Citation : 2009 Latest Caselaw 712 Del
Judgement Date : 2 March, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: January 16, 2009
Date of Order: March 02, 2009
+ ARB. P. 210/2004
% 02.03.2009
Unitech ...Petitioner
Through: Mr. S.K. Maniktala with Mr. Alok Tripathi and Mr. Jeemon,
Advocates
Versus
J.K. Industries Ltd. ...Respondent
Through: Mr. T.K. Ganju Sr. Adv. with Ms. Meghalee, Ms. Rajeshwari, Mr.
Rajat Bhardwaj and Mr. Ranjan Narain, Advocates
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. This petition under Sections 14, 17 & 29 of the Arbitration Act, 1940
(hereinafter "the said Act) read with Section 151 of CPC has been preferred
by the petitioner for making the award dated 31st August 2004 a Rule of the
Court.
2. After notice of the award was served upon the respondent, the
respondent filed objections to the award under Sections 30, 33 of the said Act
and prayed that the award be set aside. The objections were raised by the
respondent on the ground that the learned Arbitrator had mis-conducted
himself in the proceedings and there were prima facie errors apparent on the
face of the record.
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 1 Of 8
3. Brief facts are that the respondent awarded a contract for construction
of a factory building and other civil and engineering works including laying of
foundations for equipment and machinery at Banmore Tyre Plant Site in
District Morena, Madhya Pradesh to the claimant. The claimant had been
sending running bills to the respondent every month on the basis of the work
executed by the claimant and joint measurement done by the claimant and
the Consultant appointed by the respondent. After the work was over, the
claimant submitted final bill. Initially, the respondent had appointed M/s DCL
as its Consultant. DCL remained as Consultant upto 17th running bill.
Thereafter, the respondent had appointed M/s GC Sharma as its consultant
for verification and checking of the bills. M/s GC Sharma did the work of
checking the running bills and final bill from 18th running bill onwards. In the
final bill the respondent raised a dispute about the correctness of
measurements. The measurements were verified by respondent's consultant
M/s GC Sharma. Annexure C-1/A, a document duly singed by the Chief
Engineer of the respondent and representative of M/s GC Sharma shows that
against a total bill of Rs.4,14,92,192.76 after checking and verification of the
bill by M/s G.C. Sharma, an amount of Rs.3,85,39,983.88 was cleared for
payment. However, the bill finally passed by the respondent and signed by
DN Rathi was of Rs.3,62,64,224.41. Since an amount of Rs.24,37,138.57 was
deducted in respect of the earth work and lead. This amount of Rs.3,62,64,
224.41/- was also not paid to the claimant. Thus the claimant sought a
reference of the dispute to the Arbitrator and the matter was referred to the
Arbitrator. Before the learned Arbitrator, the claimant initially made total 9
claims amounting to Rs.5,79,11,729.11. However, during proceedings, the
claimant gave up certain claims and the claim stood reduced to
Rs.4,61,80,970.74. During further proceedings after reconciling the accounts
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 2 Of 8 and payments received, the claimed amount was reduced and it stood
reduced to Rs.61,73,440.74. The final proceedings before the learned
Arbitrator and the award passed by learned Arbitrator shows that the claim
was further limited to Rs.47 lac only and claimant conceded that rest of the
payment has been received.
4. The respondent also filed six counter claims amounting to around Rs.
One crore. The learned Arbitrator gave full latitude to the parties to establish
their claims; and also appointed Local Commissioner for measuring the visible
items of the constructed portions. After spending more than 9 years in the
arbitral proceedings, he ultimately gave an award of Rs.47 lac to the claimant
towards principal amount. He awarded 15% simple interest from 1st April
1993 to 1st April 1997 and thereafter 12% simple interest from 1st April 1997
to 31st March 2002 on the principal amount and from 2002, the interest was
further reduced to 9% per annum. Thus the total interest from 1 st April 1993
till passing of the award was calculated and it amounted to Rs.66,62,250/-.
The future interest of 9% on the award was allowed if the payment was not
made by 31st March 2004. Rs.3 lac was allowed as costs of Arbitration.
5. Counsel for the objector/respondent vehemently argued that the
learned Arbitrator wrongly relied upon the document Annexure C1/A. It is
submitted that this document was an internal document of the objector and
the Arbitrator could not have relied upon this document. The award based on
this document was therefore bad and this was an error apparent on the face
of award. The other ground of challenge of the award by the objector is that
as per the contract, the total value of contract was fixed at Rs.218 lac and
was revised to Rs.220.35 lacs. The contract provided a permissible increase in
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 3 Of 8 value by 25% of the contract value and further provided that the value of the
extra items covered in the contract in no case were to exceed Rs.59,85,583/-.
Thus, as per the terms of the contract, the maximum of the contract could not
exceed Rs.335.28 lac, while the claimant claimed amount more than the total
contractual value of the contract and the Arbitrator allowed amount of Rs.47
lac which was beyond the contractual value. The Arbitrator could not have
travelled beyond the contract and the award was, therefore, bad in law.
6. During arguments, counsel for the respondent also pointed out the
difference between the total running bill and the final bills. He submits that
the final bill could not have been raised by claimant more than the total of the
running bills and the calculations mentioned in the final bill of claimant
exceeded the quantities as mentioned in the running bills. It is stated that
this difference in the quantities of the final bill and the running bills was
pointed out to the Arbitrator but the Arbitrator paid no attention to this and,
therefore, the learned Arbitrator mis-conducted himself during the
proceedings.
