Citation : 2009 Latest Caselaw 2930 Del
Judgement Date : 30 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ ARB.APPL.92/2007
% Date of decision: 30th July, 2009
M/S PROGRESSIVE CONSTRUCTIONS LTD ....Petitioner
Through: Mr. Sanjay Jain, Sr Advocate with Mr
Gyanendra Kumar, Ms Ruchi Jain and
Mr Sarfaraz Ahmed, Advocates
Versus
NATIONAL HYDROELECTRIC POWER ... Respondent
CORPORATION LTD
Through: Mr Ajit Puddessery, Advocate
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? YES
2. To be referred to the reporter or not? YES
3. Whether the judgment should be reported
in the Digest? YES
RAJIV SAHAI ENDLAW, J.
1. Application under Section 11(6) of the Arbitration Act 1996 is
preferred for appointment of an arbitrator to adjudicate the disputes
and differences accrued between the parties with respect to the
agreement dated 31st March, 1989/12th April, 1989. The respondent
had, vide the said agreement, awarded to the petitioner work for
construction of Power Channel Package at Tanakpur plant of the
respondent in the State of Utter Pradesh. It is not in dispute that the
scheduled date of completion of the said work was 4th April, 1990
and the actual date of completion of the work was 30th April, 1993. It
is also not in dispute that the defect liability period was for a term of
one year only and which expired on 30th April, 1994.
2. The present application was filed on 19th March, 2007 i.e., after
nearly 14 years from the actual date of completion and 13 years from
the expiration of the defect liability period. The respondent has, in
its reply, opposed the application inter alia on the ground that the
claims now sought to be agitated are palpably barred by time.
3. It is the case of the petitioner that it had, after entering into
the agreement dated 31st March, 1989/12th April, 1989 with the
respondent, assigned the works thereunder to M/s Sharma and
Associates Contractors Pvt Ltd (hereinafter referred to as "Sharma
Associates") vide contract dated 18th April, 1989. The petitioner
claims such assignment to be with the consent of the respondent.
The respondent controverts the same. It is the case of the petitioner
that, as per its agreement with M/s Sharma Associates, the said M/s
Sharma Associates only were to deal with the respondent; that due
to non-payment of bills and clearing of dues by the respondent, M/s
Sharma Associates raised certain claims against the petitioner.
4. The senior counsel for the petitioner has, during the course of
hearing, informed that M/s Sharma Associates had instituted a
petition under Section 20 of the Arbitration Act, 1940 against the
petitioner in or about the year 1994; at the time of institution of the
said petition M/s Sharma Associates had impleaded the respondent
herein also as a party thereto; however the respondent herein was
dropped as a party to those proceedings in or about the year 1996;
that the said petition of M/s Sharma Associates under Section 20 of
the 1940 Act was allowed by a Single judge of this court on 17 th
February, 2005; that the petitioner herein preferred an appeal being
FAO(OS)159/2005 to the Division Bench of this court against the said
order; that the Division Bench vide order dated 12th September, 2006
dismissed the said appeal. It is thereafter that the present petition
as aforesaid came to be filed on 19th March, 2007.
5. Considerable emphasis is placed in the petition as well as by
the senior counsel for the petitioner on the order dated 12 th
September, 2006 (supra) in FAO(OS) 159/2005. It is recorded in the
said order that the stand of the petitioner herein all throughout had
been that without the respondent's participation in the arbitration
proceedings, no effective award could be passed in favour of the
petitioner or the said M/s Sharma Associates. In that context the
Division Bench observed that since there was no subsisting contract
between M/s Sharma Associates and the respondent herein, the
respondent could not be impleaded as a party to the proceedings
between the petitioner and M/s Sharma Associates ; however, liberty
was given to the petitioner to file an appropriate application against
the respondent herein raising their disputes in respect of the
contract and it was further observed that if and when such a petition
is filed, the same could be considered and disputes raised therein
could also be referred to the same arbitrator who was being
appointed to adjudicate the disputes between the petitioner and M/s
Sharma Associates.
6. It was put to the senior counsel for the petitioner herein during
the hearing that the respondent herein was not a party to FAO(OS)
159/2005 and could not thus be bound by any observation therein.
