Saturday, 02, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Bhartiya Const. Co. vs Delhi Development Authority
2009 Latest Caselaw 1073 Del

Citation : 2009 Latest Caselaw 1073 Del
Judgement Date : 31 March, 2009

Delhi High Court
Bhartiya Const. Co. vs Delhi Development Authority on 31 March, 2009
Author: Shiv Narayan Dhingra
           * IN THE HIGH COURT OF DELHI AT NEW DELHI

                                                Date of Reserve: 26.03.2009
                                                  Date of Order: 31.03.2009
CS(OS) 965A/1995
%                                                                31.03.2009

        BHARTIYA CONST. CO.                               ... Petitioner
                     Through:              Mr. Vivekanand, Adv.

               Versus

        DELHI DEVELOPMENT AUTHORITY                            ... Respondent


JUSTICE SHIV NARAYAN DHINGRA

1. Whether reporters of local papers may be allowed to see

     the judgment?                                                        Yes.

2. To be referred to the reporter or not?                                 Yes.

3. Whether judgment should be reported in Digest?                         Yes.


Order

1.             The matter is taken up after remand back by the

Division Bench for addressing the maintainability of the petition

inter alia under Order 2 Rule 2 CPC, on limitation and cause of

action.    None has appeared for the respondent despite service of

the Court notice.


2.             The present petition was filed under Section 20 of

Arbitration Act for directions to DDA to appoint an Arbitrator.                      A

contract for construction of 504 SFS category flats in Sukhdev Vihar

was awarded by DDA to the petitioner in 1982.                        During the

continuation of the contract a dispute arose between the parties and


CS(OS) 965A/1995     BHARTIYA CONST. CO. v. DELHI DEVELOPMENT AUTHORITY     Page 1 of 6
 this dispute in terms of the arbitration agreement was referred for

adjudication to the Arbitrator in 1983. The work under the contract

continued irrespective of the dispute being adjudicated by the

Arbitrator. The work got completed on 24th June, 1988. The award

on the dispute arisen at the initial stage of the contract was

rendered by the Arbitrator on 31.10.1988. This award was affirmed

by the Court and was made a Rule of the Court on 8.8.97.                         The

present     petition     has    been     filed   by    the   petitioner     seeking

appointment of an Arbitrator after completion of the work because

the final bill of the petitioner has not been prepared and paid,

neither the security deposit made by the petitioner has been

returned.      The petitioner has also raised other disputes seeking

escalation in price etc.


3.             I consider that the earlier award passed by the

Arbitration would not either amount to res- judicata or would bar the

invocation of the arbitration clause in respect of the disputes arisen

between the parties after completion of the work.                     Principles of

Order 2 Rule 2 CPC would have been attracted if the petitioner had

failed to raise the present dispute at the time when earlier dispute

was raised by the petitioner. The present dispute was not even in

existence at the time when earlier dispute was raised in 1983. The

present dispute arose only after completion of work, because of

non-payment of the final bill, non-return of the security deposit and

other connected matters after completion of the work.                        These

CS(OS) 965A/1995       BHARTIYA CONST. CO. v. DELHI DEVELOPMENT AUTHORITY   Page 2 of 6
 disputes had not arisen in 1983 and could not have been referred to

the Arbitration in 1983.        Thus, this petition would not be barred

under Order 2 Rule 2 CPC.


4.             It is settled law that only a living dispute can be referred

for adjudication to the Arbitrator.          There is no doubt that in the

present case, the work was completed on 24.6.1988.                           After

completion of work, the final bill of the petitioner was to be finalized

by the respondent.         It is not the case of the respondent that

respondent had finalized the final bill.          As late as on 24th October,

1994, the respondent had written to the petitioner that its challenge

to the earlier award was pending before the High Court therefore

respondent would not comment or discuss the merits of the claim

raised by the petitioner.         Respondent restricted its reply to the

extent of renewal of bank guarantee and renewal of FDR (security

provided by the petitioner to the respondent) for completion of

work. In this letter, it is stated by the respondent that completion

was recorded on 24.6.1988 and the counter claim of the department

against the petitioner was rejected by the Arbitrator in award

published on 31.10.1988. Since the respondent has challenged this

rejection of counter claim by way of suit no.2816/88, the respondent

only wanted that petitioner should get the bank guarantee renewed

without further delay and in case the bank guarantee was not

renewed, the respondent would be forced to invoke it.                          The




CS(OS) 965A/1995     BHARTIYA CONST. CO. v. DELHI DEVELOPMENT AUTHORITY   Page 3 of 6
 respondent made it clear to the petitioner that bank guarantee was

required to be kept in force till the decision of the High Court.


5.             The High Court ultimately dismissed the petition filed by

the   respondent against rejection of its claim                    by Arbitrator.

Thereafter, instead of finalizing the bill of the petitioner, the

respondent         encahsed   the    bank    guarantee       which    forced    the

petitioner to file the present petition. Until and unless final bill of

the petitioner was prepared/approved by the DDA and DDA had

given intimation to the respondent that it was forfeiting the bank

guarantee, no cause of action had accrued in favour of the plaintiff.

Cause of action accrued in favour of the plaintiff only when DDA

showed its inclination to invoke the bank guarantee and did not

finalize the bill. This happened only after rejection of the petition of

the respondent. This Court vide order dated 3rd January, 1997 had

observed that the question of appointment of Arbitrator would be

considered only after decision in the suit filed by the respondent.

The present petition which was filed in 1995 cannot be said to be

beyond period of limitation since the limitation is of 3 years and

cause of action had not even arisen in 1994 when respondent

informed the petitioner that it would not consider the finalization of

the bill until and unless its objection pending before the High Court

against rejection of its counter claim was not decided. I therefore

consider that the present petition was very much maintainable.




CS(OS) 965A/1995      BHARTIYA CONST. CO. v. DELHI DEVELOPMENT AUTHORITY   Page 4 of 6
 6.             In Hari Shankar Singhania & Ors vs. Gaur Hari

Singhania & Ors. (2006) 4 SCC 658 Supreme Court had observed

that the cause of action for filing petition under Section 20 would

arise only on the date of last correspondence between the parties

showing that the claim was still unsettled. The period of limitation

commences from the date of last communication between the

parties regarding the dispute being under consideration.                       The

present petition was therefore well within the period of limitation.


7.             It cannot be said that the present petition was filed

without cause of action.           Petitioner gave its final bill to the

respondent for payment on completion of work but the respondent

did not make the payment under this final bill and asked him to

continue the bank guarantee and security deposited with the

respondent.        The petitioner continued renewing bank guarantee

from time to time on the assurance of the respondent that they

would release the amount due to the petitioner under final bill after

waiting for the result of the challenge to earlier award made by the

respondent. I therefore consider that there was sufficient cause of

action for the petitioner to file the present petition.


8.             There is no dispute that there is an arbitration clause

between the parties. It is also settled law that non-invocation of the

arbitration clause by a separate notice is no ground to deny a

petition under Section 20.        In Anand Kumar Jain vs. UOI, 1984

RLR 438 this Court had observed that filing of an application under
CS(OS) 965A/1995     BHARTIYA CONST. CO. v. DELHI DEVELOPMENT AUTHORITY   Page 5 of 6
 section 20 itself amounts to invocation of the Arbitration Clause and

if the amount as claimed in the petition under Section 20 is not paid,

the Court can ask the respondent to refer the matter to the

arbitration in accordance with the contract.           I therefore allow this

petition. DDA is directed to appoint an Arbitrator within a period of

60 days from today in terms of the Arbitration Clause and make

reference of the dispute to the Arbitrator.




March 31, 2009                           SHIV NARAYAN DHINGRA, J.

ak

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter