Citation : 2009 Latest Caselaw 2809 Del
Judgement Date : 24 July, 2009
* HIGH COURT OF DELHI AT NEW DELHI
+ CS (OS) No. 3276/1989
Date of decision : July 24, 2009
# SH. ARUN JAITLY ..... PLAINTIFF
! Through : Mr. Ravi Sikri, Advocate with
Mr. Saket Sikri, Advocate
Versus
$ M/S. ISHWAR INDUSTRIES & ORS. ......DEFENDANTS
^ Through : Mr. N.K. Kantawala, Advocate
with Mr. Sanjay K. Shandilya,
Adv. for D-1.
Mr. J.M. Bari, Advocate for D-2.
%
CORAM:
HON'BLE MS. JUSTICE ARUNA SURESH
(1) Whether reporters of local paper may be
allowed to see the judgment?
(2) To be referred to the reporter or not? Yes
(3) Whether the judgment should be reported Yes
in the Digest ?
JUDGMENT
ARUNA SURESH, J.
1. Plaintiff filed this suit under Order 37 of the Civil
Procedure Code (hereinafter referred to as CPC) for
recovery of Rs.28,30,000/- against the defendants
along with interest @18% per annum from the date
of institution of the suit till realisation. Defendant
No.3 being a bank was a proforma party and its
name was deleted from the array of parties vide
order dated 6.9.1990 and this Court ordered the
registration of the suit under Order 37 CPC.
Summons in the prescribed proforma were duly
served upon the defendants. Both the defendants
filed their application for leave to defend. The
defendants were granted unconditional leave to
defend the present suit.
2. Briefly narrated, the case of the plaintiff is that he is
an architect and developer by profession.
Defendant No.1 engaged professional services of
the plaintiff. An agreement dated 8.1.1985 was
executed between defendant No.1 and Sh. R.C.
Goenka for the development of Tribhuvan Industrial
Cum Commercial Complex with approval from the
Bank of India vide their letter dated 23.4.1985 so as
to complete flatted factories/commercial buildings
etc. Vide letter dated 29.5.1985, R.C. Goenka
permitted defendant No.1 to engage the services of
any other party or builder for development of the
said land. The same was confirmed by defendant
No.1 on 29.5.1985 itself.
3. Thereafter an agreement dated 20.8.1985 was
executed between the plaintiff and defendant No.1
for the said work of additions, alterations and
renovation as per specifications and plans mutually
agreed at a cost of Rs.4 lacs to be borne by the
plaintiff. As against the deposit of Rs.10 lacs
security, plaintiff deposited Rs. 5 lacs and remaining
Rs.5 lacs were to be deposited by him on receipt of
approval from Bank of India in his name for
redevelopment of the property and the possession
of the site was to be given to the plaintiff on
20.8.1985.
4. Defendant No.1 entered into an agreement with
defendant No.2 on 4.2.1986 without the knowledge
of the plaintiff for the development of the same
block and the name of the plaintiff featured in sub-
clause 8 of the said agreement to the effect that
plaintiff would be consulted as an architect from
time to time.
5. On 12.7.1986 defendant No.1 made a proposal to
the plaintiff and on 14.7.1986 he gave in writing
that out of the total sum of Rs.15 lacs agreed to be
paid, Rs.5 lacs to 8 lacs would be paid by 17.8.1986
and balance amount would be paid by December
1986 and further area of 1275 square feet would be
retained by the plaintiff in the proposed complex
against security deposit of Rs. 5 lacs.
6. Plaintiff sent a letter on 17.12.1986 to defendant
No.1 asking him not to disturb the possession of the
structure since defendant No.1 had failed to make
any payment till that date. A memorandum of
understanding was executed inter se the parties on
18.12.1986 and it was agreed that Rs.15 lacs would
be paid by defendant No.1 or by defendant No.2 in
the following manner:
(a) Rs. 3 lakhs by cheque/cash on or before 22.12.1986;
(b) Rs. 2 lakhs by cheque/cash on or before 31.12.1986;
(c) Rs.2.5 lakhs by cheque/cash by 31st January 1987.
(d) Thereafter further monthly installment of Rs.1.5 lakhs is to be paid on or before the end of each month commencing from February 1987 to June 1987.
7. Plaintiff received only a sum of Rs.3 lacs from
defendant No.2 in part compliance of the
memorandum of understanding and thereafter he
did not receive any amount from the defendants.
Plaintiff wrote a letter dated 9.7.1987 and another
letter dated 10.7.1989 calling upon the defendants
to make the payment as per MoU. He also wrote a
letter dated 28.10.1988 to defendant No.1 asking
him to mark the area of the flat which would be
allotted to him in the new complex under
construction. Thereafter plaintiff sent a legal
notice dated 12.11.1989 to the defendants asking
them to make payments along with possession of
1275 square feet in Tribhuvan Complex within
seven days of receipt of notice which was duly
received by the defendants on 15.11.1989. Since
defendants failed to honour the MoU, plaintiff filed
the present suit for recovery of money.
8. Defendant No.2 sent a letter to the plaintiff on
20.7.1989 admitting that possession of the office
block Phase-I was taken over from the plaintiff with
his consent along with defendant No.1 in terms of
the MoU and he also admitted his liability to pay
Rs.25 lacs to the plaintiff out of the money
recovered from the sale of owners allocation and
also confirmed the payment of Rs.3 lacs to the
plaintiff.
9. Defendant No.1 has contested the suit of the
plaintiff contending inter alia that the suit is not
maintainable as there is no privity of contract
between the plaintiff and defendant No.1 in respect
of the subject matter of the suit as it is based on the
memorandum of understanding, fulfillment of which
is based on the conditions that it would be reduced
to a written regular agreement and that no such
written agreement was executed, that without
execution of the regular agreement as stipulated in
the MoU and in the absence of a resolution of the
company authorizing such execution it is not bound
to transfer the property, that the said memorandum
of understanding in the absence of an agreement
and resolution is not enforceable against it, that the
alleged memorandum of understanding is without
any consideration, vague, uncertain, unfair and
unconscionable being against public policy, being
illegal and void is not enforceable in law, that it is
defendant No.2 who is solely liable to the plaintiff
under the memorandum of understanding dated
18.12.1986, that defendant no.2 admitted his
liability in reply to the notice received from plaintiff
and part payment was also received by the plaintiff
from defendant No.2, that therefore it stood
released of its liability in regard to the alleged debt,
that the suit is barred by period of limitation.
10. The defendant No.1 had obtained necessary
sanction from the Bank of India on 14.9.1985 but
plaintiff failed to pay the security amount of Rs.5
lacs as per the agreement, though the demand for
deposit of security was made vide letter dated
13.9.1985. Plaintiff never carried out any work at
Sahibabad property from his own money totalling
Rs.4 lacs. The work at Sahibabad was carried out in
the premises of another company namely M/s Allied
Fiber Glass Products Pvt. Ltd. by Sh. Navin Jaitly
under the name and style Jaitly Construction,
Engineers and Contractors. The plaintiff therefore,
had no connection with the said transaction at
Sahibabad.
11. On approval granted by the Bank of India for
development of the property an agreement dated
4.2.1986 was entered into between defendant No.1
company and R.C. Goenka in supersession of the
earlier agreement dated 5.1.1985. Plaintiff never
performed his part of the contract dated 20.8.1985.
A fresh contract was entered into between plaintiff
and defendant No.1 on 12.7.1986 whereby the
parties gave up their rights under the previous
agreement dated 20.8.1985 and Rs.5 lacs deposited
earlier were to be treated as consideration for sale
by way of allotment of area of 1250 sq. ft. in the
Delhi property developed in terms of the
agreement. The plaintiff also agreed to forego the
interest as defendant company had confirmed
allotment of the said land to the plaintiff. In the
meantime, construction as per agreement dated
4.2.1986 had started but due to circumstances
beyond control, the same got delayed. Agreement
dated 12.7.1986 still continued as it was neither
revoked nor cancelled. Therefore, both the parties
were bound by the said agreement. The written
note dated 14.7.1986 was not written by defendant
No.1 and was not binding upon it. There was no
occasion at all for the payment of Rs.15 lacs to be
made to the plaintiff as claimed. Defendant No.1
has also challenged the validity of the written note
being in violation of Section 23 of the Contract Act.