The senior counsel for the petitioner agreed with the same but
nevertheless cited the said order as showing the context in which the
present petition has been filed. He further contended that in fact the
petitioner after sub-contracting the works to M/s Sharma Associates
had no knowledge whatsoever of the same and the contract of the
petitioner with M/s Sharma Associates was back to back with the
contract of the respondent with the petitioner and the claims, if any,
of M/s Sharma Associates against the petitioner were in fact against
the respondent and the petitioner would in the arbitration be making
the same claims against the respondent as made by M/s Sharma
Associates against it. It was further contended that the records of
the respondent relating to the project were necessary also for the
adjudication of the disputes between the petitioner and M/s Sharma
Associates and which in spite of being referred to arbitration were
held up. I had during the course of hearing also put to the parties
that merely because the records of the respondent were necessary
for adjudication of the lis between the petitioner and M/s Sharma
Associates was no ground for allowing this petition and the records
of the respondent, if any, required for that lis could be summoned in
accordance with law from the respondent.
7. The senior counsel for the petitioner has at the outset
contended that the plea of the respondent of the claims being barred
by time was a plea which was not necessarily required to be
adjudicated in a proceeding under Section 11(6) of the Act. Reliance
is placed on National Insurance Company Ltd Vs Boghara
Polyfab Private Ltd (2009) 1 SCC 267. It was contended that this
court as the designate of the Chief Justice ought to in the exercise of
its discretion not enter into the controversy of whether the claims
were within time or not and such questions were best left to the
arbitrator.
8. However, in view of the observations of the Supreme Court in
para 24 of SBP and Company Vs Patel Engineering Ltd AIR 2006
SC 450 that dragging a party to an arbitration when there existed
no arbitrable dispute can certainly affect the right of that party and
even on monetary terms, impose on him a serious liability for
meeting the expenses of the arbitration, even if it be preliminary
expenses and his objection is upheld by the arbitral tribunal and
further considering the long lapse of time from the completion of
work, after which the present application has been filed, I am not
inclined to blindly refuse to exercise the discretion of referring the
dispute of the claims being barred by time also to the arbitrator. In
my view, if on the basis of admitted facts, the court can come to the
conclusion of the claims sought to be referred to the arbitrators
being barred by limitation and/or whether the claims sought to be
adjudicated is a dead one that is sought to be resurrected, the Chief
Justice or his designate ought not to refer the parties to arbitration.
It is only when the facts from which the aforesaid questions can be
determined are disputed or when evidence may have to be recorded
or detailed investigation required to be done with respect thereto,
that the court would be justified in instead of returning a finding
itself, exercise the discretion to refer the same also to arbitration. I
thus proceed to determine whether the claims in the present case
can be said to be long barred and dead or not.
9. The petitioner has in the petition not given any dates
whatsoever as to what happened after the signing of the contract on
31st March, 1989/12th April, 1989. The petitioner has straightway
referred to the notice dated 29th December, 2006 stated to have been
given by the petitioner to the respondent asking the respondent to
appoint the arbitrator in terms of the agreement. The senior counsel
for the petitioner upon being quizzed in this respect invited the
attention to annexure "B" filed alongwith its rejoinder. The same is a
letter dated 11th April, 2005 of the respondent to the petitioner and
which is as under:-
"Under Postal Certificate To, M/s Progressive Construction Ltd 18 Kotla Lane, Rouse Avenue New Delhi-110002
Sub: Construction of Power Channel (From RD 4032m to RD 5200m) Package-III.
(FINAL BILL) Ref: 1. Our letter No.NH/TP/PCW/W-40/2000/194 dated 25.02.2000.
2. letter No. NH/TP/PCW/W-40/05/194 dated 04.01.2001.
3. letter No. NH/TP/CE/PC/23187 dated 09.01.2001
4. letter No. NH/TP/Civil/2002/1349/ dated 18.09.2002.
5. letter No. NH/TP/Civil/2002/1644 dated 18.11.2002.
6. letter No. NH/TP/Civil/2002/364 dated 24.04.2003
7. letter No. NH/TP/CC/1518 dated 01.19.2004 D/Sir, Kindly refer our above-referred letters regarding final bill for the work of "Construction of Power Channel (From RD 4032m to RD 5200m) Package-III." Which were prepared long back but the same could not be settled on account of non-acceptance by you.
You are once again requested to depute your authorized representative within 15 days from the date of issue of this letter to this Project for accepting the final bill, failing which the final adjustment shall be made in our accounts.
This may kindly be treated as final notice."
10. The senior counsel for the petitioner contended that the notice
dated 29th December, 2006 for appointment of the arbitrator was
issued within three years from the aforesaid letter and thus it could
not be said that the claims were barred by time. It was further
argued that from the aforesaid letter it was clear that the final bill
had not been prepared till then. It was thus contended that allclaims
of the petitioner were alive.
