Citation : 2009 Latest Caselaw 2854 Del
Judgement Date : 27 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)1645A/1996
% Date of decision: 27th July, 2009
FOOD CORPORATION OF INDIA .......Petitioner
Through: Mr. Anil K Sharma, Advocate
Versus
M/S GLOBUS CONTRACTORS PVT LTD ... Respondents
& ANOTHER
Through: Mr Raman Kapur, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may Yes
be allowed to see the judgment?
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. The petitioner instituted the petition under Sections 14 and 17
of the Arbitration Act, 1940 for filing of the arbitral award dated 13 th
June, 1996 before the court and for making the same rule of the
court. Notice was issued to the arbitrator to file the award in this
court and thereafter notice of filing of the award was issued to the
parties. The petitioner has not filed any objections to the award.
However, the record shows that considerable difficulty was faced
and time taken in service of the respondent No. 1 company. The
respondent company has filed the objections under Sections 30 and
33 of the Act pleadings whereof were completed and the usual issues
framed on 23rd March, 2001. Though the arbitral record has been
requisitioned but at the time of hearing it transpired that the arbitral
record on the file of the court was not complete. The matter being
very old and in view of the admitted position that the respondent
No.2 arbitrator who had rendered the award is now no more and
considering the likelihood of the record being now available to be
remote, the counsels were, during the course of hearing, permitted
to hand over copies of the arbitral record relied upon by them in
support of their respective submissions. A perusal of the order sheet
shows that on 20th April, 2006 also it was found that the record was
not complete and directions were issued to the registry. The registry
had reported that only the record on the file of this court had been
received from the arbitrator.
2. The arbitration in the present case also has a chequered
history. Disputes and differences had accrued between the parties
with respect to the contract/order of 1980 placed by the petitioner
on the respondent for construction of double story godowns at
Okhla; the time for completion of the work was of the essence of the
agreement and the works were to be completed on or before 7th July,
1981; the works were not so completed and the respondent
continued with the works; however the petitioner vide letter dated
22nd June, 1982 rescinded the contract. It is the case of the
petitioner that having found that the respondent was not in a mood
to complete the work, the contract was rescinded. The respondent
avers that the termination of the contract was illegal. It is further
the case of the petitioner that it got the work completed at the risk
and cost of the respondent and filed a suit for recovery of Rs
14,88,620.26 against the respondent. The respondent filed an
application under Section 34 of the Act in the said suit and also filed
a suit in this court being Suit No. 1675A/1983 under Section 20 of
the Act for reference of the parties to the arbitration in accordance
with the agreement. Vide order dated 13th February, 1985 in the
suit, arbitrator was ordered to be appointed.
3. In the aforesaid circumstances the petitioner appointed an
arbitrator. The said arbitrator retired from service on 31st March,
1988 before completing the proceedings. Another arbitrator was
appointed on 20th July, 1989 but resigned on 13th September, 1991.
The third arbitrator appointed on 7th February, 1992 expired before
completion of arbitration. It was in these circumstances that on 19 th
May, 1995 the arbitrator who has rendered the award was
appointed.
4. The award records and it is also borne out from the arbitral
record, that the arbitrator inter alia held proceedings on 19th June,
1995, 13th July, 1995, 18th October, 1995, 8th December, 1995, 17th
January, 1996, 16th February, 1996, 25th March, 1996 and 1st May,
1996 but were adjourned as the record of arbitration had not been
received from the earlier arbitrator. Mr Yogender Behal Managing
Director of the Respondent, appeared before the arbitrator on 19th
June, 1995, 16th February, 1996 and 1st May, 1996. On 1st May, 1996
the officer of the petitioner informed the arbitrator in the presence
of the said Shri Yogender Behal, that the arbitral record had been
collected from the earlier arbitrator and after pagination would be
handed over to the new arbitrator. The next date of 13 th May, 1996
was given in the presence of the said Shri Yogender Behal, for the
respondent.
5. However, none appeared for the respondent before the
arbitrator on 13th May, 1996. The arbitral record collected from the
earlier arbitrator was submitted before the new arbitrator. The
arbitrator ordered issuance of notice to Shri Yogender Behal,
Managing Director of the respondent for 3rd June, 1996.
