Citation : 2009 Latest Caselaw 2841 Del
Judgement Date : 27 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)1745A/1993
% Date of decision: 27th July,2009
M/S. SIEMENS LTD. ....... Petitioner
Through:- Mr. C.M. Oberoi with Ms. Surekha
Raman, Advocates.
Versus
M/S. SOUTH INDIA CEMENTS LTD. ....... Respondent
Through:- Mr. L.P. Dhir & Mr. Manoj Yadav,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may No
be allowed to see the judgment?
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1. The suit was registered on a petition under Sections 14 & 17 of
the Arbitration Act, 1940 for filing and making the arbitral award
dated 30th June,1993 rule of the court. On the award being filed in
this court and notice of filing thereof being given to the parties the
respondent M/s South India Cements Ltd. filed IA No.8418/1994
under Sections 30 & 33 of the 1940 for setting aside of the award.
The pleadings in the said application completed and the usual issues
framed on 19th July, 1995. The petitioner, M/s Siemens Ltd. did not
file any objections to the award and has during the hearing also
supported the award. However, application being IA No.1300/2009
has been filed by the petitioner for award of interest at 18 % per
annum from the date of the award and for the period during which
the proceedings for making it a rule of the court have remained
pending and till payment of the amount. The counsel for the
respondent had on 3rd November,1995 informed the court that the
respondent had been declared a sick company within the meaning of
SICA, 1985 and had been referred to the BIFR. Subsequently, IA
No.8788/2000 was filed by the respondent under Section 22 of SICA,
1985 for suspension of the present proceedings. However, on 27th
March, 2001 the said application was withdrawn in light of the
judgment of the Division Bench of this court in M/s Lloyd
Insulations (India) Ltd. Vs. Cement Corporation of India Ltd.
90 (2001) DLT 1 (DB) with liberty to file a fresh application but
neither any fresh application was filed nor any argument in this
regard was raised at the time of hearing.
2. To complete the narration it may also be stated that the
arbitrator who has rendered the award was appointed vide an order
dated 15th April, 1991 of this court in suit No.387A/1989. The
arbitrator so appointed was a technical rather than a legal person
and it is also not disputed that he during the arbitration, on 2nd & 3rd
July, 1992 carried out inspection of the cement plant of the
respondent to inspect the works carried out by the petitioner therein
and also directed the petitioner to carry out certain works.
3. The disputes arose between the parties out of a contract dated
1st May,1985/2nd August,1985 between the parties, containing a
provision for arbitration. The respondent was setting up a cement
plant at Malkhed, Karnataka and had vide contract aforesaid
appointed the petitioner as Electrical Contractor for the said
proposed cement plant, to do detailed designing and engineering and
to supply certain electrical equipment and to erect and commission
the same. The said contract in Clause 7.7 of General Conditions of
Contract provided for arbitration to a sole arbitrator to be appointed
by the parties with mutual consent and upon the parties being
unable to mutually agree, to the sole arbitrator to be appointed by
the Chairman & Managing Director of Engineers India Ltd. (EIL)
who were appointed as the Engineer In-charge or Consulting
Engineer by the respondent with respect to the proposed cement
plant. There was no requirement in the said arbitration clause for
the arbitrator to give a reasoned or speaking award. There was no
such requirement in the Arbitration Act, 1940 also. However, the
parties are ad-idem that they jointly requested the arbitrator on 11th
April, 1992 to give a reasoned award. The list in this regard between
the parties is only to the extent, whether the arbitrator was bound by
the said request of the parties or not.
4. The arbitral award is for payment of a total sum of
Rs.87,94,000/- by the respondent to the petitioner under the
following heads:-
i. Rs 30 lacs towards the amount of two bank guarantees
furnished by the petitioner to the respondent and which
the arbitrator found to have been wrongly encashed by
the respondent.
ii. Rs 20,25,000/- towards interest @ 18% p.a from the date
after encashment of bank guarantee till 31st May 1993
being the end of the month proceeding the date of award
on the aforesaid sum of Rs 30 Lacs.
iii. Rs 7,42,000/- towards balance amount payable by
respondent to the petitioner for supplies made and work
done.
iv. Rs 6,23,000/- towards interest @ 18% p.a. from the date
of substantial completion of works by petitioner till 31st
May 1993 supra on the amount mentioned in (iii).
v. Rs 6,00,000/- towards value of material, tools,
instruments of petitioner which the respondent had not
permitted the petitioner to remove from the site.
vi. Rs.5,04,000/- towards interest @ 18% p.a on amounts in
(iv) above, from date of substantial completion of work
till 31st May 1993 supra.
vii. Rs 10 Lacs towards establishment costs or recompense
or compensation or damages payable by the respondent
to the petitioner for delays attributable to respondent.
viii. Rs.3,00,000/- towards costs of arbitration .
5. The arbitrator did not award any future interest from the date
of the award to the petitioner. The claims of the petitioner against
the respondent were for more than the amount awarded. However,
the petitioner having not preferred any objections to the award,
there is no need to go into the same.
6. The respondent had made 14 claims before the arbitrator
against the petitioner; the same are listed herein below together
with the findings of the arbitrator thereon:-
a. Of Rs.2,29,896/- permitted to be revised to Rs.3,26,525/- for not removing the 23 check list points prepared by EIL.
The arbitrator held the petitioner to have substantially
attended to the check list points as were within the scope
of its work except the two relays, compensation of
Rs.56,000/- with respect whereto was taken into
consideration and deducted out of the claims of the
petitioner against the respondent.
b. Of Rs.7,44,024/- permitted to be revised to Rs.9,47,297/- by way of damages due to supply of VOLTAMP Make Transformer instead of Bharat Bijlee Make and the unsuitability of the VOLTAMP Make Transformer.
The arbitrator held that the petitioner could not blamed
for the alleged unsuitable character of the transformer
supplied, but awarded a sum of Rs.1,50,000/- to the
respondent on account of the change in make of the
transformer and gave adjustment of the same in
calculating the amount due to the petitioner from the
respondent.
c. Of Rs.11,42,476.25p revised to Rs.13,61,399.25p as expenditure and damages on rectification of defects and maintenance liability period.
The arbitrator held that the respondent had itself by its
conduct, in or around September, 1989 given up the
terms of the contract and further held that the petitioner
had no duty to perform after September, 1989. Hence,
the claim of the respondent was rejected.
d. Of Rs.2,12,52,393.39p by way of damages for non-
completion of the work of inter-locking system pertaining to local and control panels. The arbitrator held the petitioner not responsible for
refusing to do and/or not doing the modification work
which was found to be in the nature of additional work
and further held its scope was not clear. The arbitrator
also held the claim to be remote. Hence, the said claim of
the respondent was rejected.
e. Of Rs.4,70,228.58p on account of petitioner's failure/refusal to supply the post commission spares of the value of Rs.2,00,000/-.
The arbitrator awarded an amount of Rs.2,00,000/- to the
respondent on this account and adjusted the same out of
the monies found due to the petitioner from the
respondent. The balance claimed under this head was
rejected.
f. Of Rs.5,94,000/- for damages attributable to petitioner's failure to provide the Warranty Bank Guarantee in an amount of Rs.12 lacs.
The arbitrator held that since the respondent had failed
to discharge and return to the petitioner the earlier two
bank guarantees in the sum of Rs.30 lacs and which two
bank guarantees were valid only up to the
commissioning, the petitioner was justified in not
providing the third bank guarantee for Rs.12 lacs which
was for warranting the equipment. The said claim of the
respondent was thus rejected.
g. Of Rs.2,60,32,713/- by way of damages for the petitioner abandoning the site in or about March, 1989.