11. Per contra the counsel for the respondent has drawn attention
to clause 48 of the agreement set out in his reply and as per which
the petitioner was required to submit the final bill within a week of
the completion and the payment thereof was required to be made
within three months/six months thereof and list of disputes with
respect to the final bills were required to be submitted within 30
days of disallowance thereof; it is further provided therein that if the
contractor failed to submit the list of disputed items within such 30
days his claims shall be deemed to have been fully waived and
absolutely extinguished. The counsel for the respondent also relied
upon clause 55.5 also providing that the notice of existence of
disputes or differences in connection with the contract unless served
within 30 days of expiry of defects liability period, all rights and
claims under the contract shall be deemed to have been waived and
thus forfeited and absolutely barred. It was thus contended that it
being not the case of the petitioner that any such notice was given
within the time agreed, the petitioner was now not entitled to raise
any dispute. On inquiry as to whether such a clause would not be
governed by Section 28 of the Contract Act, the counsel for the
respondent contended that amendment to the contract Act came into
force w.e.f. 8th January, 1997 and was not retrospective and the work
in the present case having been completed much prior thereto i.e. on
30th April, 1993, Section 28 as prior to its amendment and as then
interpreted by the courts shall apply. Reliance is placed on M/s
Shakti Tubes Ltd Vs State of Bihar 2009 (9) SCALE 270 laying
down that an Act should always be regarded as prospective in nature
unless the legislature has clearly intended it to have retrospective
effect.
12. The senior counsel for the petitioner in response to the
aforesaid submission relied upon the recent pronouncement dated
26th May, 2009 of the Division bench of this court in M/s Chander
Kant & Co. Vs The Vice Chairman, DDA Arbitration Petition No.
246/2005. He also contended that the limitation for filing application
for appointment of the arbitrator under Article 137 of the Limitation
Act is 3 years from the date the disputes have arisen; it was further
contended that mere silence is no good. Reliance in this regard was
placed on Major Inder Singh Rekhi Vs DDA (1988) 2 SCC 338 and
which was countered by the counsel for the respondent with Union
of India Vs M/s L.K. Ahuja & Co. (1988) 3 SCC 76.
13. I will first deal with the aspect of Section 28 of the Contract
Act. A Single Judge of this court in Continental Construction Ltd
Vs Food Corporation of India AIR 2003 Delhi 32 has held the
same to be not retrospective. This judgment was cited before the
Division Bench in M/s Chander Kant (supra). The Division Bench
did not differ with the view taken by the Single Judge but in the facts
of that case held that though the contract had been entered into
before the amendment of Section 28 but right from the preparation
of the final bill everything had happened after the amended
provisions came into play and thus held that the amended provisions
would apply.
14. I also find that a Single Judge of the Bombay High Court in
UOI Though Textile Commissioner Vs Bhagwati Cottons Ltd
MANU/MH/0247/2008 and a Division Bench of Madras High Court in
Oriental insurance Company Ltd Vs Karur Vysya Bank Ltd AIR
2001 Mad 489 have also held the amendment w.e.f. 8th January, 1997
to Section 28 of the Contract Act being not retrospective.
15. The senior counsel faced with the aforesaid situation laid heavy
reliance on the expression "the final bill was released only in
2002....." in para 13 of the judgment of the Division Bench of this
court in M/s Chander Kant (supra). It was contended that since
the final bill had not been released as yet in the present case,
amended Section 28 would apply. However, in my view, the use of a
particular word in a judgment cannot be cited, when that was not the
subject matter of adjudication.
16. In the present case, the works were completed more than
three years prior to the coming into force of the amendment and it
cannot be argued that merely because the petitioner owing to
reasons alleged did not approach the respondent, the petitioner
could come within the ambit of the amended law. It is not in dispute
and is also borne out from the judgment of the Division Bench of
Chander Kant (supra) that prior to the amendment of the Section
28, the same as interpreted by the courts, extinguished the right of
the petitioner to raise a dispute upon the same being not submitted
within the time of 30 days etc, as prescribed in the agreement.
17. The senior counsel for the petitioner faced with this contended
that it would have extinguished only the right of arbitration not the
right to press the claim in a suit. Though I have in Biba Sethi Vs
Dyna Securities Ltd OMP 63/2007 decided on 17.03.2009 differed
with the said proposition but that is not relevant for the present
purposes, more so, when the suit has admittedly not been instituted
and long time has expired since then.
18. The senior counsel for the petitioner also contended that since
the petitioner had sub-contracted the works with the consent of the
respondent, the petitioner could not be expected to raise the
disputes within 30 days. Without entering into the controversy
whether the respondent had consented to such sub-contracting of
works by the petitioner or not, in my view such risks are inherent in
sub-contracting and merely because the petitioner had sub-
contracted the work would not make any special law applicable for
the petitioner.
