Citation : 2009 Latest Caselaw 723 Del
Judgement Date : 3 March, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO(OS) No.43/2009
Reserved on: 24th February 2009
rd
Date of Decision : 3 March 2009
VIVEK JAIN .....Appellant
Through Mr. Shiv Khorana, Adv.
versus
UNION OF INDIA .....Respondents
Through None.
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers
may be allowed to see the judgment? No
2. To be referred to the Reporter or not? Yes
3. Whether the judgment should be
reported in the Digest? Yes
% JUDGMENT
FAO(OS) No.43/2009 Page 1 of 12
MUKUL MUDGAL,J.
CM 1898/2009 (delay)
For the reasons mentioned in the application, the same is allowed. The
delay in filing the appeal is condoned. The application stands disposed of.
FAO(OS) No.43/2009
1. With the consent of the learned counsel for the appellant, the appeal is
taken up for hearing.
2. This appeal challenges the judgment of the learned Single Judge dated
th 25 February 2009 delivered in the Civil Suit (OS) No.584-A/1999, in which
th the challenge was raised to the award dated 27 January 1999 in the petition
filed under Section 30 and 43 of the Arbitration and Conciliation Act, 1996.
3. The brief facts of the case are as under:
a) The dispute in the present case arises from inviting of tender by the
respondent Union of India for the disposal of "B"-Thermal Power Station at
Raj Ghat (DESU). The appellant/claimant Vivek Jain had responded to the
said tender and offered a sale value of Rs.1,61,11,007/-.
b) Accordingly, the contract was placed on the appellant for the disposal
of thermal power station on 3rd December 1986. The appellant was to
deposit the sale value for the plant within the stipulated period and the
earnest money of Rs.1 lakh was deposited by the appellant. Upon the
appellant failing to deposit the sale value by due date, the contract was
cancelled at the appellant's risk.
c) Thereafter the appellant again participated in the second tender for the
sale of the plant which was opened on 10th December, 1987 and the appellant
had quoted the sale price of Rs.1,65,61,007/-. The appellant/claimant had
also furnished a security of Rs.1 lakh.
d) The appellant/claimant again failed to make payment of the sale value
of the thermal power station in a phased manner as stipulated in the contract
in spite of several extensions granted to the appellant and consequently,
again the contract was cancelled at the appellant's risk on 16 th September
1988. Prior to the cancellation of the contract, the appellant deposited a sum
of Rs.44,06,251/- with the respondent.
e) The third tender was opened on 29th September, 1988 where the
appellant was not a successful tenderer and consequently, the appellant
raised the dispute regarding the refund of the part deposited amount which
led to the reference to the arbitrator as per the agreement between the parties.
In his statement of claim, the appellant/claimant raised a claim of
Rs.72,44,585/- with 18% interest per annum from 1st January 1991. The
details of the appellant's claim are as follows:
"i) Refund of amount deposited Rs.44,06,251/-
ii) Refund of first security Rs.1,00,000/-
iii) Refund of second security deposit Rs.1,00,000/-
iv) damages Rs.5,00,000/-
v) Interest @ 18% per annum from due
date till 31.12.90 Rs.21,38,334/-"
f) The arbitrator had allowed the claim No(i), (ii) and (iii), though the
claim for damages of Rs.5,00,000/-, i.e., claim No.(iv) was rejected. Interest
@ 18% per annum on the awarded amount with effect from 23rd September
1991 till the realization of the amount was also awarded.
g) It was also held that the counter claim of Rs.26,601/- filed by the
respondent was already rejected by the earlier award dated 23rd September,
1991.
h) The respondent Union of India challenged the said award dated 23rd
September, 1991 before the learned Single Judge of this Court wherein the
respondent contended that the arbitrator had misconducted himself by
arriving at a finding that the entire amount of Rs.44,06251/- was wrongly
withheld. In fact, this amount was not withheld but was adjusted towards
compensation charges of Rs.41,05,379/- due from the appellant for the
delayed payment and towards ground rent of Rs.10,66,465 payable by the
appellant. The respondent also contended that the levy of compensation
charges and the ground rent was as per the terms of the contract which was
totally ignored by the arbitrator. It was also submitted by the respondent
before the learned Single Judge that the extensions were sought by the
appellant for making payments, which clearly made the appellant/claimant
liable for payment of compensation charges as well as ground-rent. Thus,
the finding of the arbitrator regarding withholding the amount of
Rs.44,06,251/- was not justified. The respondent's counter claim in respect of
Rs.26,601/- was rejected and in doing so, the fact that this Court had already
set aside the earlier award was totally ignored.
i) The respondent further contended that the arbitrator erred in ignoring
the compensation charges and ground rent which was part of the contract.
Consequently, the arbitrator had wrongly allowed the payment of earnest
money which was forfeited by the Government when the appellant failed to
make payment of the amount of the contract and failed to perform the
contract. Similarly, the earnest money was forfeited as per the contract
which was ignored by the arbitrator. Finally the award was also challenged
on the ground that the arbitrator could not allow the interest @ 18% per
annum from the date of first award.
j) The learned Single Judge in the impugned judgment dated 25th
February 2008 held as under:
i) The arbitrator rendered his award with reference to the terms of
the contract between the parties;
ii) The appellant had not challenged the cancellation of the
contract or the forfeiture of the security amount which was done in
accordance with the terms of the contract. Clause 6 of the tender
documents provides "Should the tenderer fail to observe and comply
with the foregoing stipulation, the amount deposited as a security
for the performance of the foregoing stipulation shall be forfeited to
the Government."
iii) The arbitrator could not have ignored the above clause particularly in
view of the fact that the cancellation of the second contract was challenged
by the appellant and upheld right up to the Hon'ble Supreme Court. Thus,
the non-performance by the appellant and the terms of the contract were
ignored by the arbitrator and the Claim No.(iii) was wrongly allowed in
favour of the appellant. Thus, the arbitrator has travelled beyond the scope
of the reference and the award was liable to be set aside and such conduct of
the arbitrator amounted to misconduct.
The payment clause of the contract reads as under:
"The buyer shall make payment for the goods purchased into the State Bank of India/Nationalized Banks at such place as the Director shall specify
and by the date fixed. Extension, if any,in the date of payment and the period of such extension shall be at the discretion of the Director/Government. Extension, if any, shall be subject to the payment of compensation at the rate of 10% of 1% of sale value per day of default. The Deposit-at-Call receipt for the amount of compensation payable will be forwarded by the buyer before or along with DACR for the Sale value. Permission to remove or take delivery of the goods will only be given on production of the DACR for the Sale value and compensation where paid."
iv) The tender document was modified when the second contract was
released in favour of the appellant to the extent that the extension was to be
granted @ 20% of 1% of sale value per day of default and such letter was on
the record of the arbitrator.
v) The second extension was granted to the appellant by the letter dated
19th April 1988 and third extension on 19th May 1988 and thereafter again on
22nd July 1988. The relevant part of the letter dated 22nd July 1988 reads as
follows:
"..... However, on a very extraordinary case and although not bound to do so I hereby allow you:-
1) Payment of balance of the 25% of the cost of sale as provided in Clause IVA (ii) of the Sale Letter
th dated 8 January 88 plus compensation charges as per contract (to make up for 25% of total payment th to enable issue of SRO) by 10 1988.
2) To make payment of balance of the contract value, viz., Rs.1,23,20,756/- plus compensation charges as per contract within 30 days of the issue of SRO which will be issued by us immediately after receipt of payments from you as mentioned in para 1 above.
If compliance in toto as above is not make by you the sale letter mentioned in the subject will be liable to be cancelled and the stores in question will be disposed of at your risk and cost. Save as above this amendment to the sale letter is issued leaving all other terms and conditions of the sale letter remaining unaltered and is also without any prejudice to the terms and conditions of the sale letter and other rights available to the seller."
vi) The contract was cancelled due to conduct of the appellant in seeking
repeated unwarranted extensions. The cancellation of the contract was
challenged in this Court and thereafter in the Hon'ble Supreme Court, but the
cancellation stood affirmed by dismissal of the Special Leave Petition by the
Hon'ble Supreme Court against the judgment of the High Court against the
appellant/claimant. In respect of the claim of the claimant a suit and writ
petition were also filed. The writ petition was dismissed and the suit was not
pressed upon. Thereafter, the arbitration clause was invoked and the first
arbitrator held that unsuccessful challenge by the claimant to the termination
of the contract and the dismissal of the writ petition filed by the claimant
seeking the amount with interest and dismissal of the suit led to a clear
conclusion that the claimant was not entitled to refund of the amount so
claimed.
vii) The first award was challenged before this court and the Court directed
that the filing of the writ petition would not amount to res judicata against the
claim of refund and the same was to be considered on merits. The validity
of the cancellation of the contract having been upheld by the Hon'ble
Supreme Court the arbitrator was required to consider the refund of the
amount claimed by the appellant as per the contractual terms.
viii) It is undisputed that the appellant paid an amount of Rs.44,06,251/-
lakhs and period for payment was extended from time to time at the behest of
the appellant and the delayed payment had to be compensated as per the
terms of the contract by the appellant by paying penalty. On the basis of the
terms of the contract, a claim had been raised about the payment of
Rs.7,59,380/- as a compensation for delays.
k) The appellant was thus entitled to the refund of the total amount less
contractual compensation for delayed payment and not for the entire amount
as held by the arbitrator. Since the arbitrator had ignored the terms of the
contract, the entire amount of Rs.44,06,251/- was wrongly allowed in favour
of the claimant by him. The appellant was thus entitled to an amount of
Rs.44,06,251 - 7,59380.
4. The learned Single Judge also reduced the interest from 18% per
annum to 10% per annum pendentelite. Consequently, the award was
modified to the extent that the claimant was entitled to Rs.3646,871/- with
interest @ 10% per annum from 23rd September 1991 till the realization.
5. In our view, the learned Single Judge proceeded entirely on the basis
of the terms of the contract and Shri Shiv Khorana, the learned counsel for
the appellant has been totally unable to establish as to how the judgment of
the learned Single Judge could be faulted.
6. The conduct of the appellant evidently shows that it was the appellant
alone who was solely responsible for the delays, coupled with the fact that
the cancellation was upheld by the Hon'ble Supreme Court, the learned
Single Judge could not arrive at any other conclusion save and except that
the award of the entire amount of Rs.44,06251/- to the claimant by ignoring
the compensation payable as per the contract in the sum of Rs.7,59,380/- is
incorrect and liable to be interfered with. The arbitrator had totally lost sight
of the terms of the contract contained in the tender and the subsequent
correspondence between the parties which was most material and relevant
evidence, and the learned Single Judge has correctly analyzed and applied
the contractual terms. Accordingly, the appeal having no merits is dismissed
with no orders as to costs.
MUKUL MUDGAL, J.
VIPIN SANGHI, J.
March 03, 2009 dr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!