Citation : 2009 Latest Caselaw 2947 Del
Judgement Date : 31 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.645/2008
% Date of decision: 31ST July, 2009
Wipro GE Healthcare Pvt. Ltd. ....Petitioner
Through: Mr. V.Sheshagiri and Mr. Arunabh Suman, Advocates
Versus
Medical Superintendent Deen Dayal
Upadhyay Hospital & Others ... Respondents
Through: Ms. Jyoti Singh, Advocate for respondents No.1
& 2.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1 Petition under Section 9 of the Arbitration Act, 1996 seeking
the relief of restraining the respondents No.1 and 2 i.e. Medical
Superintendent Deen Dayal Upadhyay Hospital, Delhi and the
Secretary, Health and Family Welfare, Government of NCT of Delhi,
from encashing the Performance Bank Guarantee No.CBG 343/2004
dated 12th November, 2004 in the sum of Rs.25,53,750/- issued by
the respondent No.3 Corporation Bank, Bangalore at the instance of
the petitioner in favour of respondent No.1 i.e. Medical
Superintendent, Deen Dayal Upadhyay Hospital, Delhi, is sought.
Disputes and differences are stated to have arisen between the
petitioner and the respondents No.1 & 2 out of a purchase order
placed by the respondents No.1 and 2 on the petitioner. The said
purchase order is stated to be containing a clause for arbitration.
2 In terms of the aforesaid purchase order, 80% of the price of
equipment to be supplied by the petitioner was to be paid by the
respondents No.1 and 2 to the petitioner against shipping documents
and the balance 20% within 30 days of i) due certification of the
successful completion of proving test in which the performance of
the machines supplied was to be demonstrated after commissioning
at the premises of the respondent No.1; and ii) the submission of
bank guarantee for 10% of the value of the contract indemnifying the
purchaser against all losses during the guarantee period stipulated
in the warranty clause.
3 The petitioner arranged for the issuance of the bank
guarantee, encashment whereof is sought to be restrained in
pursuance to the above.
4 The petitioner has received 80% payment. It is the case of the
petitioner that not-with standing the petitioner having furnished the
bank guarantee, the respondents No.1 and 2 have not released the
balance 20% payment to the petitioner. Attention is invited to the
language of the performance bank guarantee which in recitals states
that the same was being issued in consideration of the respondents
No.1 and 2 having agreed to pay the balance contract price to the
petitioner. Else the said guarantee is unconditional, guaranteeing
payment of the amount thereof to the respondent No.1 on demand
and without demur and merely on receipt of intimation that the
supplier i.e. the petitioner has committed a breach of any of the
contractual obligations.
5 The counsel for the petitioner has contended that since the
consideration for furnishing the bank guarantee was the release of
the balance 20% payment and which has admittedly not been
released, the petitioner has become entitled to the order restraining
the encashment of the bank guarantee. That is the case set up in the
petition also.
6 This court vide ex-parte order dated 28th November, 2008
restrained the encashment of the bank guarantee. Since the bank
guarantee was taken to be valid till 9th November, 2009, perhaps
need was not felt to make the said order conditional to keeping the
bank guarantee alive.
7 The respondents No.1 and 2 have filed a reply to the petition.
They have contended that the balance 20% payment was not
released to the petitioner because the equipment supplied was in
fact not the equipment ordered and had several deficiency and
missing parts and had also failed to perform as per the specification.
It is further the case of the respondents No.1 and 2 that though the
maintenance charges have also been charged by the petitioner in
advance but the petitioner has failed to provide any maintenance
services whatsoever. The respondents No.1 and 2 thus justified the
issuance of the letter dated 7th November, 2008 to the respondent
No.3 bank intimating that the petitioner had failed to fulfill the
contract obligations and requiring the respondent No.3 bank to
release the amount of bank guarantee in favour of the petitioner.
8 The counsel for the petitioner at the outset stated that he has
filed the rejoinder to the reply of the respondents No.1 and 2.
However the said reply was not on record. Since there was an ex-
parte order restraining encashment of bank guarantee, it was not
felt prudent to adjourn the matter and a photocopy of the rejoinder
has been taken on record in the court and kept on file. The counsel
for the respondent No.3 bank stated that he did not need to file any
reply and will be bound by the orders of this court. The counsels for
the parties have been heard. The counsel for the petitioner has
reiterated that the respondents No.1 and 2 having not released the
balance 20% payment of the equipment and which was the
consideration for issuance of the bank guarantee are not entitled to
encash the same. The counsel for the respondents No.1 and 2 has
read from her reply.
9 At the outset I may state that the law with regard to
injunctions in the matter of bank guarantees is now well settled. The
Supreme Court and the other courts have laid down that the courts
ought not to interfere lightly in the same and only ground in fact laid
down for interference by the court is, a fraud of egregious nature so
as to vitiate the underlying transaction and the very issuance of bank
guarantee. The said fraud is not to be in the encashment of the bank
guarantee but has to be in obtaining the bank guarantee. Reference
in this regard can be made to Himadri Chemicals Industries Ltd.
Vs. Coal Tar Refining Company AIR 2007 Supreme Court 2798
and UP Co-operative Federation Limited Vs. Singh Consultants
& Engineers PA Limited, 1988 (1) SCC 174 and UP State Sugar
Corporation Vs. Sumac International Limited 1997 (1) SCC 568
amongst others.
10 What is peculiar to the present case is that even in the petition
there are no averments of fraud of such nature. In the absence of
fraud, merely because the disputes have arisen between the parties
and the beneficiary is alleged to be fraudulently encashing the bank
guarantee does not become a ground for the court to restrain
encashment thereof. If that were to be permitted, it would interfere
with the very fabric of commerce and trade. Such unconditional bank
guarantees are generally taken to protect the beneficiary, when
payments are being made in advance, as in this case also.
11 Though in the absence of any averments of fraud, the petition
ought to be dismissed summarily but since the courts have in a few
cases held special equities to be also a ground for interfering in the
bank guarantee need is felt to discuss the ground taken by the
petitioner for restraining encashment.
12 The contention of the petitioner of the consideration for the
issuance of bank guarantee being the release of balance 20%
payment is not found to be correct. The balance 20% payment was
to be released subject to the petitioner satisfying two conditions i.e.
furnishing the bank guarantee and secondly obtaining due
certification of successful completion of machines performance after
commissioning. There is no averment that such certification has
been obtained by the petitioner. While the petitioner blames
respondents No.1 and 2 for the same, the said respondents contend
otherwise. That is to be gone into in the arbitration proceedings and
not in these proceedings.
13 Though undoubtedly the bank guarantee mentions only the
release of balance 20% payment as the consideration therefore but
in my view the said bank guarantee cannot change the agreement
between the parties. The bank guarantee is neither signed by the
petitioner nor by the respondents No.1 and 2. Thus it cannot change
the agreement between the parties.
14 The mere fact that the bank guarantee does not mention the
complete agreement between the parties or mentions only a part of
the consideration is no ground in equity or otherwise for interfering
with the same.
15 Even otherwise the mentioning of a wrong consideration in a
document does not prevent the parties from showing the real
consideration. In this regard see State Bank of India Vs. Premco
Saw Mill AIR 1984 Guj. 93 (DB).
16 Moreover we are in this case not concerned with what was the
consideration for issuance of the bank guarantee. It is not the case
where the bank guarantee is being sought to be voided for being
without consideration. Payment under the bank guarantee is sought
to be restrained. In judging the same, the reason for issuance of the
bank guarantee is not material.
17 The result of the aforesaid discussion is that the petitioner is
not entitled to the relief claimed in as much as no case for
restraining encashment of bank guarantee is made out.
18 The counsel for the petitioner has during the hearing
contended that the respondent No.3 bank had pursuant to the letter
of invocation of the petitioner debited the account of the petitioner
with the amount of the bank guarantee. However payment under the
bank guarantee could not be made to the respondents No.1 and 2
owing to the ex-parte order aforesaid of this court. During the
hearing it has transpired that respondent No.3 bank has kept the
amount of the bank guarantee in a FDR. The Supreme Court recently
in Abhimanyoo Ram Vs. State of U.P. 2009 (III) Apex Decisions
(SC) 41 has upheld the order of the High Court holding that the
petitioner cannot be permitted to draw the benefit of interim order
when petition is finally dismissed. I have also in Green Delhi BQS
Ltd. Vs. DTC OMP No.614/2008 decided on 26th March, 2009 while
finally dismissing the petition seeking restrain on encashment of
bank guarantee imposed interest @ 9 % per annum on the petitioner
for delay occasioned in the beneficiary receiving the amount of the
bank guarantee owing to ex-parte order obtained from the court.
Following the said dicta, I hold that the respondent No.3 bank shall
along with the amount of the bank guarantee also pay to the
petitioner the interest accrued on the FDR made of the amount of
the bank guarantee.
19 The petition is dismissed. The respondents No.1 and 2 are also
held entitled to costs of these proceedings of Rs.25,000/- from the
petitioner.
RAJIV SAHAI ENDLAW (JUDGE) July 31, 2009 J
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!