6. On 3rd June, 1996 the arbitrator recorded that Mr Yogender
Behal, Managing Director of the respondent had been served with
notice for that date by registered post, A.D. and A.D. duly signed had
been returned; however none appeared on behalf of the respondent
and the arbitrator accordingly proceeded against the respondent ex
parte and listed the matter next on 7th June, 1996 for evidence of the
petitioner. On 7th June, 1996 permission was given to the petitioner
to file affidavits by way of evidence and the matter was adjourned to
10th June, 1996. On 10th June, 1996 the affidavit of one of the
witnesses of the petitioner was tendered into evidence and on
request of the petitioner the matter was adjourned to 11th June,
1996. On the next date again adjournment was sought and the
matter was adjourned to 12th June, 1996. On 12th June, 1996 the
affidavit of the other witness of the petitioner was tendered, the
petitioner closed his evidence and also made submissions before the
arbitrator. The Arbitrator on the next date i.e., 13th June, 1996
published the award.
7. The respondent has in its objections not disputed that it was
served with the notice of hearing for 3rd June, 1996 before the
arbitrator. It is, however, the case of the respondent that Mr
Yogender Behal, Managing Director of the respondent spent time,
besides in Delhi, in Jalandhar where he had some properties and
where litigation was going on; that due to certain rush of work with
regard to the property disputes the said Mr Yogender Behal had to
rush to Jalandhar and could not appear before the arbitrator on 3rd
June, 1996; that Mr Yogender Behal remained at Jalandhar for
considerably long period; that the respondent company had by that
time more or less closed the business and all the employees had left
and it was mainly Mr Yogender Behal who was left to look after the
affairs of the respondent company; that Shri Yogender Behal
remained at Jalandhar till 3rd week of June, 1996 and thus could not
appear before the arbitrator.
8. The main stay of the contention of the counsel for the
respondent is that from the dates aforesaid it is evident that the
arbitrator acted in haste and the ex parte award is liable to be set
aside on this ground alone. It is also the contention of the counsel
for the respondent that the arbitrator inspite of service of notice of
hearing on the respondent and non-appearance of the respondent on
3rd June, 1996, ought to have served another notice on the
respondent of his intention to proceed ex parte against the
respondent.
9. The counsel for the petitioner to rebut the aforesaid contention
of the respondent relied on Hemkunt Builders Pvt Ltd Vs Punjabi
University, Patiala 49 (1993) DLT 314 where a Single Judge held
that when a party was determined not to appear before the
Arbitrator and had been openly repudiating the authority of the
arbitrator to proceed with the arbitration, the arbitrator is not
required to issue notice of intention to proceed ex parte against such
person. He has also relied upon P.S. Oberoi Vs The Orissa Forest
Corporation Ltd AIR 1982 Orissa 168 holding that where an
opportunity has been given to the party, the principles of natural
justice were satisfied and the act of the arbitrator of proceedings ex
parte could not amount to misconduct. Reliance is also placed on
Dori Lal Vs Lal Sheo AIR 1954 All 244 (DB) holding that where due
notice of proceeding has been given, the arbitrator is entitled to
proceed ex parte against the party choosing not to appear and that
there is no provision in the Arbitration Act requiring the arbitrator to
give a second notice of his intention to proceed ex parte against the
absenting party. The conduct of the arbitrator of not giving a second
notice was not held to be legal misconduct.
10. Per contra, the counsel for the respondent/objector relied upon
Lovely Benefit Chit Fund And Finance Pvt Ltd Vs Puran Dutt
Sood 23(1983) DLT 261 where another Single Judge of this Court
held that an arbitrator ought not to proceed ex parte against a party
which has failed to appear at one of the sittings and the arbitrator
should fix another date for hearing and give notice to the defaulting
party of his intention to proceed ex parte on a specified date; it is
only if the party defaults in appearance inspite of such notice that
the arbitrator may proceed ex parte. It was further held that an ex
parte award will not be upheld unless it is apparent that the failure
to give notice of intention to proceed ex parte had not caused any
prejudice to the party against whom the ex parte award was made.
Reliance is also placed on M/s Shri Ram Ram Niranjan Vs UOI
AIR 2001 Delhi 424 wherealso finding that the arbitrator had acted
in haste, the award was set aside holding the same to be legal
misconduct.
