Citation : 2009 Latest Caselaw 757 Del
Judgement Date : 5 March, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: 13.2.2009
Date of Order: 5th March, 2009
Arb. P. No. 169/2008, Arb. P. No. 448/2008 & Arb. P. No. 449/08
% 05.03.2009
M/s Simplex Infrastructure Ltd. ... Petitioner
Through: Mr. P.C.Markenda, Sr. Advocate with
Mr. Naresh Markenda & Mr. Kamlesh Mahajan, Advocate
Versus
M/s D.S.Construction Ltd. ... Respondent
Through: Mr. A.S.Chandhiok, Sr. Advocate with
Mr. Ashish Dholakia, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
By this application/petition (Arb.P.-169/2008) under Section 11 of
the Arbitration and Conciliation Act, 1996 the applicant/petitioner has prayed for
appointment of an independent and impartial second arbitrator by this Court on
behalf of the respondent to constitute Arbitral Tribunal to adjudicate the disputes
raised by the applicant.
2. The applicant contended in the petition/application that he had
entered into three contracts with the respondent as mentioned below:
(1) Conversion of Delhi-Gurgaon section of NH-8 into Access Controlled Highway from KM 13.60 to KM 42.00 for Execution of Flyover Works at Mahipalpur & IGI Link Road, Shankar Chowk-Kendriya Vihar (Udyog Vihar), IFFCO Chowk and Rajeev Chowk-Sohna Gurgaon Junction. Contract No. DSCL/Struct-4/2004, dated 1.3.2004
(2) Conversion of Delhi-Gurgaon section of NH-8 into Access Controlled Highway (Delhi Sector) from KM 13.60 to KM 23.96 - Package P1- Piling Work. Contract No. JIL/P-1/2002, dated 2.12.2002
(3) Conversion of Delhi-Gurgaon section of NH-8 into Access Controlled Highway (Haryana Sector) from KM 23.96 to KM 42.00 - Package P2
- Piling Work. Contract No. DSCL/P-2/2002, dated 2.12.2002
3. All the above three contracts were similarly worded and provided
for a settlement of disputes in terms of Clause 38 of each of the contract. The
procedure laid down for settlement of dispute provided that initially an attempt
was to be made for settling the disputes amicably, if amicable settlement was not
possible, then the disputes were to be referred to the arbitration of an Arbitral
Tribunal of three arbitrators; each party to appoint one arbitrator and third one to
be appointed by the two arbitrators.
4. The petitioner submitted that the three contracts were completed by
it to the satisfaction of the respondent and the toll road constructed by petitioner
was opened to traffic by the respondent and the respondent was earning revenue
out of the same. However, the claims of the petitioner regarding the three
contracts have not been settled despite petitioner writing a number of
communications to the respondent for amicable settlement. The respondent had
initially appointed Mr. S.K.Jain (Senior Advisor, Billing) from their side for
resolving the disputes. The petitioner also appointed its nominee and made an
attempt to settle the dispute amicably. However, no amicable settlement could
be arrived at and a number of excuses were given for denying the petitioner's
claims. The petitioner's initial name was M/s Simplex Concrete Piles and later on
petitioner changed its name to M/s Simplex Infrastructures Limited and the bills
were being raised by the petitioner under this changed name and were being
duly honored by the respondent in this name but the respondent even raised the
issue of name of the petitioner for denying the claims of the petitioner. Since,
mutual settlement failed, the petitioner vide letter dated 26/27.2.2008, invoked
the arbitration clause contained in all the above three contracts and informed the
respondent that it had appointed Mr. Justice P.K.Palli (Retd.), H.No. 246, Sector
19-A, Chandigarh as its Arbitrator and called upon the respondent to appoint its
nominee within a period of thirty days from the date of communication. However,
respondent failed to nominate its arbitrator within thirty days. The petitioner
therefore, filed this application before the Court for appointment of Arbitrator on
behalf of the respondent. The petitioner has mentioned list of his claims in the
para 14 of the petition/application. A prayer is made that the second arbitrator be
appointed by the Court and third Arbitrator shall be appointed by the two
arbitrators.
5. In reply to this application, the respondent had taken preliminary
objection that the petition was not maintainable since a single petition was filed
for appointment of arbitrator for three different contracts and this was not
permissible. It is submitted that Section 11(6) of the Arbitration & Conciliation Act
can be invoked only for one contract. These three contracts could not be
considered as one composite contract, neither it was the intention of the parties
nor it was agreed that one single arbitrator would deal with the three contracts.
All the three contracts had separate arbitration clause and therefore have to be
dealt separately. It is stated that a single composite notice of arbitration sent by
the applicant was no notice in the eyes of law. However, without prejudice to
these contentions, respondent stated that by way of reply to the notice, the
respondent vide its letter dated 29.3.2008 had agreed to the arbitration and told
the petitioner as under:
"We shall be appointing our Nominee Arbitrator, as per law and according to the Arbitration and Conciliation Act, 1996, within the stipulated time period, therein, separately for each of the three contracts."