7. I consider that none of the objections raised by the respondent are
sustainable. A perusal of the award passed by the learned Arbitrator would
show that the Arbitrator had made all efforts to reconcile the disputes
regarding measurement. He also appointed a Local Commissioner on the
suggestions of both the parties. After Local Commissioner gave report, the
parties had prepared a chart of payable amounts against different items on
the basis of agreed measurements of many of the items. The efforts of
compromise, however, fizzled out. The measurement of the items so agreed
shows that the claims made by the claimant was on the basis of actual
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 4 Of 8 measurements of the area and the work done. The Local Commissioner's
report was ultimately rejected by the Arbitrator because both the parties after
taking several hearings and opportunities to arrive at a common basis did not
come forward with any common basis. The learned Arbitrator also found that
the Local Commissioner had exceeded his jurisdiction. He even included
measurement of hidden items which could not have been measured. He, in
his report, talked of defects in the building which was not his jurisdiction,
neither the part of commission. He also subjected some parts of the building,
after taking samples, to quality control testing which was also not part of his
commission. Considering the fact that the Local Commissioner exceeded the
commission, his report was rightly rejected by the learned Arbitrator.
8. The learned Arbitrator rightly relied upon the Annexure C-1/A. The
respondent/objector could not have claimed that this document could not be
relied upon by the learned Arbitrator as it was an internal document of the
objector. It was settled between the parties that all bills sent by the claimant
were to be referred to the Consultant appointed by the Objector and the
consultant was to verify the bills. This verification of the bill was to be done
by the consultant after joint measurement. This exercise of joint
measurement was to be done by the Consultant in presence of the
representatives of the claimant. Annexure C-1/A is the document prepared by
the consultant of the respondent/objector wherein he had reduced the final
bill of the claimant after doing verification of the measurement of the work
done by claimant. It was not open to the respondent not to agree with the
consultant and say that whatever has been written by the consultant was
beyond his authority. The stand taken by the respondent that Mr. R.S.
Chadha, the person deputed by M/s GC Sharma had no authority to do the
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 5 Of 8 measurement and arrive at the amount payable to the claimant is baseless.
All the pre-final bills and the final bill were checked by a person, deputed by
M/s GC Sharma and this summersault taken by the respondent was rightly
rejected by the learned Arbitrator. Similarly, the claim of the respondent that
another measurement was carried out by Mr. Somarajan, representative of
the claimant was rightly rejected. The learned Arbitrator had found that Mr.
Somarajan had resigned from the services of the claimant much before the
date of alleged joint measurement by the objector/respondent. I consider that
this joint measurement was a false boggy raised by the respondent.
9. As far as claim of the objector regarding exceeding total value of the
contract is concerned, I find that this plea is baseless. Clause 3 of the
agreement entered into between the parties which has been reproduced in
the award reads as under:
"3. This Contract comprises the construction of buildings, machinery and equipment foundations, other civil engineering works and all other subsidiary works connected therewith within the same site as may be ordered to be done from time to time by the company for the time being although such works may not be shown on the drawings or described in the said specifications or the said schedule of rates." (emphasis added)
10. The learned Arbitrator after going through the contract has come to
conclusion that the contract was item rate contract. It is also a fact that all
running bills were passed by the consultant appointed by the objector on the
basis of contract which prescribed item-wise rates and the total value of the
running bills itself exceeded the amount being stated by the objector as the
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 6 Of 8 total amount of the contract. Had the total amount of the contract been
limited, the running bills would not have been approved on the basis of item
rate and the measurement? The mere fact that the running bills were
approved on the basis of item rates and measurement shows that the
payment was to be made for the work executed on the basis of item rates.
The estimated value of the contract specified in the contract could not have
limited the value of the total contract. If this limitation had been there, there
would have been some clause about limiting the value of the running bills and
there would have been percentage payment prescribed of the total value of
the contract at different stages. The very fact that all running bills were to be
approved on the basis of the work done item-wise and rates approved in the
contract, the plea taken by the objector must fail. I find that the learned
Arbitrator in this case had remained within the four corners of the contract
and the award rendered by the learned Arbitrator is not beyond the
provisions of the contract and the award cannot be interfered on this ground.
11. It is settled preposition of law that Court while examining an award
under Sections 14 and 17 or under Section 30 and 33 of the Arbitration and
Conciliation Act does not act as an appellate court and cannot re-appreciate
the evidence and cannot rewrite the judgment either upholding the award or
rejecting the award. The Court has only to see that the learned Arbitrator has
not committed any error apparent on the face of it and the award is not
based totally on no evidence or the learned Arbitrator was not biased towards
one party or has not conducted the proceedings in a biased manner. No
procedural error or bias of the learned Arbitrator is reflected from the
proceedings of the arbitration. The award passed by the learned Arbitrator is
a reasoned award and I do not find any preposition of law relied upon by the
Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 7 Of 8 learned Arbitrator which is illegal. There is no error apparent on the face of
the award. The objections raised by the objector/respondent are baseless and
untenable. The same are hereby rejected. The petition filed by the petitioner
hereby succeeds. The award passed by the learned Arbitrator is hereby made
Rule of the Court. Decree sheet be drawn accordingly.
12. The petition stands disposed of in above terms.
March 02, 2009 SHIV NARAYAN DHINGRA J. rd Arb.P.210/2004 Unitech Vs J.K. Industries Ltd. Page 8 Of 8
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!