11. This court's own research shows that yet another Single Judge
of this court in Anil Jain Vs Madhunam Appliances (P) Ltd 68
(1997) DLT 194 has expressly differed with the view taken in Lovely
Benefit Chit Fund (supra) and relying upon the judgments of the
Division Bench of the Allahabad High Court and of the Single Judge
of the Punjab High Court held that it will be of no use to go on
serving a man who is not ready to cooperate and to participate in the
proceedings despite innumerable opportunities granted to him to
appear and defend himself. It was further held that if the arbitrator
is required to give a notice again despite the previous non-
appearance, then it would tantamount to putting premium on the
party's lapse. However, it appears that the judgment in Anil Jain
(supra) was not brought to the attention of the court in subsequent
judgment in Shri Ram Ram Niranjan which is based merely on
Lovely Benefit Chit Fund. I also find that the matter has also
invited the attention of the Division Bench of this court in Power
Grid Corporation of India Ltd Vs Electrical Manufacturing Co.
Ltd & NTPC Ltd 153 (2008) DLT 440. Though the judgment
including in Lovely Benefit Chit Fund was cited before the Division
Bench, the Division Bench did not lay down any proposition that a
second notice of intention to proceed ex parte has to be necessarily
served by the arbitrator. Rather emphasis was placed on compliance
with the principles of natural justice and fair opportunity. In the
facts of that case it was held that the principles of natural justice and
fair play had not been complied with and the arbitral tribunal had
acted in haste and thus the award was set aside. To complete the
narrative, reference also must be made to judgments of other Single
Judge of this court in UOI Vs The Kohinoor Tarpaulin Industries
156 (2009) DLT 106 wherealso the ex parte award was set aside.
12. Coming to the facts of the present case, it is found that the
arbitration proceedings were pending for over ten years; pleadings
had already been completed before the earlier arbitrators. The
proceedings before the arbitrator, who has rendered the award,
were held up for the reason of non-availability of the arbitral record.
The respondent was fully aware of the appointment of the new
arbitrator and was appearing before the arbitrator intermittently
when the proceedings were being adjourned awaiting the record.
On 1st May, 1996 when the official of the petitioner informed the
arbitrator of the arbitral record having been collected from the
earlier arbitrator, the respondent was represented through its
Managing Director and in the presence of the respondent the next
date of 13th May, 1996 was given. The respondent thus knew that by
the next date the arbitral record would be filed before the arbitrator
and further proceedings commence. The respondent, however,
failed to appear before the arbitrator on the next date i.e., 13th May,
1996. There is no explanation whatsoever for non appearance on
13th May, 1996. Even though the arbitrator could have proceeded ex
parte against the respondent on 13th May, 1996 itself, since the
respondent had appeared on the previous date and had notice of that
date, but the arbitrator still chose to issue notice of the next date i.e.
3rd June, 1996 to the respondent. The said notice is admitted to have
been served. The respondent still neither appeared before the
arbitrator nor sent any communication to the arbitrator. In these
circumstances it cannot be said that the principles of natural justice,
audi altrum partum had not been complied with or that fair play
has not been meted out to the respondent.
13. I also do not find the reasons given by the respondent for non
appearance to be sufficient. All that has been said is that the
Managing Director of the respondent had to go to Jalandhar in
connection with some litigation. Neither the particulars of the said
litigation, if any, been disclosed nor is it the case that the said
litigations were listed before the court and the appearance of the
Managing Director of the respondent was necessary before the
court. By 1996 there was huge advancement in communications in
the country and Jalandhar was literally a call away from Delhi. The
respondent even if was unable to be represented on 13th May, 1996
and/or 3rd June, 1996 ought to have at least informed the arbitrator
and/or sought further time. There is no explanation whatsoever why
the same even was not done. In these circumstances, the non-
appearance of the respondent before the arbitrator appears to be
intentional and deliberate.