The arbitrator found that the petitioner till about
September, 1989 did look upon the contract with the
respondent as valid and binding and did not leave the
site in March, 1989. The arbitrator further held that after
September, 1989 the petitioner was under no obligation
to do anything. Hence, the claim of the respondent was
rejected.
h. Of Rs.14,63,375.40p for mis-utilization of the mobilization advance.
The arbitrator held that the petitioner did not mis-utilize
the advance and on the contrary tolerated the
respondent's non-payments and delayed payments. He
further found that when extensive changes and additions
were introduced into the contract by the respondent and
EIL the petitioner was not given any additional advance.
Hence, the claim of the respondent was rejected.
i. Of Rs.37,84,252.43p for over billing and breach of contract.
The arbitrator found that the petitioner had conceded an
amount of Rs.13,50,189/- adjustment whereof was given
by the arbitrator. The arbitrator found the respondent
not entitled to any other amount and hence the claim for
the balance amount was rejected.
j. Of Rs.48,607.10p which was conceded by the petitioner
and was taken into account by the arbitrator while
making the award in favour of the petitioner.
k. Of Rs.6 lacs by way of liquidated damages for delayed execution of the work.
The arbitrator found the respondent to have delayed the
execution and therefore rejected the claim.
l. Of Rs.10,58,671.98p by way of damages for failure to put in the necessary work in-spite of receiving full payment including 15% retention money.
The arbitrator rejected the claim of the respondent that
the retention money was not payable by the respondent
to the petitioner and hence disallowed the claim. The
arbitrator further held that the petitioner did it's best to
perform the contract in-spite of several changes,
qualitative and quantitative, made by respondent and EIL
and in-spite of several and substantial non-payments and
delayed payments and other defaults by the respondent.
m. Of Rs.9,91,450/- of costs of arbitration.
The arbitrator found the essential justice of the case with
the petitioner and having found the respondent to have
failed to carry out its contractual duties, responsibilities
and liabilities held the respondent not entitled to costs of
arbitration. Per contra, costs of Rs.3 lacs as aforesaid
were awarded to the petitioner against the respondent.
n. Of Rs.2,94,922/- on account of penal charges paid to Karnataka Electricity Board.
The arbitrator found the respondent itself to blame for
the delay in the work of switchyard and further held that
the petitioner is not in any way concerned with these
penalty charges or minimum charges and hence
dismissed the claim.
7. The respondent has in IA No.8418/1994 on the one hand
pleaded that no reasoning has been given while deciding any of the
claims or counter claims; that the award merely sets out the
pleadings, oral evidence and the documents and after recording that
the arbitrator had applied his mind to the evidence produced,
without referring to any particular document, oral evidence or
pleadings given the award, and on the other hand in other
paragraphs it is pleaded that the doctrines/principles relied upon by
the arbitrator had no application or limited application. Thus there
is inherent contradiction in the pleadings at least qua the ground of
award being unreasoned. In my opinion reading the objections of the
respondent as a whole, the ground of the award being non-speaking
or unreasoned is not made out.
8. In fact what the arbitrator has done in the award is, to after
setting out the pleadings, documents and the evidence and the
applications filed by the parties and before proceeding to discuss the
claims and the counter claims of the parties, in paras A.1 to A.37
given his general findings. He has held that the respondent having
appointed EIL as a Consulting Engineer for getting implemented the
contract with the petitioner, EIL's say would have been significant on
many important aspects of actual performance of the petitioner; he
has further recorded that though EIL was requested to depute
representative to be a witness in these proceedings but EIL did not
depute any such representative as a witness. The arbitrator also
found that the respondent was a new company having no
manufacturing experience or experience of setting up manufacturing
plant and that partly explained, according to the arbitrator, several
mistakes and failures on the respondent's part in implementing the
contract. The arbitrator further found that the respondent and EIL
had made substantial changes and additions at different stage in
quality/number and also on the specifications of the equipment to be
supplied by the petitioner and which substantially contributed to
delays in the petitioner's performance of the contract.
9. The arbitrator further found that the respondent and EIL
delayed feeding of engineering inputs to the petitioner and found the
same to be the main reason for delayed implementation of the
petitioner's work. The arbitrator further found that the respondent
had substantial financial difficulties and delayed repeatedly and on a
substantial scale the payments for supply made and work done by
the petitioner and which delays added to the total time taken. The
arbitrator further held that the respondent did not give any
importance to the dates stipulated in the agreement for completion
and did not arrange for the basic engineering inputs, drawings,
standard and specification necessary for the petitioner to perform its
part of the agreement. The arbitrator further found that the
respondent did not hold regular periodical coordination meetings of
all the contractors engaged by it and which meetings were necessary
for inter-connected and inter-dependent activities/tasks of each
contractor as well as the respondent. It was also found that owing to
differences between respondent and EIL, EIL had left the site and
owing to the decision of the respondent, subsequent to contract with
the petitioner, of having DG sets in addition to normal electric power
supply, ancillary changes and modifications had to be introduced in
the work of the petitioner and which radically changed the contract
between the petitioner and the respondent; the said introduction of
DG sets was also held to be a major cause for delay.
10. The arbitrator also found that the two bank guarantees
furnished by the petitioner of Rs.30 lac were valid only up to
commissioning of equipment supplied by petitioner and the said
commissioning had been done in May, 1988/September, 1988 and in
June, 1989 there was no justification for the respondent to encash
the said guarantees. The arbitrator also found that the loss claimed
by the respondent were indirect, remote, irrelevant, inconsequential
or insignificant in nature and there was no warranty by the
petitioner as to the quantity or quality of cement that would be
produced in the plant of the respondent. The arbitrator also held
that the respondent had not taken any prompt action with respect of
the alleged breaches on the part of the petitioner and had not
mitigated the losses or damages alleged.
11. The counsel for the respondent/objector has contended that
the award does not comply with the request of the parties for a
reasoned award and relied upon the dicta of the Division Bench of
this court in College of Vocational Studies Vs. S.S. Jetli AIR 1987
Delhi 134. It is argued that the arbitrator has given his meandering
thoughts which do not amount to reasoning as required by law.
Attention in this regard is also invited to M/s Short Pile
Construction Co. Vs. DDA 76 1998 DLT 189. In response to the
contention of the counsel for the petitioner of the arbitrator being
not bound by the request of the parties for a reasoned award
reliance is placed on K.N. Damodharan Vs. State of Kerala (2000)
10 SCC 351 and on BSNL Vs. Subash Chandra Kanchan (2006) 8
SCC 279. The counsel for the respondent towards the end also cited
Gora Lal Vs. Union of India (2003) 12 SCC 459 also laying down
that where the agreement of the parties required the arbitrator to
indicate his findings along with the sums awarded, separately on
each individual item of the dispute and where the arbitrator did not
record findings on each item, the same was held to be a ground for
setting aside of the award. I may, however, notice that the Supreme
Court in the said judgment made it clear that the same was confined
to the facts of that case and to the interpretation of the clause of the
agreement in that case. In the present case, I may reiterate that not
only there was no requirement in the agreement for giving reasons
but on 11th April, 1982 request is stated to have been made only for a
reasoned award and not for a finding on each and every item. Thus
the last of the said judgments which the Supreme Court confined to
the facts of its own is not applicable.
12. Per contra, the counsel for the petitioner has contended that
the arbitrator was not obliged to give a reasoned award. He has also
argued that from a reading of the award in the present case it is
manifest that it is the result of due consideration of all the evidence
produced and the submissions made and contains the findings and
observations as a result of perusal and study of the evidence and the
site visit. It is controverted that the award is not reasoned. The
counsel for the petitioner has also argued that a reasoned award
amounted to a judgment of the court and merely because the award
is not written in the language as a judgment, is no ground for
averring that the same is unreasoned or non-speaking. The counsel
for the petitioner relied upon India Oil Corporation. Vs. Indian
Carbon Ltd. JT 1988 (2) SC 212 holding that it is one thing to say
that reasons should be stated and another thing to state that a
detailed judgment be given in support of the award; even if it be held
that it is obligatory to state the reasons, it is not obligatory to give
detailed reason. To the same effect is Gujarat Water Supply &
Sewerage Board Vs. Unique Erectors (Gujarat) (P) Ltd. AIR
1989 SC 973 wherein the Supreme Court held that an award should
be read reasonably as a whole to find out the implication and the
meaning thereof - short intelligible indications of the grounds should
be discernible to find out the mind of the arbitrator for his action;
even if it be enjoined that reasons have to be stated - the said
reasons should be intelligible and should deal expressly or impliedly
with the substantial points that have been raised - sufficiency of
reasons depends upon the facts and circumstances of the case and
the court does not sit in appeal over the award and review of the
reasons. The counsel for the petitioner also relied upon Chaudhary
Construction Co. Vs. MCD 1995 34 DRJ 487 also laying down that
the arbitrator is only required to indicate his mind set as to how he
arrived at the decision in the award and sufficiency and quality of
evidence is a matter for the arbitrator and the court is not permitted
to reappraise the evidence and sit as a court of appeal over the
arbitrator's award.
13. I am unable to accept the contention of the counsel for the
petitioner that in-spite of the parties having requested the arbitrator
to give a reasoned award, the arbitrator was not bound by the said
request. The arbitrator is a creature of the contract between the
parties and is bound by the same. Just like an arbitrator is bound to
give a reasoned award when the arbitration agreement provides so,
even where the parties reach an agreement for the award to be
reasoned, after commencement of arbitration, the arbitrator would
be bound by the said agreement. I do not see any differences in such
agreement for the award being reasoned being reached prior to
reference to arbitration or post such reference. The only option of
the arbitrator, where the consensus for a reasoned award is reached
post reference is to, if not desirous of proceeding with the arbitration
and giving reasoned award is to recuse himself. The arbitrator in the
present case having not done so, impliedly consented to give a
reasoned award.
14. I am however unable to accept the contention of the counsel
for the respondent of the award in the present case being non-
speaking or unreasoned or of the award with respect to some of the
claims only being reasoned and being unreasoned with respect to the
others. In this regard, the judgment (supra) laying down that the
requirement for reasons is to be viewed in the facts and
circumstances of each case is apposite. The facts of the present case
were inter-alia concerned with the delays in execution of the work
and non-completion of the work by the petitioner and the claims
against each other arising therefrom. The arbitrator before dealing
with the individual claims and counter claims has in paras A.1 to
A.37 returned general findings with reasons. In the facts of the case,
the general findings with reasons govern the findings written
subsequently by the arbitrator with respect to individual claims and
counter claims. It is for this reason that the findings written with
respect to individual claims are not lengthy and which has given
occasion to the respondent to take the plea of the award being not
reasoned as it was required to be. In view of the detailed reasons
and findings in para A.1 to A.37, the reason for rejection or
acceptance of individual claims and counter claims are implicit.
Wherever required, the arbitrator has supplemented the same with
other reasons.
15. Test whether reasons exist or not is not quantitative but
qualitative. To justify the award as reasoned, the length thereof is
not to be seen. There may be cases where in-spite of several pages
having been devoted to each claim, award may still be held to be
unreasoned or non-speaking. Conversely, reasons may be in the form
of a single word or sentence. The courts are thus while dealing with
such pleas not to be swayed merely because it is demonstrated that
with respect to a particular claim no reason has been given, if from
the contents of the other paragraphs or from a reading of the award
as a whole, the reason for the arbitrator having reached the
conclusion in a particular paragraph in which no reasons may have
been stated is decipherable or is implied.
16. The arbitrator, as aforesaid was a technical and not a legal
person. Such technical persons are not expected to be steeped in
law and familiar with language as the lawyers and the courts are
accustomed to. Axiomatically, the award of such an arbitrator
cannot be expected to be in the form of a judgment of the court or
pass the test of the form in which a judgment of the court, also
required to be reasoned, is written.
17. I have in Jai Singh Vs. DDA 2008(3) ARBLR 667 (DELHI) and
the Division Bench of this court in DDA Vs. Sunder Lal Khatri's
Sons 157 (2009) DLT 555 dealt with the aspect of and defined
"reason". Reason is a ground or motive for a belief or course of
action, a statement in justification or explanation of belief or action.
It is in the sense that the award must state reasons for the amount
awarded. Reason is the link between the materials by which certain
conclusions are based and the actual conclusions.
18. Though the respondent has in para 3 of the preliminary
objections in IA No.8418/1994 contended that the arbitrator has
given a finding only in respect of 6 claims out of the 14 claims raised
before him and the award is silent/non-speaking in respect of rest of
the claims, the respondent has not specified with respect to which of
the claims the award is averred to be silent/non-speaking. The
objections of the respondent thereafter in the paragraphs on merits
are as to insufficiency of evidence for the findings of the arbitrator.
The sufficiency or insufficiency of evidence before the arbitrator for
reaching a particular finding is not within the domain of this court.
The counsel for the petitioner has in this regard rightly relied upon
M/s Sudarsan Trading Co. V. Govt. of Kerala AIR 1989 SC 890
laying down that appraisement of evidence by the arbitrator is never
a matter which the court questions and considers and that the
arbitrator is the sole judge of the quality as well as the quantity of
evidence and it is not for the court to take upon itself the task of
being a judge on the evidence before the arbitrator. Reliance was
also placed on Indu Engineering & Textiles Ltd. Vs. DDA 2001 5
SCC 691 on the proposition that a plausible view taken by the
arbitrator could not be said to be suffering from any manifest error
on the face of the award or wholly improbable or perverse one and
cannot be interfered with. The counsel for the petitioner also
referred to UP State Electricity Board Vs. Searsole Chemicals
Ltd. (2001) 3 SCC 397 to the effect that where the arbitrators have
applied their minds to the pleadings the evidence adduced before
them and the terms of the contract, there is no scope for reappraisal
of the matter by the court as if it were an appeal and where two
views are possible, the view taken by the arbitrator would prevail.
The judgments of the Supreme Court in Smita Conductors Ltd. Vs.
Euro Alloys Ltd. (2001) 7 SCC 328 and in Puri Construction Pvt.
Ltd. Vs. Union of India AIR 1989 SC 777 were also cited in this
regard.
19. The counsel for the respondent in support of his proposition
relied on Rajasthan State Mines & Minerals Ltd. Vs. Eastern
Engineering Enterprises (1999) 9 SCC 283 to the effect that the
arbitrator is bound by the contract of the parties. On the basis of the
said judgment error on the face of the award is averred with respect
to the doctrine of substantial performance adopted by the arbitrator
in contravention of the contract.
20. I am afraid the same is not the position. The arbitrator has not
given go bye to the 23 defects which were pointed out by EIL to be
rectified by the petitioner. What the arbitrator has held is that the
same were complied and/or those which were not complied were
either not required to be complied or which were required to be
complied and not complied, the arbitrator has given adjustment with
respect thereto. Thus, the findings by the arbitrator are findings of
fact and plausible and are non-interfereable in this jurisdiction. The
counsel for respondent further relied upon :-
(i) K.V. George Vs. Secretary to Government Water & Power
Department, (1989) 4 SCC 595. In this case, the counter claims
had not been considered. That is not the position here and thus the
judgment is not applicable.
(ii) The respondent also referred to Food Corporation of India
Vs. Chandu Construction (2007) 4 SCC 697 which is also a case of
departure by the arbitrator from the contract and which has been
held to be a misconduct. This judgment is also not applicable to the
facts of the present case. The arbitrator in the present case has
either held the contractual term to be complied or to have been
varied with the consent of the parties. Neither of the said findings is
interfereable under Sections 30 & 33, of the 1940 Act and no finding
of the arbitrator is shown to be in the teeth of unambiguous terms of
the agreement.
(iii) The respondent also referred to Bharat Coking Coal Ltd. Vs.
Annapurna Construction (2003) 8 SCC 154. This is also a case of
the arbitrator travelling beyond the contract and which has been
held to be without jurisdiction. No case herein is made out of the
arbitrator travelling beyond the terms of the contract.
(iv) Union of India Vs. Banwari Lal & Sons (P) Ltd. (2004) 5
SCC 304 defining misconduct as ignoring of material documents,
evident from the face of the record and/or if the award is based on a
erroneous proposition of law apparent from award itself. I find the
same also to be not the case herein.
(v) Ramachandra Reddy & Co. Vs. State of Andhra Pradesh
(2001) 4 SCC 241 holding an erroneous legal proposition made the
basis of the award and such proposition being discernible from the
award itself a ground for setting aside of the award. Objection in
this regard is taken to the doctrine of anticipated breach and
substantial performance referred by the arbitrator. I do not find that
such doctrine even if in applicable, forms the sole basis of the award.
The award has generally recorded that the petitioner had completed
the works for which its claims have been allowed. The award further
records the findings with respect to the conduct of the parties and
the resultant delays and thus holds the actions of the petitioner to be
not in breach of the contract. In my opinion, even independently of
the reference to the said doctrines, there are sufficient reasons in
the award for the findings returned.
21. I have already dealt with the various contentions in the
objections petition. The counsel for the respondent has tried to build
his case only on the principles laid down by the Division Bench of
this court in College of Vocational Studies (Supra). However, on
perusal of the award in the present case, I do not find the same to be
without reasons, considering the facts and circumstances of the
case. This court while appointing the arbitrator considering that the
matter involved some technical knowledge had not only appointed a
technical person as arbitrator but also permitted the arbitrator to
also take assistance of other technical persons in this regard. The
arbitrator in the present case has given the award after visiting the
site and inspecting the same. The counsel for the respondent
contended that though the arbitrator who had rendered the award
has died ten years ago but the case merits remand to another
arbitrator for rehearing. No purpose will be served in remanding the
matter in as much as the position at site may have changed
drastically in the last 15 years. It would not be possible for any new
arbitrator even if appointed to have the feel which the arbitrator
whose award is challenged had the benefit of, by inspection at the
contemporaneous time.
22. That leaves the prayer of the petitioner for award of interest.
Though no objection has been taken by the petitioner to the award
before this court but I find that in Amar Industries Vs. U.O.I.
(2006) 2 Arb. LR 253 (Delhi) this court has taken a view that this
court is empowered to award interest for the period, the proceeding
for making the award a rule of the court remained pending before
this court. The same view otherwise follows in law; under the 1940
Act the court had the inherent power to modify the award. In the
present case, the objections have remained pending before this court
for a long time of over 15 years. The value of the money awarded 15
years ago would have totally eroded today and even interest would
not afford actual compensation. The buying power of the rupee has
considerably come down in the last over 15 years. I thus award
interest on the awarded amount at 10% per annum from the date of
institution of the IA No.8418/1994 in the court and till the date of
payment. The petitioner shall also be entitled to costs of these
proceedings quantified at Rs.50,000/- from the respondent.
23. The award as modified aforesaid is thus made rule of the court
and judgment in terms thereof passed. The petitioner shall also be
entitled to interest @ 10% p.a. on the principal amount u/s. 29 of the
1940 Act, from the date of decree till payment.
Decree sheet be drawn up.
RAJIV SAHAI ENDLAW (JUDGE) July 27, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!