Citation : 2009 Latest Caselaw 2847 Del
Judgement Date : 27 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ F.A.O. (OS) No. 15 of 2007
% Reserved on: July 23, 2009
Pronounced on: July 27, 2009
M/S. DAISY TRADING CORPORATON ..... Appellant
Through: Mr. Rajesh Banati, Advocate.
versus
UNION OF INDIA ..... Respondent
Through: Ms. Jyoti Singh and Mr. Ankur
Chhibber, Advocates.
CORAM:
HON'BLE MR. JUSTICE MUKUL MUDGAL
HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL
1. Whether Reporters of the local newspapers may be allowed to
see the judgment? Yes
2. Whether to be referred to the Reporter or not? Yes
3. Whether the judgment should be reported in the Digest? Yes
JUDGMENT
NEERAJ KISHAN KAUL, J.
1. This appeal has been preferred against the decision of the
learned Single Judge dated 10th November, 2006. Before the learned
Single Judge, the appellant had challenged the Award dated 29th
June, 2001. The learned Single Judge had affirmed the Award dated
29th June, 2001 and made the same rule of the Court.
2. Briefly stated the facts of the present case are that a risk
purchase tender was floated by the respondent in the year 1987. The
appellant/supplier submitted an offer. The offer was accepted by the
respondent and unit price per tent was fixed at Rs.4,791/-.
3. Admittedly, supplies were not effected and within the
stipulated periods governing the contract between the parties and a
new tender was floated by the respondent styling the same as a "risk
purchase tender". It was not disputed by the parties before the
learned Single Judge that the contract stipulated that in case of
breach committed by the supplier/appellant, the remedy of the
respondent was to proceed to effect risk purchase and recover the
loss to be determined on the differential price paid by the respondent.
4. At the second stage when risk purchase was resorted, a party
named Ashok Tent Industries was the lowest bidder and the contract
for the same number of tents was placed on the said party at a unit
price of Rs.6,925/-. Thus, the total price at which the contract was
awarded to the new supplier was Rs.7,27,125/-. The Union of India
(for short „UOI‟) sought to enforce the loss suffered by it and invoked
arbitration. The UOI sought an award in its favour for a sum of
Rs.2,33,033/- i.e. the differential price at which it actually purchased
the goods. It also claimed interest @ 18% per annum on the said
amount. The appellant claimed a sum of Rs.75,460/- alleging illegal
termination of the contract and loss of profits. The appellant also
contended before the Arbitration that the UOI had recovered
Rs.2,33,033/- by withholding the said amount from other contracts
in respect whereof payment had to be made by UOI to the appellant
and accordingly the appellant claimed refund of the said sum along
with interest. The learned Arbitrator rejected the claims of the
appellant. The claim of the UOI/respondent for the sum of
Rs.2,33033/- was allowed. Interest was disallowed to the UOI for the
reason as held by the learned Arbitrator that the UOI had already
made the necessary recoveries. The appellant restricted their
submissions before the learned Single Judge as also before us to the
award of risk purchase damages to the UOI.
5. It was contended on behalf of the appellant that it is settled law
that where risk purchase has to be effected, terms of the risk
purchase have to be identical to the terms of the original purchase.
It was further contended that not only have the specification of the
goods to remain the same, the other terms of the contract also have
to be the same. Reliance was placed on certain decisions including
the decision of the Delhi High Court in UOI vs. M/s Daisy Trading
Corporation reported as 2006 (5) AD (Delhi) 290. This judgment
was subsequently affirmed by a Division Bench of this Court in
FAO(OS) No. 570 of 2006 decided on 15th September, 2006. As per
the learned counsel for the appellant, there were three discrepancies
in the tender as originally floated and the risk purchase tender; price
paid whereunder has been treated as the measure to determine the
damages. The three differences pointed out by learned counsel for
the appellant are as follows:-
"A. In specification No.1 pertaining to the tender floated when petitioner made the offer, specification noted was ?IND/TC/0008 (J)? read with................
In the tender at the risk purchase stage specification noted was: "IND/TC/0009 (J)"
B. Whereas, vide serial no.10, date of delivery notified to the petitioner was 2-3 months reckoned effective from one month after receipt of formal AT. In case of risk purchase tender delivery period was accepted to 6-9 months.
C. Whereas, vide serial no.11 of the contract of the petitioner, term of delivery was F.O.R.
Bombay/Vasai. In case of the risk purchase
tender term of delivery was F.O.R.
N.Delhi/Noida."
6. The learned Single Judge dealing with the first discrepancy
took note of the fact that the learned Arbitrator had noted after
perusing the original file that the specification was the same. The
record of the Arbitrator which was perused by the learned Single
Judge showed that photocopies of the AT placed on the
petitioner/appellant as well as AT placed on M/s Ashok Tent
Industries had been filed. Thus, the learned Arbitrator had fully
satisfied himself that the specification of the two ATs was the same.