14. There is yet another very important aspect of the matter.
Though the Managing Director of the respondent is stated to have
returned from Jalandhar to Delhi at least in 3rd week of June, 1996
but still no efforts are stated to have been made to contact the
arbitrator or to find the fate of proceedings. Had the respondent
been bonafide unable to appear on 13th May, 1996 and 3rd June,
1996, it would have immediately thereafter, upon finding of ex parte
award, applied to this court for filing thereof and setting aside
thereof. Then the respondent's contention of arbitrator acting in
haste and prejudice thereby caused to it would have been
established. On the contrary, the respondent could not be served
with the notice of this court for nearly four years. Even though the
notices of this court erroneously issued in the name of the Managing
Director of the respondent instead of in the name of the respondent
Company were served as recorded in the order sheet dated 11th
January, 1999 but still the respondent did not appear before this
court. All this shows the intention of the respondent to, somehow or
the other, delay the proceedings. From the conduct of the
respondent, the haste even if any of the arbitrator is not found to
have caused any prejudice to the respondent.
15. There is yet another aspect of the matter. The respondent has
in its objection petition itself stated that the business of the
respondent company has come to an end and it has no employees.
The petitioner had in the present proceedings filed IA.No. 159/2001
under Order 38 of the CPC for attachment of certain monies in
another proceeding between the petitioner and M/s T.R.Behal &
Company. However, the said application was dismissed on 23rd
March, 2001 for the reason of the award in the present case being
against the company, even though it appears that the firm M/s. T.R.
Behal and company was of the directors/shareholders of the
respondent company only. The respondent though preferred claims
before the arbitrator has also not shown any urgency for pressing
the same. In fact, the respondent, in spite of termination of the
agreement, is not stated to have initiated any proceedings
whatsoever for recovery of its claims, if any, against the petitioner.
The arbitrator was appointed only after the petitioner instituted the
suit for recovery of monies. The facts of the arbitrator who has
rendered the award having expired, the arbitral record being not
available and likelihood of any recoveries under the award being
made by the petitioner from the respondent company being remote,
also compel me to hold that no useful purpose would be served in
giving another opportunity to the respondent for setting aside of the
award merely for the reason of being ex parte.
16. Yet another factor which prevails upon me is that the
procedure before the arbitrator cannot be made more stringent than
before the court, unless expressly agreed by the parties. The courts,
upon finding service to be completed or upon non appearance of any
party on any date are free to and generally do proceed ex parte
against such party. There is no requirement for the courts to issue a
notice to the defaulting party giving it a second chance informing it
that upon another default it will suffer. If that be so, I find no reason
to hold that arbitrator is so liable. However, if it were to be found
that the arbitrator has acted in connivance with the party, to enable
that party to steal a march owing to accidental non appearance of
the other, then the court would certainly be entitled to interfere.
Nothing of this sort is found in the present case. The arbitrator who
has rendered the award is a retired judge of High Court and is not an
officer of the petitioner. It is not the case of the respondent also that
the arbitrator did not issue a second notice to help the petitioner in
any manner whatsoever.
17. The purpose of arbitration is expediency. Arbitration law has
been re-enacted with the said motive. It is also common knowledge
that in most of the cases one party is interested in delay. If general
propositions that a notice of intention to proceed ex parte must be
given, were to be laid down, it will give a handle to unscrupulous
litigants to indefinitely delay the arbitral proceedings and to make it
virtually impossible for the arbitrator to proceed. It would also add
to the costs of the arbitration.
18. The counsel for the respondent has also argued that while the
arbitrator was earlier giving dates of minimum 15 to 20 days or over
a month, after non-appearance of the respondent, the proceedings
were concluded within ten days. There is no merit in the said
contention also. Long dates were being given earlier since the
arbitral record was being requisitioned from the family of the earlier
arbitrator. Once the arbitral record had been received, there was no
reason for adjourning the matter for a long date. No party can claim
a right to delay litigation. Moreover, as aforesaid no case of the
respondent having suffered any prejudice is made out.
19. The respondent had made claims before the arbitrator of Rs
10,70,800/- for works done and not paid for, of Rs 52,133/- for refund of
security deposit; for Rs 1,50,000/- towards costs of its material lying at site
and not permitted to be removed, of Rs 3,05,780/- as costs of its tools,
plants & machinery besides scaffolding, shuttering etc lying at the site and
not permitted to be removed, of Rs 4,00,000/- for wrongful suspension of
work, of Rs 2,45,000/- as compensation for idle labour and staff and
overhead expenses and finally Rs 12,00,000/- as damages for wrongful
termination.
20. Even though, in my view, upon default of the respondent to appear
before the arbitrator and substantiate its claims, the arbitrator was entitled
to dismiss the same in default and consider only the counter claims of the
petitioner but the arbitrator allowed Rs 5,17,022.28p to the respondent for
the works done and not paid for and Rs 52,133/- for refund of security
deposit. The remaining claims of the respondent were dismissed.