It is also denied that letter dated 10.7.1986 had any
reference to the alleged MoU. It is the defendant
No.2 who has admitted his liability of Rs.25 lacs
towards the plaintiff and therefore, the matter was
between defendant No.2 and plaintiff and defendant
No.1 had no concern with the same. The suit as
against the defendant No.1 is liable to be dismissed.
12. Defendant No.2 in his written statement has
contended inter alia that in the MoU dated
18.12.1986, he is only a confirming party and no
decree can be passed against him as he is not liable
to satisfy the claim of the plaintiff. He is neither
liable on the original cause of action nor he is surety
or guarantor for and on behalf of defendant No.1.
Agreement dated 4.2.1986 was entered into
between defendant No.1 and M/s. B.D. Developers,
an Association of persons including the defendant
No.1 with the knowledge, consent and intimation of
the plaintiff. The alleged agreement dated
18.12.1986 is without consideration, is
unenforceable against defendant No.2 and is only a
memorandum and parties never intended to
enforce the same and is therefore not binding on
the parties. Regular agreement regarding the
terms contained in the MoU was to be entered into
between the parties. It was incumbent upon the
parties to file said MoU with appropriate authorities
in Form 37 to seek permission under Section 269
UC of the Income Tax Act within a period of 15 days
and since Form 37-I was not filed, the document lost
its force and therefore, the suit is not maintainable.
The property at Ishwar Nagar was mortgaged with
Bank of India. Therefore, defendant No.1 and
defendant No.2 had entered into an agreement
dated 4.2.1986 for development of the property
with a view to repay the loan amount. For that
purpose defendant No.2 had deposited Rs.42 lacs
with defendant No.1 as security for development of
the property. The agreement was entered into with
a tacit understanding with the Bank of India that out
of the sale proceeds by selling the developed
property the debt of the bank would be paid by
defendant No.1. Defendant No.1 was to receive
80% of the sale proceeds and defendant No.2 was
to receive 20% for adjusting the security amount
deposited and the interest accrued thereon. Vide
letter dated 2.12.1988, the Bank of India had
objected the claims or lien of the plaintiff. It was
the absolute liability of defendant No.1 to satisfy
the claim if any of the plaintiff. Defendant No.2 has
no objection if the claims, if any, of the plaintiff are
directed to be satisfied for allocation of defendant
No.1. Bank of India has not recognized earlier, the
agreement dated 20.8.1985 as it was entered into
without the approval and consent of the bank who
is the mortgagee of property of defendant No.1 at
Ishwar Nagar. Memorandum of understanding had
no genesis in the agreement dated 8.1.1985 and
20.8.1985. It was alleged that MoU was not
executed with a view to save the agreement dated
4.2.1986 as alleged though the name of the plaintiff
appears in clause 8 in the said agreement as
architect consultant. There is no cause of action for
filing the suit against defendant No.2. Defendant
No.2 was not in a position to make any payment for
and on behalf defendant No.1 without the
permission of Bank of India or of defendant No.1
with prior approval of Bank of India. The suit of the
plaintiff as against defendant No.2 is without any
cause of action and is not maintainable and is liable
to be dismissed.
13. Plaintiff filed his replication in answer to the written
statements of both defendants wherein he has
reasserted his stand taken in the plaint and has
denied the averments of the defendants as
contained in their respective written statements.
14. Upon the pleadings of the parties, the following
issues were settled for adjudication of the disputes
inter se them:
1. Whether the plaintiff is entitled to a sum of Rs.28,30,000/- as claimed in the suit? OPP
2. Whether the plaintiff is entitled to receive interest on the said amount, if so, at what rate and for which period? OPP
3. Whether in the alternative, the plaintiff is entitled to a sum of Rs.18,30,000/- together with interest @18% p.a. from the date of suit together with vacant possession of space in the Tribhuvan Complex measuring 1275 sq.ft. as per the memorandum of understanding dated 18.12.1986 along with interest [email protected]% on Rs.10 lacs being the cost of the space, as the same was to be handed over on or before 30.9.1987? OPP
4. Whether the defendants 1 and 2 are jointly and severally liable for the dues to the plaintiff? OPP
5. Whether the memorandum of understanding dated 18.12.1986 is without consideration as against defendant No.2 and is not enforceable as set out in paras 3 and 4 of the preliminary objections of the written statement of defendant No.2? OPP
6. Whether the plaint does not disclose any cause of action against defendant No.2? OPD
7. Whether the memorandum of understanding dated 18.12.1986 was not executed on behalf of defendant No.1 and as such is not binding on
defendant No.1?
8. Whether the suit is barred by limitation ? OPD
9. Relief.
15. I have heard Mr. Ravi Sikri, learned counsel for the
plaintiff, Mr. N.K. Kantawala, learned counsel for the
defendant No.1 and Mr. J.M. Bari, learned counsel
for Defendant No.2 and have carefully perused the
record. My observations on the issues as above are
as follows:
16. Defendant No.1 has challenged the maintainability
of the suit on the grounds that it is barred by period
of limitation. Learned counsel for the defendant
No.2 conceded that defendant No.2 has not joined
any issue on the aspect of limitation.
17. Period of limitation for filing a suit for recovery of
money is three years from the date when the work
is done by the plaintiff for the defendant at his
request where no time has been fixed for payment.
18. By virtue of Section 18 of the Limitation Act
(hereinafter referred to as Act) where before the
expiration of the prescribed period for a suit in
respect of any property or right, an
acknowledgment of liability in respect of such
property or right has been made in writing signed
by the party against whom such property or right is
claimed or by any person through whom he derives
his title or liability, a fresh period of limitation starts
running against the party who is to discharge the
liability from the time when the acknowledgment is
so signed. Under section 19 of the Act where a
part payment on account of debt has been made,
fresh period of limitation is to be computed from the
time when the payment is made. Section 20 of the
Act speaks of effect of acknowledgment of payment
made by another person for and on behalf of the
person who under the law is liable to make payment
in discharge of his liability.
19. Defendant No.1 had entered into an agreement with
the plaintiff on 20.8.1985 (Ex.-P5). Thereafter
another agreement dated 12.7.1986 (Ex.-P8) was
executed between the plaintiff and defendant No.1
whereby the parties revoked all their rights and
liabilities arising out of the agreement dated
20.8.1985 and defendant No.1 agreed to provide
1250 sq. ft. covered area to the plaintiff in
consideration of the security deposit of Rs.5 lacs
already made by him. An acknowledgment letter
was issued on 14.7.1986 (Ex.-P9) by defendant No.1
through its director Bharat Bhaskar wherein it
admitted its liability towards the plaintiff and
agreed to the terms along with the time schedule
for making the payments whereby complete
payment of Rs.15 lacs was to be made by
December, 1986 and the flat was to be allotted to
the plaintiff. However, no deadline was set for the
allotment of the house. As per the said letter,
proper agreement for allotment was to be signed by
the plaintiff when defendant No.1 required the
same to be signed.
20. In the meantime, defendant No. 1 and defendant
No.2 entered into a development agreement dated
4.2.1986 and they agreed among themselves to
retain the plaintiff as their consultant architect on
behalf of defendant No.1. This resulted into
execution of a Memorandum of Understanding
dated 18.12.1986 (Ex.-P1) between the plaintiff and
defendants No. 1 and 2. In this memorandum of
understanding defendant No.1 admitted its liability
to pay sum of Rs.15 lacs to the plaintiff in
installments. Parties admit having executed the
MoU dated 18.12.1986. Defendant No.2 made
payment of Rs.3 lacs being the first installment in
terms of the MoU in the last week of December
1986. However, no payment was made later on.
The present suit was filed by the plaintiff on
4.12.1989. Therefore, under the circumstances,
fresh period of limitation started running against the
defendants on execution of memorandum of
understanding as well as when part payment of
Rs.3 lacs was made by defendant No.2.