The learned Single Judge had rightly held that the learned Arbitrator
had recorded a finding of fact that he had seen the original record
and there were no reason to disbelieve the learned Arbitrator.
7. The learned Single Judge, in our view, has correctly observed
that identity in the specifications has to be not literally construed. It
has to be near identity. Trivial differences would make no difference.
As correctly observed by the learned Single Judge what is required to
be considered is that the second stage of supply could be evaluated
on objective parameters with the parameters of the first purchase for
only then it could be ascertained that the price at the second stage of
purchase is comparable with the offer at the first stage.
8. The learned Single Judge dealing with the second discrepancy,
namely, the time granted to effect supplies being different i.e. two to
three months reckoned after the first month of placement of AT upon
the appellant and six to nine months granted to Ashok Tent House
correctly observed that the said discrepancy was of no consequence
as it had no bearing on the unit price quoted.
9. Dealing with the third discrepancy, the learned Single Judge
observed that at the time of the first tender as also the second tender,
it was clearly notified that the term of delivery would require the
supplier/appellant to pay the freight for the goods being delivered to
the notified place but the freight had to be reimbursed. Thus, the
learned Single Judge has correctly observed that the price quoted
would clearly be linked to the supply price and would exclude the
freight element. The two prices would, therefore, be predicated on the
same factors. The learned Single Judge, thus, rightly came to the
conclusion that the so-called discrepancy alleged by the appellant
pertaining to the term/place of delivery was, therefore, of no
consequence.
10. In our view, the learned Single Judge has correctly observed in
the impugned judgment that only where there is a variance of a
material kind i.e. objective parameters being different resulting in
objective evaluation being rendered impossible or at least difficult,
comparability would be lost and, therefore, price at the risk purchase
stage will not form the measure to determine the loss suffered.
11. In the present case, the appellant has failed to show what was
the material variance between the terms of the two tenders. Even in
the counter statement filed before the learned Arbitrator, the
appellant had not set out any variance of a material kind to establish
that the objective parameters were different between the two tenders
and thus there could be no objective evaluation and that
comparability had been lost and, therefore, the price at the risk
purchase stage could not form the measure to determine the loss
suffered. Except for simply setting out the three discrepancies, no
factual basis was made out before the learned Arbitrator to aver that
these so-called discrepancies amounted to variance of a material kind
which would, in turn, effect the basis for determining the loss
suffered. Even during the course of hearing before us the counsel for
the appellant was unable to bring out any variance of a material
kind.
12. The learned Arbitrator has specifically given a finding that the
terms and conditions of the risk purchase tender was the same as
those of the original purchase. The learned Single Judge has rightly
concluded that identity in the terms and conditions does not have to
be literally construed. Trivial differences would make no difference
as long as the variance is not of a material kind. Neither before the
learned Arbitrator nor before the learned Single Judge or before us
has the appellant been able to make out any case of variance of a
material kind between the terms and conditions of the original tender
and the terms and conditions of the subsequent risk purchase
tender.
13. The learned counsel for the appellant has relied on the decision
of the Delhi High Court in UOI Vs. M/s Daisy Trading
Corporation's case (supra) which was affirmed by a Division Bench
of this Hon‟ble Court. The relevant paras of the said judgment are
reproduced hereinbelow:-
"6. A perusal of the award shows that the arbitrator tried to put cart before the horse and first considered the issue of risk purchase. The arbitrator on consideration of the legal pleas came to the conclusion that since the respondent had failed to participate in the risk
purchase advance tender, despite the judgments cited of different courts by the respondent, it was not necessary to compare the terms and conditions of the original purchase order and the risk purchase.
7. In my considered view this is contrary to law and is not even seriously disputed that in order for the risk purchase to be upheld, the terms and conditions of the two tenders should be more or less similar. It may however, be noticed that the arbitrator thereafter proceeds to state that on comparison of the terms and conditions he finds no major difference. There is no comparison recorded in the award of what terms and conditions were material and identical and if there were some "minor difference" what was the same. The award certainly suffers from absence of reasons on this account.
8. The arbitrator thereafter proceeds to record that since the respondent failed to supply the material, the petitioner was within its rights to make risk purchase. The arbitrator was required to consider the plea of the respondent whether the petitioner had not followed the terms of the original contract, calling upon the respondent to do certain things which were not envisaged in the original contract and thus the same amounted to novation of the contract. This plea of the respondent has not at all been considered. No finding has been recorded in respect of the same. Thus the award does suffer from absence of reasons even on this account."