21. The arbitrator has allowed counter claims of the petitioner of Rs
98,501/- for removal of goods/materials supplied by petitioner and removed
by respondent from site without permission, of Rs 8,34,269.33p on account
of penal recovery of steel issued by the petitioner at site and removed by
the respondent from the site, of Rs 1,16,492.72p towards price of cement
removed by the respondent from the site and of Rs 13,78,501.88p towards
costs of getting the work completed at the risk and costs of the respondent.
Interest at 12% per annum from 1st May, 1986 on the amounts due to the
petitioner, after adjusting the amounts found due from the respondent has
also been awarded. Other claims of the petitioner have been dismissed.
22. The counsel for the respondent has challenged the award on merits
contending that there is an inconsistency therein. It is urged that once the
arbitrator had allowed the claim of the respondent for refund of security
deposit, it implies that there was no breach of agreement by the
respondent. It is contended that, in the circumstances, the arbitrator could
not have, on the other hand, allowed the claim of the petitioner on the
premise of the respondent being in breach of the agreement. This
contention of the counsel for the respondent is fallacious. The petitioner
had before the arbitrator admitted the receipt of security deposit from the
respondent but had asserted its claims to forfeit the same in satisfaction of
its claims against the respondent. The arbitrator has in the award, in fact,
adjusted the security deposit in the claims of the respondent. Merely
because security deposit has been so taken into account does not imply
that the arbitrator has returned the finding of the petitioner not being in
breach.
23. It is next contended that during the pendency of the suit under
Section 20 of the Act before this court a Commissioner was appointed who
had submitted a report and had shown materials/goods lying at site. It is
contended that the respondent had no access to the site thereafter and
thus the award holding that there were no material/steel lying at site is
erroneous. Though as aforesaid the arbitral records are not available but
the counsel for the respondent has handed over a copy of the report dated
2nd January 1986 of the Court Commissioner in Suit No.1675A/1985. The
same shows some bricks and steel lying at site. However, upon default of
the respondent to appear before the arbitrator and establishing that after
the said report said materials continued to be at site and / or of being not
removed by it, it cannot be said that there is any error on the face of the
award or that the arbitrator has misconducted himself.
24. Similarly, objections are raised to other amounts allowed under the
award. However, in my view, if a party does not press/establish its case
before the arbitrator, opportunity to do the same cannot be given at this
stage, especially when no sufficient cause has been found for non
appearance of the respondent before the arbitrator. I must however record
that the counsel for respondent has urged that that non application of mind
by arbitration is borne out from paras 6 and 7.5 of the award. It is argued
that in para 6 claims of contractor are stated to be of Rs 10,86,133/- only,
from para 6.1 to 6.7, they are found to be of much more . However, I find
this to be merely a typographical error. With respect to para 7.5 it is
pointed out that while the claim for cost of excess cement was of Rs
10,064.73p only, a sum of Rs 1,16,492.72p is allowed. The counsel for
respondent has not filed anything to demonstrate the same. The counsel
for the petitioner has filed a copy of its claim. Though under claim No.4 at
one place it is mentioned that Rs 10.064.73p is claimed for excess cement,
at another place, the amount claimed is mentioned as Rs 1,21,525.09. The
respondent having chosen not to appear before arbitrator, he cannot be
permitted a second chance before this court. The counsel for respondent
has also urged that while the officials of petitioner were caught selling
imported steel, the arbitrator has awarded costs of steel to the petitioner
against the respondent. This submission also cannot be considered. There
is nothing to show that the steel attempted to be sold was that issued to the
respondent and with respect to cost of which award has been made. Also,
the steel issued to the respondent was to be in custody of respondent and
the question of officials of petitioner selling the same does not arise.
25. Resultantly the objections are dismissed. The arbitral award dated
13th June, 1996 is made rule of the court and judgment in terms thereof is
pronounced. The petitioner shall also be entitled to interest under Section
29 of the Act on principal amount, with effect from the date of the decree
at 12% per annum. The petitioner shall also be entitled to costs of Rs
25,000/-.
RAJIV SAHAI ENDLAW (JUDGE) 27th July, 2009/M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!