21. Since the present suit has been filed on 4.12.1989,
the acknowledgment was lastly made on
18.12.1986 and the part payment was made in the
last week of December, 1986, the suit having been
filed within three years of the acknowledgment and
part payment is well within the period of limitation.
22. Learned counsel for the defendant No.2 has argued
that plaintiff has no right to sue defendant No.2 as
he had acted as an agent for and on behalf of
defendant No.1 and was not a party to the property
development agreement dated 4.2.1986 executed
between the plaintiff and defendant No.1. It is
further argued that primary liability to pay the dues
is that of defendant No.1. Defendant No.2 only
became a collection agent for defendant No.1 from
the owners of the site and payment to the plaintiff
was to be made by him from the amount so
collected. It is impressed upon that under the
circumstances there is no cause of action for the
plaintiff to file the present suit against him.
23. Learned counsel for the plaintiff has submitted that
plaintiff has filed the present suit for recovery of
amounts due and payable to the plaintiff by
defendants No. 1 and 2 which were admitted by
defendants and reduced to writing in the form of
MoU dated 18.12.1986 wherein defendant No.2
agreed to make payment to the plaintiff due from
defendant No.1 and therefore, a cause of action has
accrued in favour of the plaintiff and against the
defendant No.2 to file the present suit for recovery
of money against him.
24. Before MoU was executed on 18.12.1986 defendant
No.1 had written in hand that 1275 sq. ft. to be
retained and Rs.15 lacs to be paid in cash in
installments. Rs.8 lacs to be paid by 17th August,
1986 and balance amount was to be paid by
December, 1986. This document is dated
14.7.1986 (Ex.-P9) and is signed by Mr. Bharat
Bhaskar, the director of defendant No.1 company.
Though initially defendant No.1 denied having
executed any such writing but at the stage of
admission and denial of the documents, Bharat
Bhaskar admitted this document. MoU dated
18.12.1986 (Ex.-P1) is an admitted document. In
the MoU defendant No.2 has been described as
confirming party. The relevant part of the MoU qua
defendant No.2 reads as follows:
"This understanding supersedes all other previous agreements, understandings, writings or any other document executed between the first party and the second party or confirmed by the third party in respect of the property at Ishwar Nagar belonging to Ishwar Industries Ltd. Broadly the terms as agreed are:
A sum of Rs.15,00,000/- (Fifteen lakhs) payable to the second party, will be paid either by the first party or the confirming party in the following manner....."
25. Since defendant No.2 has admitted the execution of
this MoU and also admits that this amount was
payable by defendant No.1 to plaintiff and had
undertaken to make the payment for and on behalf
of defendant No.1, the defendant No.2 admitted his
liability.
26. Cause of action consists of bundle of facts which
give cause to the plaintiff to enforce his legal rights
for settlement in a court of law. The cause of action
therefore means a right to sue. In Meenu Bhar v.
Renu Khosla & Anr. bearing CS (OS)
No.1033/2004 decided on 7.11.2008, I have
discussed the meaning of cause of action. The
relevant paragraphs of the said case read as
follows:
25. Cause of action consists of bundle of facts which give cause to enforce the legal injuries for redress in a court of law. The 'cause of action' means, therefore, every fact, which if traversed, would be necessary for the plaintiff to prove in order to support his right to a judgment of the court. In other words, it is a bundle of facts which taken with the law applicable to them, gives the plaintiff a right to claim relief against the defendants. It must include some act done by the defendant since in the absence of such an act no cause of action would possibly accrue or would arise.
27. What is a cause of action has been summed up in
reference to its various judgments by the Supreme
Court in Om Prakash Srivastava v. Union of
India and Anr. - 2006(7) SCALE 318 in the
following manner:
"9. By "cause of action" it is meant every fact, which, if traversed, it would be necessary for the plaintiff to prove in order to support his right to a judgment of the Court. In other words, a bundle of facts, which it is necessary for the plaintiff to prove in order to succeed in the suit (See Bloom Dekor Ltd. v. Subhash Himatlal Desai and Ors. (1994 (6) SCC 322).
10. In a generic and wide sense
(as in Section 20 of the Civil Procedure Code, 1908) "cause of action" means every fact, which it is necessary to establish to support a right to obtain a judgment (See Sadanandan Bhadran v. Madhavan Sunil Kumar (1998 (6) SCC 514).
11. It is settled law that "cause of action" consists of bundle of facts, which give cause to enforce the legal inquiry for redress in a court of law. In other words, it is a bundle of facts, which taken with the law applicable to them, gives the plaintiff a right to claim relief against the defendant. It must include some act done by the defendant since in the absence of such an act no cause of action would possibly accrue or would arise. (See South East Asia Shipping Co. Ltd. v. Nav Bharat Enterprises Pvt. Ltd. and others (1996 (3) SCC 443).
12. The expression "cause of action" has acquired a judicially settled meaning. In the restricted sense "cause of action" means the circumstances forming the infraction of the right or the immediate occasion for the reaction. In the wider sense, it means the necessary conditions for the maintenance of the suit, including not only the infraction of the right, but also the infraction coupled with the right itself. Compendiously, as noted above the expression means every fact, which it would be necessary for the plaintiff to prove, if traversed, in order to support his right to the judgment of the Court. Every fact, which is necessary to be proved, as distinguished from every piece of evidence, which is necessary to prove each fact, comprises in "cause of action". (See Rajasthan High Court
Advocates‟ Association v. Union of India and Ors. (2001 (2) SCC 294).
13. The expression "cause of action" has sometimes been employed to covey the restricted idea of facts or circumstances which constitute either the infringement or the basis of a right and no more. In a wider and more comprehensive sense, it has been used to denote the whole bundle of material facts, which a plaintiff must prove in order to succeed. These are all those essential facts without the proof of which the plaintiff must fail in his suit. (See Gurdit Singh v. Munsha Singh (1977 (1) SCC 791).
14. The expression "cause of action" is generally understood to mean a situation or state of facts that entitles a party to maintain an action in a court or a tribunal; a group of operative facts giving rise to one or more bases of suing; a factual situation that entitles one person to obtain a remedy in court from another person. (See Black‟s Law Dictionary). In Stroud‟s Judicial Dictionary a "cause of action" is stated to be the entire set of facts that gives rise to an enforceable claim; the phrase comprises every fact, which if traversed, the plaintiff must prove in order to obtain judgment. In "Words and Phrases" (4th Edn.) the meaning attributed to the phrase "cause of action" in common legal parlance is existence of those facts, which give a party a right to judicial interference on his behalf. (See Navinchandra N. Majithia v. State of Maharashtra and Ors. (2000 (7) SCC 640).
15. In Halsbury Laws of England (Fourth Edition) it has been stated as
follows:
"Cause of action has been defined as meaning simply a factual situation the existence of which entitles one person to obtain from the Court a remedy against another person. The phrase has been held from earliest time to include every fact which is material to be proved to entitle the plaintiff to succeed, and every fact which a defendant would have a right to traverse. „Cause of action‟ has also been taken to mean that particular act on the part of the defendant which gives the plaintiff his cause of complaint, or the subject matter of grievance founding the action, not merely the technical cause of action‟.
16. As observed by the Privy Council in Payana v. Pana Lana (1914) 41 1A 142, the rule is directed to securing the exhaustion of the relief in respect of a cause of action and not to the inclusion in one and the same action or different causes of action, even though they arises from the same transaction. One great criterion is, when the question arises as to whether the cause of action in the subsequent suit is identical with that in the first suit whether the same evidence will maintain both actions. (See Mohammad Khalil v. Mahbub Ali Mian (AIR 1949 PC 78).
28. The cause of action has no relation either to the
defence that may be raised by the defendant nor
does it depend on the character of relief prayed for
by the plaintiff. It only refers to facts upon which
the plaintiff basis his claim before the Court to
arrive at a conclusion in his favour.
29. In this case it is the defence raised by defendant
No.2 that he was acting as an agent for and on
behalf of defendant No.1 and had agreed to make
payment due to the plaintiff in terms of MoU (Ex.-
P1) after realization of the amount from the owners
of the site and he in no manner is individually liable
to pay the amount claimed by the plaintiff.