14. However, the facts of that case were entirely different. That
was a case where the learned Arbitrator on consideration of legal
pleas came to the conclusion that since the respondent therein had
failed to participate in the risk purchase advance tender, despite the
judgments cited of different courts by the respondent, it was not
necessary to compare the terms and conditions of the original
purchase order and the risk purchase. It was in this background
that the learned Single Judge held the approach of the learned
Arbitrator to be incorrect and contrary to law. The learned Single
Judge in the said judgment, thus, held that the Arbitrator was
required to consider the plea of the respondent whether the petitioner
therein had not followed the terms of the original contract calling
upon the respondent to do certain things which were not envisaged in
the original contract and thus the same amounted to innovation of
the contract.
15. In the present case, the Arbitrator has compared the terms and
conditions of the two tenders and found them to be the same.
Further, no doubt that in the judgment of UOI Vs. M/s Daisy
Trading Corporation's case (supra), it was observed that the
Arbitrator therein had not recorded the comparison as to what terms
and conditions are material and identical and if there were some
minor differences, what were the same. Ordinarily, the comparison
of the terms and conditions should be contained in the decision.
However, in the present case, the respondent themselves failed to set
out in their counter statement any variance of a material kind
between the earlier tender and the subsequent risk purchase tender.
The learned Arbitrator on comparison of the terms and conditions
found them to be the same. No infirmity can be seen in the said
finding of the learned Arbitrator. Moreover, as explained by the
learned Single Judge the appellants have failed to make out a case of
any material variance between the two tenders. The judgments in
UOI Vs. M/s Daisy Trading Corporation's case (supra) or that of
Division Bench of this Court in FAO(OS) No. 570 of 2006 affirming
the said decision do not state that the terms and conditions of the
two tenders have to be identical and there cannot be any
minor/trivial differences between the same. What is important is
that there should be no variance of a material kind which in turn
would effect the price at the stage of risk purchase tender not forming
the correct measure to determine the loss suffered.
16. The learned counsel for the appellant also relied on the
judgment of the Hon‟ble Supreme Court in M/s. Murlidhar
Chiranjilal vs. M/s. Harishchandra Dwarkadas & Anr., reported
as 1961 (1) SCR 653, the relevant part of which reads as follows :-
"The two principles on which damages in such cases are calculated are well-settled. The first is that, as far as possible, he who has proved a breach of a bargain to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed; but this principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable steps to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps: (British Westinghouse Electric and Manufacturing Company Limited v. Underground Electric Railways Company of London (1912) A.C. 673, 689). These two principles also follow from the law as laid down in s. 73 read with the Explanation thereof. If therefore the contract was to be performed at Kanpur it was the respondent‟s duty to buy the goods in Kanpur and rail them to Calcutta on the date of the breach and if it suffered any damage thereby because of the rise in price on the date of the breach as compared to the contract price, it would be entitled to be re-imbursed for the loss. Even if the respondent did not actually buy them in the market at Kanpur on the date of breach it would be entitled to damages on proof
of the rate for similar canvas prevalent in Kanpur on the date of breach, if that rate was above the contracted rate resulting in loss to it. But the respondent did not make any attempt to prove the rate for similar canvas prevalent in Kanpur on the date of breach. Therefore it would obviously be not entitled to any damages at all, for on this state of the evidence it could not be said that any damage naturally arose in the usual course of things."
17. We fail to understand how this judgment has any relevance to
the facts of the present case. This was a case where one of the
question which arose for consideration was the taking of reasonable
steps to mitigate the loss consequent on the breach. The Hon‟ble
Supreme Court in the said case has held that even if the respondent
did not actually buy the goods in the market on the date of the
breach, it would still be entitled to damages on the proof of the rate
for similar goods prevalent in the market on the date of the breach if
that rate was above the contracted rate resulting in loss to it. But
since the respondent in that case did not make any attempt to prove
the rate for similar goods prevalent in Kanpur on the date of the
breach, it was held that he was not entitled to any damages at all.
This was a case which dealt with mitigation of losses and not with a
risk purchase tender. Moreover, the facts of the said case or the
decision rendered therein have no bearing on the case at hand. The
learned Single Judge has correctly distinguished M/s. Murlidhar
Chiranjilal's case(supra). The learned Single Judge has rightly
observed that in the instant case, risk purchase tender was opened to
all eligible suppliers throughout the territories of India and the
prices received would reflect the prices offered by various suppliers.
This, the learned Single Judge has correctly held would include the
suppliers at Delhi, Nasik and Vasai.
There can be no quarrel with the proposition that the material
conditions of the two tenders cannot be at variance if the price of the
risk purchase tender is to form the basis of the measure of the loss
suffered. However, the appellant has failed to make out any case of
variance of a material kind between the two tenders. Minor
differences or differences which have no bearing, whatsoever, on the
price in the risk purchase tender cannot be considered to be a
variance of a material kind.
18. We find no infirmity in the impugned judgment. This appeal is
accordingly dismissed.
NEERAJ KISHAN KAUL [JUDGE]
MUKUL MUDGAL [JUDGE] JULY 27, 2009 sb/RS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!