6. It is submitted that respondent only deferred the appointment of the
arbitrator as the notice was not a valid and complete notice. However, petitioner
failed to respond to the letter of the respondent for a long time consequently,
respondent vide letter dated 24.5.2008 appointed Mr. A.K.Jain, Kavi Nagar,
Ghaziabad as its nominee Arbitrator in respect of the contract no.1 (referred
above). The respondent also appointed Mr. K.K.Mutreja, J-229, Sector 25,
Noida, UP as its nominee arbitrator for rest of the two contracts. It is submitted
that petitioner rushed to the Court prematurely and the petition was liable to be
dismissed.
7. During pendency of the petition, the petitioner filed two more
petitions/applications being Arb. P. Nos. 448/2008 & 449/2008 under Section
11(6) of the Arbitration and Conciliation Act, 1996 for appointment of Arbitrators
in respect of two contracts at sl.no. 2 & 3 in para 2 above so now there are three
arbitration petitions in respect of three different contracts. The leave was sought
vide IA No. 15444/2008 and in para 3 of this application, applicant/petitioner
stated that though Arb. P. No.-169/2008 was filed in respect of three contracts
but in order to obviate the objection taken by the respondent, the petitioner filed
separate arbitration applications in pursuance to the liberty sought from the
Court. Arb. P. No. 169/2008 be read as being confined to contract mentioned at
Sl. No. A [Contract No. (1) in para 2 above] only.
8. This application was allowed. In view of this application Arb. P. no.
169/2008 of the petitioner has to be treated only for one contract, the other two
petitions no. 448 & 449/2008 are in respect of other two contracts. The
respondent in response to the two petitions filed subsequently, has taken the
stand that respondent had appointed Mr. K.K.Mutreja as its nominee Arbitrator
and petitions have become infructuous.
9. During arguments, learned Counsel for the petitioner/applicant
stated that the respondent had lost right to appoint Arbitrator since the
respondent failed to appoint Arbitrator within the time provided in law i.e. within
30 days. He stated that the Arb. P. No-169/2008 was listed before the Court for
the first time on 2.5.2008 and the order of the service of notice of the issued by
the Court and appointment of Arbitrator by the respondent was made on
24.5.2008. The petitioner also argued that there was no infirmity in the petition
no. Arb.P. 169/2008 when it asked for appointment of a combined arbitral tribunal
for the three contracts and relied upon Gas Authority of India Ltd. & Anr. v. Keti
Construction (I) Ltd. (2007) 5 SCC 38 wherein the Supreme Court had upheld the
appointment of an Arbitrator for four contracts observing that there was no
requirement of law that for each of the contract a separate panel ought to have
been formed. The same panel could be very well utilized for the disputes arising
out of the other contracts between theparites.
10. This issue has become redundant since petitioner itself had chosen
to make an application that initial petition be considered restricted to only one
contract and the petitioner simultaneously filed two more petitions. As far as right
of the respondent to appoint Arbitrator is concerned, I consider that in view of the
judgment of Supreme Court in Northern Railway Administration, Ministry of
Railway, New Delhi v. Patel Engineering Company Limited (2008)10SCC 240, it
is incumbent upon the Court that while considering the application under Section
11 of the Arbitration and Conciliation Act, the effort of the Court should be to
adhere to the contract between the parties and to give effect as closely as
possible to the Arbitration Agreement entered into between the parties. The
Supreme Court observed that the Court may ask to do as what has not been
done and the Court must first ensure that the remedies provided for, are
exhausted. It was not mandatory for the Chief Justice or any person or institution
designated by him to appoint the named arbitrator or arbitrators, but at the same
time, due regard has to be given to the qualifications required by the agreement
and other considerations.
11. In the present case, the agreement provides for appointment of a
panel of three arbitrators; one to be appointed by each party and the third one to
be appointed by the two arbitrators. The petitioner has already named its
arbitrator. The respondent nominated its arbitrator on 24.5.2008 before
respondent received notice of this petition. The respondent had informed to the
petitioner about its willingness to appoint arbitrator in March'08 itself and the
petitioner was to provide some more information to the respondent. The
petitioner could have after providing information to the respondent asked the
respondent to appoint an arbitrator as the respondent had shown its willingness
to refer the matter to arbitration and matter could have referred to the arbitrators,
so appointed.
12. I consider that in this case the respondent has not lost the right to
appoint Arbitrator. The respondent after receipt of combined notice for three
contracts did respond to the notice though denied the claim of the petitioner and
certainly showed its willingness to refer the matter to the Arbitral Tribunal. There
was a delay in appointment of arbitrator on the part of the respondent, but the
arbitrator was appointed before respondent received notice from the Court.
Under these circumstances, I consider that arbitrator appointed by the
respondent would be the proper arbitrator in terms of agreement and the two
arbitrators can than appoint an umpire (third arbitrator). However, the
respondent has appointed two different arbitrators for the three contracts, I
consider that it would be appropriate that the same Arbitral Tribunal decides the
disputes relating to the three contracts. The arbitrator Mr. K.K.Mutreja, appointed
by the respondent for two of the contracts shall be considered as arbitrator for
the disputes regarding all the three contracts. Thus, the Arbitral Tribunal shall
consist of three arbitrators viz. Mr. Justice P.K.Palli (Retd.), H.No. 246, Sector
19-A, Chandigarh, Mr. K.K.Mutreja, J-229, Sector 25, Noida, and the third
arbitrator to be appointed by the two arbitrators. All the three petitions are
disposed of in terms of this order.
March 05, 2009 SHIV NARAYAN DHINGRA, J. vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!