19. Having held that the petitioner was at the contemporaneous
time governed by Section 28 of the Contract Act as prior to its
amendment, it follows that under the clauses aforesaid of the
contract, the claim, if any, of the petitioner for any items to which it
was entitled under the final bill and which was disallowed by the
respondent stood extinguished and waived and similarly upon the
failure of the petitioner to give a notice within 30 days of the expiry
of the defect liability period, all rights, claims of the petitioner under
the contract stood waived and forfeited and absolutely barred.
20. Coming to the letter dated 11th April, 2005 set out hereinabove
and on which much emphasis was placed by the senior counsel for
the petitioner, in my view, the same also does not advance the case
of the petitioner. The senior counsel for the petitioner has
contended that the reference of the earlier letters of the respondent
from the 25th February, 2000 to 1st September, 2004 is made in the
said letter. It was contended that with these periodical letters the
limitation would be extended. Per contra, the counsel for the
respondent contended that the works were completed on 30th April,
1993 and there is no reference whatsoever to any letter from that
date till 25th February, 2000. It was stated that acknowledgment of
liability has to be within every three years.
21. In my view, the said letter also does not come to the rescue of
the petitioner. The letter clearly states that the final bill was
prepared long back but could not be settled on account of non-
acceptance by the petitioner. From the said letter it transpires that
the dispute had arisen on non-acceptance of the final bill by the
petitioner. As aforesaid, upon such non-acceptance, the petitioner
was to within 30 days make its claims. There is no averment that
any such claim was made. All that the aforesaid letter does is to call
upon the petitioner to accept the final bill. The counsel for the
respondent contended that the respondent, being a public sector
undertaking, since monies as per the final bills prepared by the
respondent were payable to the petitioner and were standing in the
books of accounts of the respondent, repeated letters were being
written. It was fairly conceded that the respondent even now was
ready to release the payment due under the final bill as computed by
the respondent. In my view, the limitation which would be extended
by issuance of letter dated 11th April, 2005 is only for the petitioner
to make a claim for the amount of the final bill due according to the
respondent. The petitioner would be entitled to have an arbitrator
appointed only if the said payments were being disputed by the
respondent. However, as aforesaid, the respondent is not disputing
the said payment and is ready to release the same to the petitioner.
22. As far as the plea of the petitioner on the basis of Inder Singh
Rekhi (supra) is concerned, Article 18 to the Schedule of the
Limitation Act prescribes the Limitation of three years commencing
from the date when the work is done, for the price of work done,
where no time has been fixed for payment. In the present case the
time of 30 days from completion of work was fixed for the petitioner
to submit the final bill and the time of three months thereafter was
fixed for the respondent to make the payment. The said period of
four months from the date of completion i.e. 30th April, 1993 would
expire in end of August, 1993 and the claims could have been made
only within 3 years thereafter i.e. till the end of August, 1996. The
claims have been made long thereafter. As aforesaid, the notice for
appointment of arbitrator was given only on 29th December, 2006.
The claims, if any, of the petitioner as on that day were not within
limitation. Reliance in this regard can be placed on J.C. Budhiraja
Vs Orissa Mining Corporation Ltd (2008) 2 SCC 444. Besides the
claims having stood forfeited, abandoned and waived under Section
28 as prior to its amendment, the claims are even otherwise barred
by time. Moreover Inder Singh Rekhi (supra) which is on an
interpretation of Section 20 of the 1940 Act also makes a distinction
between the Limitation for making the claims and the limitation for
preferring the petition for appointment of arbitration. In the present
case the Supreme Court having held that the appointment of
arbitrator shall not be made when the claim is palpably barred by
time, or when a dead claim is sought to be resurrected, even if it
were to be held that the petition under Section 11(6) has been made
within three years from failure to appoint the arbitrator, the same
will still not succeed if the claim is sought to be agitated are barred
by time.
23. The observations made by the Division Bench of this court in
FAO(OS)159/2005 (supra) also do not come to the rescue of the
petitioner and would not validate the claims of the petitioner against
the respondent if otherwise invalid and barred by law. The
respondent has also contested the petition on the ground of being
not maintainable for the reason of the petitioner having illegally sub-
contracted the work. However, in view of the findings above, it is
not deemed appropriate to deal with this aspect which, in any case,
is highly contentious. Accordingly, the petition is dismissed with
costs of Rs 35,000/- on the petitioner.
RAJIV SAHAI ENDLAW (JUDGE) July 30, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!