Citation : 2009 Latest Caselaw 2817 Del
Judgement Date : 24 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)No.851A/1995
% Date of decision:24th July, 2009
M/S R.P. BUILDERS ....... Petitioner
Through: Mr. Raman Kapur, Advocate.
Versus
DDA ....... Respondent
Through: Ms. Anusuya Salwan, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The suit was registered on receipt/filing of arbitral award
dated 19th May, 1994 in this court. Notice of filing of the arbitral
award was issued to the parties and the petitioner M/s R.P. Builders
filed IA No.633/1996 under Sections 30 & 33 of the Arbitration Act
objecting to the award in so far as rejecting/declining its claims.
Pleadings in the said application were completed and on 19 th
September, 1997 the usual issues framed. Though the parties were
directed to file affidavit evidence and there is on record an affidavit
by way of evidence on behalf of the petitioner but on 24 th September,
1998 both the counsels stated that the arbitration proceedings which
had been received in this court, only be read as evidence in the
present suit and no further evidence was required to be recorded.
The respondent DDA has not filed any objections to the award. The
counsels for the parties have been heard.
2. Claim No.1 of the petitioner before the arbitrator was of
Rs.30,000/- on account of unlawful withholding of the said amount
from the final bill for the reason of quality control. During the course
of proceedings before the arbitrator the respondent DDA admitted
that a sum of Rs.20,300/- out of the said deductions was releasable in
favour of the petitioner. The petitioner also on 26th August, 1993
agreed to withdraw the claim for Rs.30,000/- subject to the amount
of Rs.20,300/- being released to him on or before 30th September,
1993. The arbitrator records that the said monies were not so
released by the respondent DDA in favour of the petitioner. The
arbitrator however under the said claim awarded the sum of
Rs.20,300/- only to the petitioner. The counsel for the petitioner has
contended that there is no reason in the award for not allowing the
entire claim of Rs.30,000/-.
3. Undoubtedly the arbitrator has been swayed by the offer of the
petitioner in the hearing on 26th August, 1993 to withdraw the entire
claim of Rs.30,000/- if Rs.20,300/- admitted by DDA were paid on or
before 30th September, 1993. Technically speaking, the offer of the
petitioner for withdrawing the claim of Rs.30,000/- was conditional
to the payment being made by the stipulated date and on that
payment being not made by the stipulated date the said offer
disappeared. However, what cannot be lost sight of is that the
arbitrator is a private court/forum chosen by the parties themselves
as an alternative to the court and for the sake of expediency.
Arbitration was/is not intended to be a first step in litigation. A party
opting for arbitration makes a conscious choice that instead of
hierarchy of courts as under the ordinary law of land being available
to him, he would be bound by the order/award of such private
court/forum. The role of the courts against the said awards is very
limited and supervisory. The parties having made such a choice take
the inherent risk of the said arbitrator's sense of justice and fair
play. The courts, unless find the sense of justice/fair play applied by
the arbitrator to be totally perverse are not to interfere with the
same. The arbitrator has in the award stated that he has examined
the statements and evidence of the parties and their respective
submissions. If after such an exercise the arbitrator has chosen to
dispose of the claim No.1 with the award for an admitted amount
only, considering the amount involved and totality of the
circumstances, in my opinion no perversity or misconduct can be
attributed to the arbitrator. The arbitrators are entitled to draw
general conclusions. The counsel for the petitioner also neither in
the objections nor at the time of hearing pointed out any such
material on the arbitral record from which it can be said that the
balance amount of Rs.9,700/- was payable and in-spite thereof not
granted by the arbitrator. I, therefore, do not find any merit in the
objections with respect to the award under claim No.1.
4. Claim No.2 of the petitioner was on account of recovery of
Rs.28,647.37p by the respondent DDA from the amounts due from
DDA to the petitioner on account of penal recovery i.e. at double the
rate of excess, cement, SCI, G.I. & L.A. Pipes not returned by the
petitioner to the respondent DDA. The arbitrator found that the
petitioner had in carrying out the work consumed the material/goods
aforesaid in excess of the agreed variations; that the petitioner was
supposed to utilize the material in optimal way without wastage; that
the petitioner having so wasted was in accordance with the terms of
the contract (clause 42) liable for payment at penal i.e. double the
issue rate of the said material. The arbitrator also found, as a matter
of fact, that the petitioner had not proved return of the excess L.A.
Pipe 150 mm dia meter and was thus liable for penal value thereof
also.
