Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

V.Arindam Const Pvt Ltd vs Ircon International Ltd. & Anr.
2009 Latest Caselaw 1085 Del

Citation : 2009 Latest Caselaw 1085 Del
Judgement Date : 31 March, 2009

Delhi High Court
V.Arindam Const Pvt Ltd vs Ircon International Ltd. & Anr. on 31 March, 2009
Author: Shiv Narayan Dhingra
      * IN THE HIGH COURT OF DELHI AT NEW DELHI

                                   Date of Reserve: 26.03.2009
                                     Date of Order: 31.03.2009
OMP 374/2005
%                                         31.03.2009
     V.ARINDAM CONST PVT LTD.       ... Petitioner
                 Through: Mr.Sanjoy Ghose, Adv.

           Versus

     IRCON INTERNATIONAL LTD. & ANR ..Respondents
                 Through: Mr. Chandan Kumar, Adv.

JUSTICE SHIV NARAYAN DHINGRA

1. Whether reporters of local papers may be allowed to see
   the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?


Order

1.         By this Petition under Section 34, the petitioner has

assailed an award dated 1st July, 2005 passed by the sole

Arbitrator on the ground that the learned Arbitrator wrongly

rejected a part of the claims of the petitioner and allowed only

a part of the claims.


2.         A   contract   was   entered   into   between    IRCON

International Limited and the petitioners, M/s. V. Arindum

Construction Pvt. Ltd. and Vinod Kumar (a Joint Venture) for

supply of boulders to the respondent. The boulders were to be

OMP 374/2005                                       Page 1 of 5
 supplied for use in Bangladesh.       The boulders were to be

loaded in India in railway wagons and were to be received in

Bangladesh. The contract provided for 15% of the voids in the

loaded boulder.     The quantity in cubic meters was to be

measured at both the places, that is at the time of loading and

at the time of unloading the wagons. All wagons after loading

in India were sealed and the seal was taken off at the time of

unloading the wagons.


3.          It was found that the shrinkage in the quantity

received at Bangladesh was much more than 3% permissible

shrinkage as per contract and it went upto 19% in some cases.

The measurements were taken in India at the time of loading

in presence of the representatives of both the parties and

recorded.   However, the measurements in Bangladesh were

taken by the representative of the respondent at the time of

unloading, in terms of the contract.        The contract did not

provide for joint measurement in Bangladesh.


4.          The   contention   of   the   petitioner    is   that    the

measurement in Bangladesh was taken by unskilled labours

and not by some supervisor who was skilled in taking

measurements and the shrinkage of around 19% shown at the
OMP 374/2005                                           Page 2 of 5
 time of receiving the material could not have been there. The

respondent had paid to the petitioner on the basis of

measurements taken at the receiving end resulting into raising

of a dispute by the petitioner.         The learned Arbitrator

considering the fact that the measurements at the receiving

end were taken by unskilled labours devised a formula of

taking average of the measurement taken at the loading time

and taken at the unloading time and awarded an additional

amount to be paid to the petitioner on the basis of this

average.    The petitioner has contended that this average

arrived at by the learned Arbitrator was not a proper

method/formula and the petitioner was entitled for payment in

accordance with the measurement done on Indian site at the

time of loading. This is the main ground of challenge to the

award.


5.          I consider that this contention of the petitioner must

fail.   The contract specifically provided that the maximum

voids at the time of loading should not exceed 15%. It was for

the petitioner to ensure at the time of loading that the loading

is done in such a manner and boulders of such sizes are

adjusted in the wagons in such a manner that the voids among

OMP 374/2005                                       Page 3 of 5
 different boulders was not more than 15%. The contract also

provides that the shrinkage in the volume should not be more

than 3% than what was loaded when the boulders are received

in Bangladesh. If the voids are not taken care of at the time of

loading and the persons who load the boulders do not adjust

the boulders in such a manner that there are minimum voids

and not more than 15% voids, the volume is bound to shrink

much more than 3% by the movement of the wagons and by

vibrations which are produced during the movement of the

wagons. Since the shrinkage in volume had gone upto 19%,

this only shows that precautions were not taken by the

petitioner at the time of loading to ensure voids to be 15% or

less.   There is no force in the plea of measurement being

wrongly taken at Bangladesh by unskilled labour. The wagon

base has standard measurement and for finding volume only

height of boulders was to be measured. Not much of the skill

or expertise is required in measuring height of level of

boulders in the wagon.


6.         I therefore consider that no fault can be found with

the award given by the Arbitrator, on this ground.             The



OMP 374/2005                                     Page 4 of 5
 Arbitrator rather devised a formula which was in favour of the

petitioner and not against the petitioner.


7.         The petitioner drew my attention to a document

called PA-34 which petitioner placed before the Arbitrator

during arguments.      This document was not part of the

documents relied upon by the petitioner or proved during

evidence and was rightly not considered by the Arbitrator.

According to the petitioner this document showed the quantity

of boulders received at Bangladesh was more than the

quantity as pleaded by the respondent. I consider unless this

document was put to the respondent during the proceedings

before the Arbitrator, no reliance can be placed on this

document at this stage. The Arbitrator rightly did not consider

this document.


           I find no merits in the objections raised by the

petitioner. The petition is hereby dismissed.




March 31, 2009              SHIV NARAYAN DHINGRA, J.

ak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter