Citation : 2009 Latest Caselaw 2955 Del
Judgement Date : 31 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 09, 2009
Date of Order: July 31, 2009
+CS(OS) 342A/1995
% 31.07.2009
M/s Kirat Chand Jain Family Trust ...Plaintiff
Through: Mr. Sandeep Sharma, Advocate
Versus
Union of India ...Respondent
Through: Nemo
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. The petitioner has filed this petition under Section 30 and 33 of the
Arbitration Act, 1940 assailing an award dated 4th November 1994 passed by
learned Sole Arbitrator whereby he awarded a sum of Rs.28,27,666/- in
favour of respondent and against the petitioner.
2. The petitioner was awarded work of construction of 110 bedded ward
block with intensive care unit and other technical facilities at G.B. Pant
Hospital, New Delhi SH. Pile Foundation vide letter of award dated 13th June
1986. The schedule date of start of work was 23rd June 1986. The completion
period of work was 9 months and schedule date of completion of work was
22nd March 1987. The work included providing 12 meter deep driven Cast-in-
Situ Pile foundation. Respondent, Union of India through its specialized wing
was to conduct detailed soil exploration and laboratory tests in presence of
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 1 Of 8 petitioner and the petitioner based on soil data so obtained was to prepare
designs for the foundation as per IS-2911 Part-I Section-I-1971.
3. There was some delay in conducting soil investigation by the
respondent, Union of India, and the report of soil testing was sent to claimant
for preparing designs on 28th November 1986. It was alleged by respondent
that the claimant, instead of preparing designs as per the contract raised
objections to the report and pointed out shortcomings of the report despite
the fact that petitioner was associated in soil investigation it objected to the
report on the ground that the claimant was not associated during soil
investigation. Ultimately, when the claimant submitted designs of the pile
foundation, it furnished designs contrary to contract based on Hiley formulae
whereas contract provided for designs based on static formulae as given in
I.S. Code. The suggestion of the claimant was that 2/3 pile foundations as per
hiley design could be driven in earth and checked for required strength of 60
metric ton capacity. This design was rejected by the respondent, Union of
India, being not in conformity with IS 2911 Part-I Section 1979 as required
under the contract. Respondent asked the claimant to do pile foundation as
per the designs given in contract and bring a hammer of 3.5 metric ton for
the same as against 1.5 and 2 metric ton capacity hammer which had been
brought by the claimant on the site. The claimant insisted that the design
submitted by the claimant would give requisite strength as the claimant
(petitioner herein) had followed sound design practice. Because of this
dispute, piles were not constructed and practically no work had started. While
petitioner insisted on a soil depth of about 6 meters, the respondent Union of
India struck to its stand of 12 meters deep piles as per I.S. Code. The claimant
ultimately installed two test piles and conducted tests on these piles.
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 2 Of 8 According to claimant, the tests were satisfactory and gave requisite strength
whereas the contention of respondent had been that the tests were not
conducted earnestly with dispatch due to inadequate and improper technical
arrangement. The respondent insisted that the piles depth should be as per
the agreement and asked the petitioner to provide additional test piles to be
driven up to 12 meter or the refusal point. During this process, the
completion date had already expired but the parties continued with the work.
A 'RIG' mobilized by the petitioner on the site also toppled on the site. The
claimant thereafter told the respondent that it was improper to ask him to
drive piles up to 12 meters depth in view of available data of soil when the
required load carrying capacity could be achieved at much smaller depth of 6
meter. The petitioner stated that it was ready to get further test conduct on
the piles with 6 meters depth in the ground.
4. The respondent Union of India ultimately rescinded the contract on 7th
June 1988 when the petitioner apparently did not seem to be prepared to
have pile foundation with 12 meter depth. After rescinding of contract,
respondent got this work completed through other agency. On rescinding of
contract, petitioner raised several claims against respondent and wanted the
claims to be referred to the Arbitrator. The respondent appointed an
Arbitrator as per letter dated 18th July 1988 and referred the disputes raised
by the petitioner to the arbitrator with a condition that if the amount awarded
was more than Rs.50,000/-, the Arbitrator shall give a reasoned award. This
condition was even otherwise provided in the contract in clause 25 and the
arbitrator was to give a reasoned award in case of amount of award
exceeding Rs.50,000/-.
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 3 Of 8
5. The claimant in his initial letter dated 30thJune 1987 raised an issue
that rescinding of contract was bad in law and claimed an amount of
Rs.11,74,900/- against various heads. The claimant sent reminder of his letter
for appointment of an arbitrator and in the reminder claimant made
additional claims and stated that he was entitled to Rs.25,17,748/-.
6. The claimant had also approached this Court for appointment of an
arbitrator vide Suit No.559 of 1988 alleging therein that despite invocation of
arbitration clause, respondent did not appoint an arbitrator. However, this
Court was informed by respondent on 27th April 1988 that an arbitrator had
already been appointed. This Court vide order dated 27th April 1988 observed
that all the disputes that were raised by the claimant (petitioner herein) in the
suit filed before the Court shall be adjudicated by the arbitrator appointed by
respondent, Union of India.
7. Both parties made claim and counter claim before the arbitrator and
the learned arbitrator gave the impugned award.