5. The petitioner objects on the ground that no penal recovery
could have been ordered without proving the actual loss; that though
the respondent DDA has sought time to submit details of the loss
suffered but no such losses were proved; that in the absence of
actual loss, no award at penal rate could have been made.
6. It is not disputed that the respondent DDA under the
agreement with the petitioner was entitled to penal recovery. The
factual finding of the arbitrator of excess consumption is non
interfereable in these proceedings and, in any case, has also not
been challenged in the objections. The Supreme Court in the short
judgment in Hindustan Tea Co. Vs. K. Sashi Kant Co. AIR 1987
SC 81 reiterated that once it is found that the award is a reasoned
one, under the law, the arbitrator is made the final arbiter of the
dispute between the parties and the award is not open to challenge
on the ground that the arbitrator has reached a wrong conclusion or
has failed to appreciate facts.
7. As far as the ground made out in law, of no penalty being
payable without proof of loss, is concerned, the Supreme Court in
ONGC Ltd. Vs. Saw Pipes Ltd. AIR 2003 SC 2629 has held that
when such contracts by pubic bodies provide for penalties, absolute
insistence on a proof of loss cannot be made. The Supreme Court
observed that in the functioning of public bodies there could be no
proof of loss. Examples were cited of no particular individual or
person suffering by delay in construction of roads or bridges. It is the
public at large which suffers. In view thereof, the petitioner's
reliance on earlier judgment of this court in A.K. Jain Vs. U.O.I. suit
No.136 of 1991 decided on 23rd March, 1993 with respect to clause
42 is of no avail.
8. The clause for penal recovery appears to have been made in
the contract, in which part of the material used in execution of the
contract is provided by the respondent DDA, to ensure that there is
no wastage of such material. It is the public at large which suffers
from such wastage. By providing penal rate of recovery, it is
expected that the contractors will ensure return of excess material.
In such a situation, in my view, no absolute insistence can be made
on proof by loss before the agreed penalty can be awarded. No error
is thus found in the award on this ground also and the objection is
rejected.
9. Claim No.3 of the petitioner was for recovery of the amounts
stated to have been wrongfully deducted out of the bills towards
agreed rebates; it is contended that the respondent DDA was entitled
to the said rebates only on timely payment of monthly bills, final
bills, release of security deposit and all of which was not done and
hence such rebates were wrongly deducted and the DDA is liable to
make good to the petitioner the amount adjusted on this account.
10. The arbitrator has found the rebates to have been correctly
availed by the respondent DDA with respect to the months of which
payments were made timely; he has further found that for the
months for which the payments were not made within the stipulated
time, the petitioner had not carried out the work of the minimum
value i.e. of Rs.25,000/- required to be carried out in that month and
thus the payments due for that month were carried forwarded to the
next month along with rebate; that even for the months for which the
payments were made, the petitioner had failed to establish of having
carried out the work of the minimum value of Rs.25,000/- and for
want of evidentiary support that part of the claim could not be
granted; that though the completion certificate was dated 20th
August, 1991, the same was subject to carrying out of substantial
works which were carried out later and the final bill was released
within the stipulated time from the said completion of works and
thus the respondent DDA was entitled to rebate with respect to final
bills also. The release of the security deposit was also found to be
within the agreed time from the date of such completion of
remaining works and thus DDA found entitled to rebate on that
account also.
11. The counsel for the petitioner has vehemently contended that
the factual finding of the arbitrator of the work of the minimum value
of Rs.25,000/- having been not carried out in months in which the
payments were not released is contrary to the document Exhibit R-30
of the respondent itself. In the objection petition, it is further
pleaded that even in the pleadings the respondent had admitted the
work done to be of the minimum value of Rs.25,000/-. With respect
to the rebate on timely payment of final bill and release of security
deposit it is contended that even in-spite of completion certificate
issued by the respondent certain works remained to be completed at
the insistence of the respondent DDA only; it is argued that the
respondent DDA has a practice of getting the works of final paint,
fixing of brass items carried out just before the delivery of
possession of the flats to the allottees so as to avoid theft/pilferage
thereof between the time of completion and allotment of the flats. It
is contended that if the date of completion certificate issued is
considered, neither was the payment of the final bill nor the release
of security deposit was within the time so as to entitle the
respondent DDA to rebate.
12. I am afraid the findings of the arbitrator are again factual in
nature and on the law aforesaid it is not appropriate to interfere with
the award on the said grounds. Undoubtedly, the courts have in
some cases interfered with the award if found to be contrary to a
particular document or pleading. However, in my view each
inconsistency does not fall within the ambit of Sections 30 & 33 of
the Act. The role of the courts is supervisory only to prevent gross
injustice or misdemeanor on the part of the arbitrators. It is not each
inconsistency or invalidity which empowers the court to set at knot
the arbitration proceedings. There must exist an element of
carelessness, dishonesty, breach of the principles of natural justice
of the category so as to shock the judicial conscience of the court or
a prudent person. It is only then the award would be set aside or
modified or remitted to the arbitrator. If the courts were to start
interfering in the arbitral awards in every case where they find any
such inconsistency, the whole purpose of arbitration would be
defeated and the jurisdiction exercised with respect thereto be akin
to that of an appellate court.
13. In the present case, though the counsel for the respondent
DDA had no reply to Annexure R-30 relied upon by the petitioner but
the fact remains that the arbitrator notwithstanding the same has
reached a conclusion of payments having been made within the time
entitling the respondent DDA to rebate. I do not consider the
present inconsistency, even if any from the record, in the finding of
the arbitrator, to remit the award for reconsideration to the
arbitrator.
14. As far as the plea of the works carried out beyond completion
certificate is concerned, it is not disputed that the completion
certificate was conditional and various works stated therein to have
been not carried out were carried out subsequently. Even if it is to
be believed that a practice has evolved in DDA and DDA is
compelling the contractors to carry out the said works later, just
before the allotment of the flats, the fact remains that the same has
no basis in contract. Nothing wrong can be found with the approach
of the arbitrator of having decided the case in accordance with the
contract and in ignoring such practice, if any. After all, the
petitioner also, probably because of several contracts and future
business with DDA, also obliged DDA by, notwithstanding having
completed the work, not putting the final touches thereto till just
before the allotment of flats. The petitioner contractor cannot now
be heard to say that though for its own reasons it earlier acted as
desired by DDA, DDA is nevertheless liable to compensate the
petitioner for the same.
15. Claim No.4 of the petitioner was for Rs.2,00,000/- under Clause
10 (cc) of the agreement and in relation to the claims under Claims
No.3,5&7. The claim No.3 and the objections with respect thereto
have already been dealt with herein above. The objections to the
claims No.5 & 7 are considered herein below. If the objections of the
petitioner thereto succeed, the petitioner shall be entitled to
proportionate amount under this claim also.
16. Claim No.5 of the petitioner was for Rs.6,340.57p on account
of unjustified and arbitrary deduction made by the respondent DDA
for smooth finishing of RCC work. The arbitrator held the action of
the respondent DDA to be strictly in terms of specifications and
mode of measurements qualifying for payments in this regard and
hence rejected the claim.
17. The objection of the petitioner as pleaded only is that the
arbitrator has given no reasons. That is not true. The arbitrator has
held that the action of DDA is in terms of the specifications and mode
of measurements. The same are reasons enough for rejecting the
claim.
18. Claim No.6 of the petitioner was for Rs.50,000/- in respect of
extra/substituted items. The arbitrator awarded Rs.3,028.80p as
admitted by the respondent DDA. Neither has any argument been
addressed in this regard nor do I, in the objections of the petitioner,
find any plea with respect to rejection for the balance amount under
the said claim.
19. Claim No.7 of the petitioner was for Rs.66,000/- on account of
unjustified and arbitrary deductions made by the respondent DDA.
The arbitrator held the same to be an excepted matter under clause
25 (b) of the agreement. Clause 25(b) provides that the decision of
the Supdt. Engineer regarding the quantum of deductions as well as
justification thereof in respect of rates for substandard work shall be
final and would not be open to arbitration. There is no dispute
between the parties that if the said claim fell within the said clause
25 (b), the same was not arbitrable. The counsel for the petitioner
however contends that while clause 25(b) is only with respect to
reductions for substandard work accepted by DDA, the claim No.7
was not for such reductions but was on account of deductions made
from the bill. In this regard, the statement of facts of the petitioner
on arbitral record was perused. The claimant has therein inter-alia
stated that the entire work was executed under the supervision and
control of DDA; that DDA had in each RA bill certified that the works
have been done as per specifications; that whatever defects or
discrepancies were pointed out by the respondent DDA were duly
rectified before completion and only whereafter the provisional
completion certificate was issued; that nevertheless the respondent
DDA had made number of deductions, items and recovered amounts
against such deductions without even giving proper notice therefor.
The details of such deductions were contained in Annexure C.7 (A) to
the statement of claim.
20. A reading of the claim No.7 of the petitioner leaves no manner
of doubt that irrespective of the terminology of reduction/deduction,
it was the case of the petitioner also that the amount claimed had
been reduced/deducted for substandard work which though DDA was
entitled to reject and not pay for, had been decided to be accepted at
reduced rates. If there was any ambiguity in this regard, a reading
of Annexure C.7 (A) further clarifies the position. Each and every
item therein is found to be on account of the work not carried out as
per the agreed specifications. In view thereof, this court at least on
reading of statement of facts to which attention was invited is not
able to find any error in the award in treating the said claim to be
within the excepted matters. The objections with respect to claim
No.7 are also thus rejected.
21. Claim No.8 of the petitioner was for Rs.1,20,000/- for
deployment of watch and ward staff and day to day maintenance of
the flats from the alleged date of completion and till the date of
allotment of the flats by the respondent DDA. It is the case of the
petitioner that the works were completed on 20th August, 1991 when
the completion certificate was given and the works mentioned to be
remaining therein were left out at the instance of the respondent
DDA as aforesaid. The petitioner thus claimed expenses for securing
the flats.
22. I have with respect to the objections under Claim No.3 herein
above held that no error/misconduct can be found with respect to the
finding of the arbitrator of the work having been completed only on
20th May, 1992. Accordingly, this claim for watch and ward staff also
does not survive and the objection with respect thereto is also
dismissed.
23. Claim No.9 of the petitioner was with respect to the increase in
prices of materials, idle labour, T&P and establishment due to
prolongation of contract by 44 months after the stipulated date. A
sum of Rs.11 lacs was claimed on this account.
24. The arbitrator did not allow the said claim for the reason (i) of
the petitioner having while applying for extension of time waiving
any such claim (ii) finding a lot of internal inconsistencies,
contradictions and factual inaccuracies in the claim of the petitioner,
(iii) the claim being unsubstantiated by any material evidence,(iv)
there being no substantial documentary evidence, books of account
or the like having been adduced by the petitioner in proof of the said
document, and (vi) the said claim being also barred by Clause No.1
of the general conditions of contract.
25. The petitioner contends that the finding of the arbitrator of the
claim being barred by clause No.1 being contrary to the judgment of
this court and the arbitrator having not given any detailed reasons.
26. As aforesaid, the arbitrator has given several reasons for
rejecting the said claim. It cannot be thus said that the rejection of
the claim is without reason.
27. The counsel for the petitioner has relied upon judgment dated
13th March, 2006 of this court in Kamal Construction Co. Vs. DDA
in CS(OS) No.794/2000 setting aside the award in favour of DDA.
However, the court in that case had found the award to be without
any reasons and mechanical. That is not the position here. The said
judgment has no application. The counsel for the petitioner has also
relied upon Umed Singh Vs. DDA 91 (2001) DLT 126 with respect
to clause No.1 of the general conditions and holding that the same is
applicable only in cases where the delay was beyond control of DDA
and unavoidable and not where the delay was otherwise on part of
DDA and allowing claim on that account. I do not feel the need to
apply the ratio of the said judgment also to the facts of the present
case in as much as the arbitrator has referred to the said clause as
only one of the five reasons for rejecting the claim. The thrust of the
arbitrator is of there being no delay by DDA and the petitioner
having waived its right to claim any damages. That reason, in my
opinion is enough not to interfere with the award.
28. I may notice that the counsel for the respondent DDA has in
this regard drawn attention to DDA Vs. Bhagat Construction Co.
Pvt. Ltd. 2004 (3) Arbitration Law Reporter 548 Delhi (DB) holding
that where the arbitrator is well-versed in the matters before him he
is not required to give a detailed judgment and it is sufficient if he
indicates his trend and gives outline to indicate basis of which he
arrived at the conclusion. Reliance was also placed on Jagdish
Chander Vs. Hindustan Vegetable Oils Corpn. AIR 1990 Delhi
204 holding that where an arbitrator is an expert his award should
not be lightly interfered with.
29. Claims No.10&11 of the petitioner were for interest. The
petition having failed, it is not deemed necessary to deal with the
objections thereto.
30. Resultantly, IA No.633/1996 is dismissed. The award dated
19th May, 1994 is made rule of the court and judgment pronounced
in terms thereof.
Decree sheet be drawn up. Parties are left to bear their own
costs.
RAJIV SAHAI ENDLAW (JUDGE) July 24, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!