30. Defendant No.2 in his written statement also
admitted that he was to pay a sum of Rs.25 lacs to
the plaintiff as per MoU. This admission itself is a
relevant fact to reach to a conclusion that plaint
discloses cause of action against defendant No.2.
31. Under these circumstances, I conclude that in view
of the admitted facts and documents a cause of
action has accrued in favour of the plaintiff and
against defendant No.2 as is apparent from the
pleadings contained in the plaint. Hence, this issue
is accordingly decided against defendant No.2 and
in favour of the plaintiff.
32. An agreement was executed between the plaintiff
and defendant No.1 through Mr. Bharat Bhaskar, its
director, on 20.8.1985 (Ex.-P5/D1/6). This
agreement was executed for renovation of property
erected on plot bearing Khasra No.264, Village
Bahapur, New Delhi (now known as Ishwar Nagar)
on terms and conditions laid down in the
agreement. Plaintiff in his cross examination has
stated that on 24.8.1985, there was a newspaper
publication in Hindustan Times wherein it was
stated that Mr. Bharat Bhaskar was not authorised
to enter into an agreement for redevelopment of
the property in question. With the result plaintiff
wrote a letter on 12.9.1985 to Bharat Bhaskar to
clarify his stand in regard to the publication which
appeared in the paper. Admittedly this letter was
replied by defendant No.1 company on 13.9.1985
(Ex.-D1/21) duly signed by Bharat Bhaskar as
director of the company. Letter dated 13.9.1985 is
an admitted document (Ex.-D1/21). The relevant
part of this letter reads:
"We are pleased to inform you that the publication of the notice in the Hindustan Times dated 24th August 1985 was wrongly made and without any authority and as such, the said S/Shri Rajeev Bhaskar, Sanjeev Bhaskar and Sunil Johar have subsequently on 6-9-1985 withdrawn and cancelled the earlier notice published by them in the Hindustan Times of 24th August, 1985. A photocopy of the notice dated 6-9- 1985 is enclosed for your information and perusal.
Further, in clarification, a resolution was passed in the meeting of the Board of Directors of the Company on 6-9-1985 clarifying the necessary authority pursuant to the publication in the Hindustan Times, a copy of which is also enclosed for your information."
33. This letter clarified the confusion created by the
publication appearing in the newspaper „Hindustan
Times‟ and Mr. Bharat Bhaskar continued to deal
with the plaintiff as director of defendant No.1.
34. In its written statement defendant No.1 has
nowhere objected to the authority of Bharat
Bhaskar to act as director of defendant No.1
company and have business dealings with the
plaintiff or enter into the impugned agreements for
and on behalf of the company. The only plea which
has been raised in the written statement is that
plaintiff by virtue of his dominant position executed
his influence on Bharat Bhaskar who, without actual
verification of the accounts and the work signed the
writing dated 14.7.1986. According to the
defendant No.1, it is also not a party to the MoU
dated 18.12.1986 (Ex.-P1).
35. Vinay Bhaskar DW-1 has denied execution of writing
dated 14.7.1986 (Ex.-P9). He has deposed that the
said writing was executed by Bharat Bhaskar under
the influence of the plaintiff without actual
verification of the account and without the authority
of defendant No.1 and therefore it has no binding
effect on defendant No.1. In his cross examination
he did admit that Mr. Bharat Bhaskar is one of the
directors of defendant No.1. He also admitted that
Bharat Bhaskar had dealt with all the transactions
including execution of all the agreements and
subsequent correspondences with the plaintiff on
behalf of defendant No.1 company. Thus, it is clear
that Bharat Bhaskar as director of defendant No.1
continued to represent the company while dealing
with the plaintiff. He was duly authorised by the
company to act on its behalf. MoU (Ex.-P1) dated
18.12.1986 is signed by Bharat Bhaskar as director
of defendant No.1. Defendant No.1 has not been
able to prove its case that Bharat Bhaskar was not
authorized by defendant No.1 company to enter
into an agreement for renovation on 20.8.1985 and
subsequent agreements and to indulge into
correspondences for and on behalf of defendant
No.1 company with the plaintiff. Learned counsel
for the defendant No.1 has argued that no
resolution was passed in favour of Bharat Bhaskar
authorizing him to act on behalf of the company. As
pointed out above these submissions are without
any force specially when defendant No.1 has
admitted that Bharat Bhaskar has been dealing for
and on behalf of defendant No.1 with the plaintiff.
Neither he nor any other director of the company
dealt with the plaintiff for renovation of the
properties at Ishwar Nagar owned by defendant
No.1 company.
36. Learned counsel for the defendant No.1 has argued
that MoU does not bear any stamp of Ishwar
Industries and it was executed by Bharat Bhaskar in
his individual capacity. Therefore, this MoU is not
binding on defendant No.1. He has referred to G.
Subba Rao v. M/s. Rasmi Die-Castings Ltd. -
AIR 1998 AP 95 to support his submissions.
37. I do not agree with the contentions of the learned
counsel for the defendant No.1. From the
contentions of the parties it is clear that MoU was
executed. The opening lines of the MoU (Ex.-P1)
suggest that it was between the plaintiff and Ishwar
Industries Ltd. The relevant lines are:
"This understanding supersedes all other previous agreements, understandings, writings or any other document executed between the first party and the second party or confirmed by the third party in respect of the property at Ishwar Nagar belonging to Ishwar Industries Ltd...."
38. The recital of the MoU therefore clarifies that Bharat
Bhaskar was acting on behalf of defendant No.1
company and not in his personal capacity. It is true
that Resolution of the Board dated 6.9.1985 has not
been placed on record. It was for the defendant
No.1 to produce it as it finds reference in the letter
dated 13.9.1985 (Ex.-P7) written by Bharat Bhaskar
on behalf of defendant No.1 company to the plaintiff
informing him that he had been authorized to enter
into agreements on behalf of defendant No.1. It
was for the defendant No.1 to discharge the onus of
proving that Bharat Bhaskar was not authorized by
it to enter into agreement or transaction or writing
etc. with the plaintiff which it has miserably failed.
39. In G. Subba Rao v. M/s Rashmi Die-Castings
Ltd. - AIR 1998 Andhra Pradesh 95 who can be
a managing director of a company is defined.
Besides, in the said case it was questioned if the
MoU could be treated as a settlement between two
individuals or Chartered Accountant and the
respondent company. The Court held MoU as not
binding on the company with the observations that
preamble did not describe the signatory of the MoU
as the managing director of the company. Besides
the petitioner was director of the company till the
year 1993. The court presumed that under the
circumstances the two individuals wanted to settle
certain disputes of the respondent company on the
basis of this MoU. Besides the observations were
made in a writ petition filed by the petitioner
seeking winding up of the company. Therefore, the
observations made in the said case were in the
context whether the company under such
circumstances on the basis of MoU should be wound
up or not. This judgment therefore is of no help to
defendant No.1.
40. The signatory of the MoU happened to be the
director of Ishwar Industries. The contents of the
MoU also indicate that the terms and conditions
were settled for and on behalf of defendant No.1.
Therefore, it is not acceptable that Bharat Bhaskar
had no authority to act on behalf of the company for
want of resolution of the company.
41. Under these circumstances, I conclude that MoU
(Ex.-P1) was executed by Bharat Bhaskar on behalf
of defendant No.1 and it is binding on it. This issue
is accordingly decided against defendant No.1 and
in favour of the plaintiff.
42. Mr. Ravi Sikri, counsel appearing for the plaintiff has
submitted that the present suit has been filed by
the plaintiff for recovery of professional fee. All the
documents executed between the plaintiff and
defendant No.1 are admitted and proved in
evidence. Defendant No.1 admitted its liability to
pay a sum of Rs.15 lacs in its writing dated
14.7.1986 (Ex.-P9) in two installments by the end of
December 1986 and also an area of 1275 sq. ft. was
to be retained by the plaintiff in the proposed
Tribhuvan Complex, Ishwar Nagar, Delhi against the
security amount of Rs.5 lacs deposited by the
plaintiff in pursuance of the agreement dated
20.8.1985 (Ex.-P5). He further argued that
defendant No.1 also admitted its liability to pay the
due amount when memorandum of understanding
was executed between the plaintiff and defendant
No.1 and defendant No.2 and that defendant No.1 is
legally bound to pay the admitted amount along
with interest of Rs.6,21,000/- @18% per annum as
on 15.11.1989 as agreed inter se the parties.
