLD‟s Claim No.6 was for the depreciated value of the
temporary structures raised by it for various site offices,
quarters etc. and for the depreciated value of the furniture used
therein. The claim was reduced by MLD from US $ 2,20,687 to
US $ 1,76,814. The umpire awarded only the salvage value of
the structure and the depreciated value of the furniture used
therein. The Umpire has appreciated the evidence produced by
MLD in the form of documents and arrived at the said
conclusions. Nothing has been shown by the learned Senior
counsel for the Appellant to persuade this Court to hold that the
said conclusion is erroneous or perverse or contrary to the
record.
16. For the aforementioned reasons, this Court is unable to find
any perversity as regards the concurrent findings of both the
learned Umpire as well as the learned Single Judge. The appeal
is, accordingly, dismissed. The pending applications also stand
dismissed.
S. MURALIDHAR, J.
CHIEF JUSTICE
MARCH 19, 2009 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!