8. The award has been assailed by petitioner on the ground that the
learned arbitrator grossly misconducted the proceedings and acted with
prejudiced mind and was biased in favour of respondent and against the
petitioner /claimant. He passed the award behind the back of claimant by
keeping the claimant in dark. The claimant had made an application dated
28th December 1993 and 4th January 1994 regarding deficiency of record and
documents and the vital information was yet to be supplied by respondent to
claimant, however, arbitrator issued no instructions on these applications and
did not seek the record from respondent which was necessary for
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 4 Of 8 adjudicating the disputes. Thus, this amounted to legal misconduct. The other
objection is that the time for publishing the award had already expired. The
learned arbitrator manipulated the proceedings and behind the back of the
claimant recorded that the parties extended the time, by mutual consent, up
to 31st December 1994. It is further alleged that the arbitrator misconducted
himself in disclosing his mind to respondent by issuing directions telling
respondent to file non judicial stamp paper for aware and keeping silent
about the similar action by the petitioner. The petitioner quoted other
instances in support of its contention that the arbitrator misconducted himself
and stepped out of his jurisdiction. It is also alleged that Arbitrator did not
decide the basic disputes pertaining to required length of piles for carrying
required load. It is submitted that as per contract the length could be 12
meter (±) i.e. variation in length was allowed but the learned arbitrator
assumed that the scope of work envisaged the depth of the piles as 12
meters deep driven-caste-in-situ.
9. It is also submitted that the arbitrator though observed that there was
a five months' initial delay out of total 9 months contract period on the part of
respondent but he still has not found petitioner entitled for any relief. The
arbitrator has also erred in holding that claimant wished to draw only 6.0
meter depth piles whereas claimant's case had all along been that the depth
should not be calculated on the basis of static formulae as insisted upon by
the respondent but the actual driven depth may vary depending on under
rocks data and resistance of the place. It is also submitted that the learned
arbitrator did not apply its mind. The agency which was assigned the contract
after the petitioner was not the one as mentioned by the learned arbitrator
i.e. M/s Suplex Private Limited. The learned arbitrator awarded an amount of
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 5 Of 8 Rs.28,02,281/- in favour of respondent without mentioning the name of
agency even correctly. It is further submitted that the award passed by
learned Arbitrator was a non speaking generally and none of the claims of
petitioner was discussed or a specific order was passed whereas claim of
respondent has been allowed without giving reasons.
10. Respondent has refuted the application made by claimant/petitioner
and denied all allegations.
11. A perusal of award would show that the learned arbitrator gave
sufficient time and opportunities to both the parties to place their case before
the arbitrator. The conduct of petitioner before the arbitrator has been that of
an escapist. The petitioner had been seeking adjournments after
adjournments and the allegations made by petitioner against the arbitrator
regarding his bias are not supported from the proceedings as conducted by
the learned Arbitrator.
12. The award shows that the learned arbitrator in the award first
discussed the scope of work and the conduct of petitioner during the
continuation of work and observed that petitioner was not prepared to do
work in accordance with the contract and was not prepared to lay pillars/piles
to the depth of 12 meters as per specification, provided in the contract and
the arbitrator came to conclusion that the claimant had generally failed to
discharge the contractual obligations of supply of designs as per the agreed
specifications and parameters with due discharge after providing of soil test
results and failed to work as per contract. The arbitrator held petitioner/
claimant responsible for rescinding of contract. After holding so, the learned
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 6 Of 8 arbitrator rejected all the claims of petitioner since they were based on the
plea that petitioner was not responsible for rescinding the contract. However,
learned arbitrator thereafter observed that the respondent had to get the
work done through alternative agency and, therefore, he awarded a sum of
Rs.28,02,281/- as amount spent extra by respondent. The other claim of
respondent for levy of compensation was rejected. A claim of respondent for
recovery of Rs.25,605/- from the claimant towards costs of cement was also
allowed. The arbitrator observed that after rescinding of contract of
petitioner, the respondent got the work completed through M/s Simplex
Private Limited which was a specialized agency in this kind of work and this
agency drive the pillars up to 12 meters depth and even more at most of the
location, in accordance with contract.
13. It is obvious from the award that the learned arbitrator while allowing
the claim of respondent to the tune of Rs.28,02,281/- has not given reasons
as to why this amount was being allowed . If the work had been got done by
respondent at risk and costs of petitioner in terms of agreement, the learned
arbitrator was supposed to give the reasons as to what costs the respondent
would have incurred had the work been done by petitioner under the contract
and what was the contractual amount paid by respondent to the new agency
and for what extent of work. The difference in two costs showing the amount
of risk purchase has not been specified by the learned Arbitrator.
14. In my view, giving of reasons in allowing a claim of more than
Rs.50,000/- was mandatory for the arbitrator under arbitration clause as well
as per the letter of appointment of the arbitrator. The award passed by the
arbitrator in respect of claim No.1 of Rs.28,02,281/- without giving reasons,
CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 7 Of 8 therefore, is not tenable and it is liable to be set aside.
15. The learned arbitrator has awarded another sum of Rs.25,605/-. This
amount the arbitrator held, respondent was entitled to recover towards the
costs of cement and steel supplied by respondent to the petitioner. Since this
claim was below Rs.50,000/-, the learned arbitrator could have allowed this
claim without a speaking award. In the counter claim filed by respondent,
respondent had given analysis of different quantities of steel and cement
supplied by it to the claimant and the quantities which were already removed
/shifted to other site and the balance quantities in the custody of the
claimant/ petitioner. Since the arbitrator has allowed this claim of respondent
taking into account the data presented to him which were remained
uncontroverted, this part of the award though non-speaking, cannot be set
aside on account of giving no reasons.
16. In the result, I partly allow objections filed by the petitioner. The award
of learned arbitrator for a sum of Rs.28,02,281/- is hereby set aside and the
award for a sum of Rs.25,605/- and for costs and interest is made a rule of
the Court. Decree sheet be prepared in above terms.
17. The petition stands disposed of.
July 31, 2009 SHIV NARAYAN DHINGRA J. rd CS(OS) 342A/1995 M/s Kirat Chand Jain Family Trust v.UOI Page 8 Of 8
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!