Learned counsel for the plaintiff has referred to
following judgments:
1. United India Insurance Co. Ltd. & Anr. v. Andrew Vivera - AIR 1990 Kerala 139.
2. Gopal Krishnaji Ketkar v. Mahomed Haji Latif & Ors. - (1968) 3 SCR 862.
3. Sports Authority of India v. Sports Authority of India Kamgar Union & Ors. - 2005 III AD (Delhi)
55.
43. Mr. N.K. Kantawala, counsel appearing for the
defendant No.1, has argued that plaintiff is an
architect and builder. His services were engaged
for purpose of addition/alteration/renovation of the
existing office block, phase-I at a cost of Rs.4 lacs
which were to be borne by the plaintiff and later on
to be paid by defendant No.1. This agreement is
absolutely silent about any work to be carried out at
M/s Allied Fiber Glass Products Pvt. Ltd. at
Sahibabad.
44. It is argued that plaintiff did not complete the
construction work and has raised bills for the work
done at Sahibabad by one Navin Jaitly. Therefore,
he is not entitled to the amount claimed for the
work done at Sahibabad. On the failure of the
plaintiff to complete his work, defendant No.1 had
to enter into a second agreement with defendant
No.2 on 4.2.1986. Plaintiff never objected to this
agreement though he has tried to argue that the
said agreement was executed without his
consultation and previous knowledge. Plaintiff has
not placed on record any document nor has
adduced any evidence to prove that the total cost
of the work executed by him at Mathura Road and
at Sahibabad was Rs.4 lacs. He has also pointed
out that there was no written agreement between
the plaintiff and defendant No.1 for executing any
work at Sahibabad and the work at Sahibabad was
with Navin Jaitly, a cousin of the plaintiff.
45. It is further argued that plaintiff has committed
breach in the enforcement of the agreement as he
only deposited Rs.5 lacs as security amount against
Rs.10 lacs as per the terms contained in clause 3 of
the agreement dated 12.7.1986. Learned counsel
for the defendant No.1 has submitted that MoU
dated 18.12.1986 cannot be enforced in law
because there is a clause contained in the said MoU
that a regular agreement would be executed but no
such agreement was executed. He has referred to
letter dated 10.7.1989 wherein there is no mention
of any MoU having been entered into by the parties
whereby defendant No.1 admitted its liability to pay
the suit amount and for the first time vide this letter
that plaintiff has clubbed both the claims as against
Tribhuvan Complex and construction at Sahibabad
unit. He argued that vide letter dated 5.10.1989
claim of the plaintiff made in letter dated 10.7.1989
has been specifically refuted and liability if any to
pay the amount is that of defendant No.2. He has
submitted that MoU is to be read as it is and cannot
be given any other meaning in view of Sections 91
and 92 of the Evidence Act.
46. It is further argued that plaintiff has not led any
evidence to show that any forgery or fraud has
been played by the MD of the company and no
evidence has been led to show that defendant No.1
is liable to pay the amount. To support his
submissions he has referred to M.V. Shankar Bhat
and another v. Claude pinto (D.) by L.Rs. and
others - AIR 2004 SC 636 and National
Properties Ltd. v. Bata India Limited - AIR
2001 Calcutta 177.
47. As per the agreement dated 20.8.1985 plaintiff was
to carry out the renovation/alteration of the first
part of the existing office block, phase-I owned by
the company at Ishwar Nagar, New Delhi. It was
agreed between the parties that plaintiff would be
responsible to make additions/alterations/
renovations in the existing office block, phase-I as
per the specifications and plans mutually agreed
between the parties along with a covered area of
1275 sq. ft. approximately at his own cost which
was assessed at Rs.4 lacs. It was also agreed that
defendant No.1 would clear all the structures,
machines and other items lying in the said office
block on execution of the agreement and the work
was to be completed within four months from the
date of the handing over of the possession of the
impugned property to the plaintiff. Plaintiff agreed
to deposit security of Rs.10 lacs carrying interest
@15% per annum for three months i.e. during the
period of completion of the work. Out of this Rs.10
lacs, Rs. 2 lacs were deposited at the time of
signing of the agreement, Rs.3 lacs were to be
deposited on or before 10.9.1985 and balance
amount of Rs.5 lacs was to be deposited by the
plaintiff immediately on receipt of approval from the
Bank of India in its name as builders for
redevelopment of the total land of the owner.
48. Clause 5 of this agreement finds mention that
necessary sanction and approval of Bank of India,
Khan Market Branch, with which the property was
mortgaged for lease/transfer, had already been
granted in favour of the defendant No.1, the owner,
vide letter dated 2.8.1985. In case the approval of
the Bank was not obtained in favour of the builder,
the security deposit of Rs.5 lacs was to be returned
back to the builder i.e. plaintiff. Para 7 of the
agreement also contains a narration of fact that
necessary sanction and approval for redevelopment
of the property has already been accorded by the
Bank of India in favour of the owner vide letter
dated 23.4.1985.
49. Letter (Ex.-P6) is dated 20.8.1985 written by
defendant No.1 to the plaintiff on the same day
when the agreement (Ex.-P5) was executed inter se
the parties. As per this letter, physical possession
of the office block was handed over to the plaintiff
and in acknowledgment of having received the
physical possession, plaintiff had appended his
signatures. In this letter defendant No.1 undertook
to remove the material/furniture/equipments etc. in
due course. Perusal of letter dated 13.9.1985 (Ex.-
P7) makes it clear that the equipments etc. installed
in the premises were not completely removed by
the defendant No.1 and it undertook to remove
them on 21.9.1985.
50. Plaintiff in his cross-examination admitted that he
did not deposit the balance security amount of Rs.5
lacs but volunteered that since the necessary
approval from Bank of India as well as municipal
corporation in his name was not received, he did
not deposit the balance security amount of Rs.5
lacs. He was confronted with the letter dated
14.9.1985 (Ex.-D1/20) written by Bank of India to
defendant No.1. To this he replied that this letter
was not approval of the Bank of India in his name.
Perusal of this letter makes it clear that the bank
did not give any approval to the plaintiff to carry out
necessary work in the suit premises. It permitted
defendant No.1 to lease out the administrative
block of the property (present built up area with
certain conditions). In fact this letter does not
relate in any manner to the renovation work to be
carried out by the plaintiff in the office block. It has
come in evidence that Bank of India never gave any
approval in the name of the plaintiff for execution of
the work as agreed. Under these circumstances,
therefore, plaintiff was right when he did not
deposit the balance security amount of Rs.5 lacs as
agreed because the pre-requisite condition for
deposit was not fulfilled by defendant No.1.
51. Ex.-D1/7 to Ex.-D1/16 are the bills purportedly
raised by N.K. Jaitly on M/s. Allied Fibre Glass
Products (P) Ltd. for the construction work carried
out by him in the premises of the said firm at
Sahibabad for the period from 31.1.1996 onwards.
Defendant No.1 has produced these bills to prove in
evidence that Sahibabad work was carried out by
Naveen Kumar Jaitly and this work was never
allocated to the plaintiff. True, that there is no
mention of any work to be carried out by the
plaintiff at M/s. Allied Fibre Glass Products (P) Ltd.
Sahibabad which is a sister concern of defendant
No.1. The fact remains that this work was carried
out by Navin Jaitly on behest of the plaintiff.
52. As per clause 9 of the agreement (Ex.-D1/6/Ex.-P5)
plaintiff was at liberty to appoint in consultation
with the owner engineers, supervisors, workers and
other staff in connection with the said work to be
carried out under the joint supervision of the owner
and the builder. Plaintiff was to provide
workmanship required, labour and material etc.
Plaintiff has stated that he engaged the services of
Navin Jaitly as he was entitled to do under the said
agreement. Plaintiff accordingly took the services
of Mr. Navin Jaitly and he was making payment.
53. Navin Jaitly in his affidavit on oath as PW-2 has
affirmed that in September 1985 he was appointed
by Arun Jaitly to carry out addition/alteration work in
one of the factory complex belonging to Ishwar
Industries, Okhla. Since the scope of work was not
defined, no specific contract was signed and it was
agreed that he would be paid by Arun Jaitly on the
cost plus basis i.e. actual expenses incurred by him
on the work plus 15% as the contractor‟s profit. He
carried out the work under the instructions of
Mr.Arun Jaitly in the presence of Bharat Bhaskar
who was having his office in the same premises.
However, in December 1985 though his work was
not complete he was asked to stop his incomplete
work and shift all the material procured by him and
the old salvage structural material to the site of M/s.
Allied Fibre Glass Products (P) Ltd., sister concern of
M/s. Ishwar Industries in which Bharat Bhaskar
happened to be the director. He carried out the
construction work there on item rate basis.
However no agreement was executed despite his
persistent requests. He has further declared that
he never received any payment from M/s. Allied
Fibre Glass Products (P) Ltd. or Bharat Bhaskar
against the bills raised by him. He received all the
payments from Arun Jaitly for the work done by him
at Okhla unit and Sahibabad unit. Admittedly no
written agreement was executed between him and
the plaintiff.
54. It is significant to note that when agreement dated
20.8.1985 (Ex.-P5/D1/6) was enforced, defendant
No.1 without prior intimation or consultation with
the plaintiff entered into an agreement dated
4.2.1986 (Ex.-P-2/D1/22) with Mr.R.C. Goenka and
others forming a consortium, by virtue of which the
original agreement entered into between R.C.
Goenka and others dated 8.1.1985 (Ex.-D1/19) was
sought to be restored. This was so done after
finalising the terms and conditions of the
consortium between the two on 22.11.1985. This
fact is admitted by defendant No.2 in his cross-
examination. The said agreement dated 4.2.1986
(Ex.-D1/22) was executed by B.D. Steel Castings
Ltd., Acharya Arun Dev and others with Ishwar
Industries Ltd. This agreement, therefore, was
executed between defendant No.1 and defendant
No.2 in utter violation of the terms and conditions of
the agreement dated 20.8.1985, without giving the
statutory period of four months to the plaintiff to
complete the work.
55. When agreement dated 4.2.1986 (Ex.-P2) was
executed between the defendants, they had agreed
to retain the services of the plaintiff as
architect/builder. Plaintiff must have been
executing his work properly and that must have
been the reason for the defendants to continue with
the services of the plaintiff despite the fact that
agreement entered into between the plaintiff and
defendant No.1 on 20.8.1985 was still in force when
agreement dated 4.2.1986 (Ex.-P2) was executed.
Defendant No. 2 has not placed on record any
document to indicate that the payment of the bills
Ex.-D1/7 to Ex.-D1/16 was directly paid by it to
Naveen Jaitly and not to the plaintiff. Viney Bhaskar
DW-1 in his cross-examination has avoided giving
any specific reply to the questions put to him and
rather has shown his ignorance about various
documents executed and correspondence
exchanged between the parties. Viney Bhaskar in
his cross examination admitted that he and Bharat
Bhaskar are the directors of M/s Allied Fiber Glass
Products Pvt. Ltd. Viney Bhaskar was given
opportunity to go through the relevant record of the
company but he was evasive when he said that
record was an old one and old employees had left
the company. He could not do the same. When
asked as to whether any payment was made by
defendant No.1 for the work done at Sahibabad
unit, he could not give any specific reply. He also
could not answer if there was any agreement with
the plaintiff or Mr. Naveen Jaitly for execution of
work at Sahibabad unit.
56. In Gopal Krishnaji Ketkar v. Mahomed Haji
Latif & Ors. (supra), it was observed that even if
the burden of proof does not lie on a party, the
court is within its rights and powers to draw an
adverse inference, if he withholds important
documents in his possession which can throw light
on facts at issue. The Supreme Court detested the
practice for those desiring to rely upon a certain set
of facts to withhold from the court, the best
evidence which is in their possession which could
throw light upon the issues in controversy and to
rely upon the abstract doctrine of onus of proof.
57. In Sports Authority of India v. Sports Authority
of India Kamgar Union & Ors. (supra) this Court
drew an adverse inference against the management
for withholding the attendance register which was
in the power and possession of the management to
decide the objections filed to the award by the
petitioner.
58. Since defendant No.1 failed to produce the record
about the work executed by the plaintiff, an adverse
inference is drawn against the defendant No.1 that
had the record been produced, it would have gone
against the defence of defendant No.1 that plaintiff
did not complete the work in terms of agreement
dated 20.8.1985 and that Naveen Jaitly was
separately engaged by M/s Allied Fiber Glass
Products Pvt. Ltd. to carry out work at Sahibabad.
59. Therefore, I do not find any reason to disbelieve the
testimony of Naveen Jaitly that he had received all
the payments of the bills from plaintiff only.
60. The other significant factor in this case is the
execution of an agreement between plaintiff and
defendant No.1 on 12.7.1986 (Ex.-P8). By virtue of
this agreement, defendant No.1 did acknowledge
that plaintiff had deposited a sum of Rs.5 lacs
carrying interest @15% per annum in the manner
mentioned in the agreement dated 20.8.1985. Both
the parties to this agreement (Ex.-P8), released
themselves of their obligations and gave up their
rights under the said agreement against each other.
The agreement dated 20.8.1985 was superseded
vide agreement dated 12.7.1986. By virtue of this
agreement deposit of security amount of Rs.5 lacs
was to be treated as consideration for allotment/
sale of 1250 sq. ft. of covered area in favour of the
plaintiff. Its value was worked out at Rs.4000 per
sq. ft. and plaintiff agreed to forego his interest
which was receivable by him on security deposit
from defendant No.1 in terms of agreement dated
20.8.1985 because plaintiff had paid the full value
of the said area in advance. Letter (Ex.-P9) dated
14.7.1986 is an acknowledgment by Bharat
Bhaskar, director of defendant No.1 to the fact that
besides the agreement (Ex.-P8) dated 12.7.1986,
defendant No.1 had agreed to make payment of
Rs.15 lacs in cash to the plaintiff in two
installments; one to be paid by 17.8.1986 and the
balance amount to be paid by December, 1986
along with handing over 1275 sq. ft. area to the
plaintiff.
61. Defendant No.1 has raised a plea that
acknowledgment dated 14.7.1986 (Ex.-P9) was
obtained by plaintiff and executed by Bharat
Bhaskar without verification of accounts, on plaintiff
exercising undue influence by virtue of his
dominant position on Bharat Bhaskar.
62. Order VI Rule 4 CPC provides that in cases where a
party pleading relies on misrepresentation, fraud,
breach of trust, wilful default or undue influence
and in all other cases in which particulars may be
necessary, the particulars with dates and items if
necessary have to be stated in the pleading.
63. In M/s. United India Insurance Co. Ltd. v.
Andrew Vivera (supra), it was observed:
"6. Order 6, Rule 4, C.P.C. provides that in all cases in which the party pleading relies on any misrepresentation, fraud, breach of trust, wilful default, or undue influence, and in all other cases in which particulars may be necessary beyond such as are exemplified in the forms aforesaid, particulars (with dates and items if necessary) shall be stated in the pleading. The position admits no doubt that allegation of fraud, undue influence and coercion must be set forth in full particulars and not vaguely. The allegation must be fully stated so that the case be decided on the particulars pleaded. There cannot be any departure from what has been ordained under O. 6, R.
4. Any allegation in a sweeping manner will hardly suffice for the Court to act....."
64. In the present case written statement of defendant
No.1 does not contain any particulars regarding the
alleged undue influence or misrepresentation or
fraud or breach of trust or willful default. Therefore,
the argument raised by the defendant No.1 at this
stage regarding undue influence having been
exercised on Bharat Bhaskar in getting
acknowledgment (Ex.-P9) executed from him
cannot be looked into and is of no relevance. It is
not disputed by defendant No.1 that this document
was written and signed by Bharat Bhaskar on
14.7.1986 in his own writing and under his
signature. Plaintiff being the builder of the property
was working in terms of the agreement executed
inter se the parties on 20.8.1985 (Ex.-P5). In what
manner he could be in a dominant position to
exercise undue influence on Bharat Bhaskar is not
known or explained or proved in evidence by
defendant No.1.
65. Viney Bhaskar has admitted that the entire
transaction in this case i.e. execution of agreements
and correspondences were dealt with by Bharat
Bhaskar and no other director of the company. He
as a director did not even attend a single meeting
held between Bharat Bhaskar and the plaintiff.
Bharat Bhaskar is still working as a director in the
company. Why he did not step in the witness box is
not known. He was the only person who could
explain the circumstances in which letter dated
14.7.1986 (Ex.-P9) was written by him. Bharat
Bhaskar‟s conduct in not appearing as a witness in
the case raises an adverse inference against
defendant No.1 that had he appeared in the witness
box his testimony would have gone against the
defence raised by defendant No.1.
66. Under these circumstances, it is clear that pleadings
pertaining to undue influence are not specific and
lack material particulars. Such pleadings cannot be
looked into by the court. The document (Ex.-P9),
which is an acknowledgment of liability by Bharat
Bhaskar on behalf of defendant No.1, proves that
defendant No.1 had agreed to pay the amount due
to the plaintiff and also allot space measuring 1275
sq. ft. to the plaintiff.
67. Since defendant No.1 failed to honour its
acknowledgment made in the agreement dated
12.7.1986 (Ex.-P8) and acknowledgment dated
14.7.1986 (Ex.-P9), plaintiff wrote a letter dated
17.12.1986 (Ex.-D1/3) calling upon defendant No.1
not to disturb the possession of the structure with
the plaintiff. Consequently, parties to the suit
entered into a tripartite agreement i.e. MoU on
18.12.1986 (Ex.-P1). Broadly the terms as agreed
between the parties as per the MoU are:
"A sum of Rs.15,00,000/-
(fifteen lakhs) payable to the second party, will be paid either by the first party or the confirming party in the following manner.
a. Rs.3,00,000/- by cheque/cash
on or before 22 Dec. 1986
b. Rs.2,00,000/- ---- do ----
--- on or before 31st Dec. 1986.
c. Rs.2,50,000/- ---- do ----
(Two and half only) --- on or before
31st Jan. 1987.
Thereafter further monthly
instalments Rs.1.50 lakhs (one and half) on or before the end of each month i.e. 28 Feb, 1987, 31st March, 1987, 30 April, 1987, 31 may 1987, 30 June, 1987."
68. It was also agreed in the MoU that the plaintiff by
way of security for due payment would have lien over
the sale proceeds recovered by Ishwar Industries Ltd.
of which Bharat Bhaskar is the director, out of the sale
of the area/flats in Tribhuvan Complex, Ishwar Nagar,
New Delhi. It was also agreed that defendant No.1
would furnish sale statements to the plaintiff so that
the installments as decided in the MoU could be
regularly remitted to the plaintiff by defendant No.1.
69. The other term settled in the MoU was that
defendant No.1 would provide the plaintiff with area of
1275 sq. ft. in Tribhuvan Complex on or before 30th
September, 1987 and two percent brokerage was to
be paid to Bharat Bhaskar as the sale proceeds by the
plaintiff. In default of allotment of the space as
agreed, defendant No.1 was to pay to the plaintiff the
value of the said space @Rs.775/- per sq. ft.
70. Last lines of the MoU read as follows:
"This is only understanding and the parties will enter into regular agreement embodying the above terms on or before 15th Jan, 1987."
71. Admittedly, no regular agreement was executed
into between the parties after execution of the MoU on
18.12.1986. Thus, it is clear that defendant No.1
admitted its liability to pay a sum of Rs.15 lacs and
also to allot a space measuring 1275 sq. ft. to the
plaintiff within the specified period as above. The MoU
was acted upon partially when, defendant No.2, the
confirming party to the MoU paid a sum of Rs.3 lacs to
the plaintiff in part performance of the settled terms at
the end of December, 1986. Plaintiff handed over the
physical possession of the suit property to defendant
No.2. Vide letter dated 20.7.1989 (Ex.-P3), defendant
No.2 acknowledged having received the physical
possession of the office block, phase-I from the
plaintiff with the consent of the plaintiff and Bharat
Bhaskar of Ishwar Industries Ltd. in terms of the MoU.
Though, no agreement was executed between the
parties, but since MoU has been acted upon by parties,
it has a binding force on the parties. Thus, it is proved
on record that defendant No.1 acknowledged its
liability to pay a sum of Rs.25 lacs including cost value
of the space to the plaintiff.
72. Plaintiff had earlier filed a suit for mandatory
injunction against the defendants seeking direction
against defendant No.1 to provide the original
tripartite agreement to the plaintiff for its due
compliance and implementation with a further
direction to be issued to defendants No.2 and 3 to
issue no objection to the defendant No.1 regarding
passing over of the original tripartite agreement along
with copy thereof to the plaintiff for its due
implementation. Defendant No.1 in the said case was
Sh. B. Mohan, who was in custody of this document.
The said case was decided on 21.2.1990 by the civil
judge and he decreed the suit of the plaintiff for
mandatory injunction with the direction to the
defendants to provide a certified copy of the tripartite
agreement to the plaintiff. The copying agency was
also directed to prepare a certified copy of the MoU
and supply the same to the plaintiff on payment of
fees as per law. Hence, MoU (Ex.-P1) stood proved in
the civil court as an admitted document.
73. The acknowledgment of liability undisputedly was
made by Bharat Bhaskar for and on behalf of
defendant No.1 for the professional fees payable to
the plaintiff whose services as an architect were
engaged for carrying out additions/alterations/
renovations etc. at Tribhuvan Complex, Ishwar Nagar.
Pertinently, before filing of the suit defendant No.1
never raised any objection by way of correspondence
or otherwise that plaintiff had not completed his work
within the stipulated time. Therefore, I conclude that
plaintiff is entitled to the balance amount of Rs.12 lacs
(as three lacs have admittedly been received by him).
74. As regards the space of 1275 sq. ft. in Tribhuvan
Complex, I am of the view that since the flats/space
have been sold away by defendant No.1 to different
people it might be that no space is available with
defendant No.1 for allotment to the plaintiff. Under
these circumstances, it is more appropriate that
plaintiff is paid the value of the space as agreed
between the parties which comes to Rs.10 lacs.
Therefore, plaintiff in all is entitled to a sum of Rs. 22
lacs as claimed by him.
75. There is no agreement inter se the parties regarding
payment of interest @18% per annum or any other
rate on the value of the space at the agreed rate
which comes to Rs.10 lacs. Hence, plaintiff is not
entitled to any interest on the said amount of Rs.10
lacs before the filing of the suit.
76. Plaintiff has fastened the liability jointly and
severally on defendant No.2 and defendant No.1 for
the dues claimed by him in the suit on the basis of
MoU (Ex.-P1) as well as the agreement dated
4.2.1986 (Ex.-P2). Plaintiff was not a party to the
agreement dated 4.2.1986 (Ex.-P2) entered into
between defendants No.1 and 2, R.C. Goenka and
others. Even if in the said agreement defendants
had agreed to retain the plaintiff as consultant
architect for the project on behalf of the defendant
No.1, it does not in any manner make liable
defendant No.2 to make the payment which was
due to plaintiff from defendant No.1. The
agreement does not speak of liability of defendant
No.1 to be discharged by defendant No.2. It only
revived earlier agreement dated 8.1.1985 between
defendant No.1 and R.C. Goenka. Defendant No.2
appeared in the scenario when he signed MoU
dated 18.12.1986 as a confirming party and
therefore, it can be safely said that defendant No.2
was not a party to any agreement or
correspondence which took place between the
plaintiff and defendant No.1 prior to MoU (Ex.-P1).
77. Learned counsel for defendant No.2 has argued that
defendant No.2 was neither a guarantor nor an
indemnifier for payment of the amount due from
defendant No.1 to the plaintiff. At the maximum he
can be considered as an agent and an agent cannot
be sued where the principal is disclosed. He further
argued that liability of defendant No.2 to satisfy the
claim of the plaintiff in the present suit is only to the
extent of payment of Rs.15 lacs out which Rs.3 lacs
have been paid and defendant No.2 is not
connected with the provision of the area of 1275 sq.
ft. or payment of the value of the said area in lieu
thereof.
78. The handing over of the possession of Office Block
Phase-I by the plaintiff in terms of MoU cannot be
termed as consideration nor there are any such
pleadings in the plaint as defendant No.2 had
received the possession of the said property by
virtue of agreement dated 4.2.1986. Learned
counsel for the defendant No.2 has also highlighted
that MoU was merely an agreement to enter into
another regular agreement which never came into
light and therefore MoU is not enforceable against
the defendant No.2. The MoU was never intended
to create any legal relationship between the plaintiff
and defendant No.2. He has referred to Punit
Beriwala v. Suva Sanyal & Anr. - AIR 1998
Calcutta 44.
79. It is further argued by the learned counsel for the
defendant No.2 that he was authorized to collect
sale proceeds in respect of „owners‟ allocation‟ in
proposed building Tribhuvan Complex and to use,
utilise and disburse the same in terms of the
agreement and arrangement between the
defendants as well as other concerned parties like
Bank of India. Plaintiff was also to be paid from the
amount so collected by defendant No.2 for and on
behalf of defendant No.1. The bank had made it
clear vide letter dated 28.2.1989 that no payment
was to be made to the plaintiff.
80. It is emphasised that though defendant No.2 was
ready and willing to make the payment as agreed in
terms of MoU but because of refusal by Bank of
India he could not make the payments and it is for
the defendant No.1 to clear the dues of the plaintiff
which fact is also borne out from the MoU (Ex.-P1).
He has referred to Rahunath Jha v. Kesori Lal
and others - AIR 1934 Patna 269 and Midland
Overseas v. M.V. "CMBT Tana and others - AIR
1999 Bombay 401 to support his submissions.
81. It is submitted that defendant No.2 is neither
severally nor jointly liable to pay any amount to the
plaintiff and the memorandum of understanding
dated 18.12.1986 being without consideration is not
enforceable as against defendant No.2.
82. Section 10 of the Indian Contract Act defines
agreements which are contracts. All agreements
are contracts if they are made by the free consent
of the parties competent to contract for a lawful
consideration and with a lawful object and are not
declared to be void.
83. Section 48 of the Companies Act authorises a
company to empower any person either generally
or in respect of specific matters as its attorney to
execute its deeds on its behalf at any place. A deed
signed by such an attorney on behalf of the
company under its seal, where sealing is required,
becomes binding on the company.
84. Undisputedly MoU dated 18.12.1986 (Ex.-P1) qua
defendant No.2 is without consideration. Defendant
No.2 was appointed to collect money for the
owners‟ allocation. This fact finds mention in the
letter dated 20.7.1989 (Ex.-P3). Vide this letter
plaintiff was informed by defendant No.2 that he
and Bharat Bhaskar were to pay Rs.25 lacs out of
the money receivable from the sale of owners‟
allocation and that in terms of the agreement he
had already paid a sum of Rs.3 lacs. Defendant
No.2 showed his inability to pay the balance amount
and informed the plaintiff that Mr. Bharat Bhaskar
had entered into a MoU without prior consent of
Bank of India, the mortgagee bank and the bank
had intimated him not to make any payments to the
plaintiff. Defendant No.2 wrote another letter dated
7.10.1989 to Mr. O.P. Khadaria, Advocate that
whatever money was to be paid by him to the
plaintiff was on behalf of and on account of Ishwar
Industries.
85. Plaintiff in his cross-examination admitted that
defendant No.2 had made payment of Rs.3 lacs to
the plaintiff on behalf of defendant No.1. These two
letters clearly indicate that defendant No.2 was to
make payment for and on behalf of defendant No.1
from the amount so collected by him from owners‟
allocation. Therefore, he never made himself
personally liable to pay the debt of the plaintiff
payable by defendant No.1.
86. Bare reading of MoU (Ex.-P1) makes it clear that
defendant No.2 did not undertake to discharge the
liability of defendant No.1 completely. The line
appearing in the MoU "either by the first party or
the confirming party" clearly indicates the liability
of defendant No.2. This liability was confined to the
payment of Rs.15 lacs only for and on behalf of
defendant No.2. As discussed above no regular
contract followed the MoU. While contracting,
defendant No.2 did not undertake any personal
liability. Hence his status remained as that of
collecting agent and he cannot therefore be made
personally liable for the alleged breach of contract.
Reference is made to Rahunath Jha v. Kesori Lal
and others (supra) and Midland Overseas v.
M.V. "CMBT Tana and others (supra).
87. Similarly, in the facts and circumstances of this
case, it cannot be said that defendant No.2 had
entered into a concluded agreement with the
plaintiff for valid consideration. A mere agreement
to agree to pay certain amount to the plaintiff
cannot be considered as a legal agreement
between the parties and therefore, such an
agreement is not enforceable against defendant
No.2.
88. MoU was never executed with a view to create a
legal relationship between the plaintiff and
defendant No.2. As already stated above, no formal
or regular agreement was executed between the
parties after the execution of MoU (Ex.-P1).
Impugned MoU is written in hand on three sheets
probably torn out from some notebook. Plaintiff did
not do anything for defendant No.2 which the
defendant No.2 was legally bound to do so as to
bind defendant No.2 to compensate him for
something by him. In such circumstances
therefore, MoU qua defendant No.2 is a void
agreement within the meaning of Section 25 of the
Contract Act. Payment of Rs.3 lacs made by
defendant NO.2 to the plaintiff does not make MoU
as valid contract. Reference is made to Punit
Beriwala v. Suva Sanyal & Anr. (supra).
89. It is a common case of the parties that the
impugned property was mortgaged with Bank of
India even prior to the execution of agreement
dated 20.8.1985 between plaintiff and defendant
No.1. Being a mortgagee, bank is a secured
creditor and has a lien over the property.
Therefore, without the permission of the bank
plaintiff could not have enforced any rights against
the property.
90. Reference has already been made to letter dated
14.9.1985 written by Bank of India to Ishwar
Industries Ltd. wherein it was made clear that in
respect of areas proposed to be leased out,
cheques, drafts for all interest free deposits and
rentals to be received from the prospective lessees
should be made out in the name of Bank of India A/c
of the Ishwar Industries Ltd. and deposited with
their Khan Market Branch.
91. Because of the embargo placed by the Bank of India
on defendant No.1, defendant No.2 after realization
of the owners allocation could not have made the
payment of the due amount to the plaintiff.
Therefore, no liability can be fastened on defendant
No.2. Hence, I conclude that defendant No.2 is
neither severally nor jointly liable to pay the suit
amount to the plaintiff. Memorandum of
Understanding dated 18.12.1986 (Ex.-P1) is not
enforceable against defendant No.2. These two
issues are accordingly decided in favour of
defendant No.2 only.
92. Plaintiff has claimed interest @18% per annum on
the due amount on the basis of clause 4 contained
in the MoU wherein the parties agreed that if the
payment was not made in time, the defendant shall
be liable to pay interest @18% from the date of
default till payment.
93. The amount of Rs.28,30,000/- also includes interest
amounting to Rs.6,30,000/- upto 30.11.1989. As
per MoU (Ex.-P1) rate of interest was agreed as 18%
per annum from the date of default until payment
was made. As discussed above, MoU (Ex.-P1) has
been fully proved on record and being admitted
document wherein defendant No.1 has
acknowledged its liability to pay the amount of
Rs.15 lacs and allot space of 1275 sq. ft. or in the
alternative to pay the value of the space to the
plaintiff within the stipulated period and in case the
payment was not so made defendant No.1 agreed
to pay interest @18% per annum on the due
amount. Therefore, plaintiff is entitled to interest as
per agreement and as claimed by him in the suit. In
all plaintiff is entitled to Rs.6,30,000/- as interest
upto 30.11.1989 i.e. for the period before the filing
of the suit. These two issues are accordingly
decided.
94. Plaintiff has claimed interest @18% per annum on
the amount of Rs.22,00,000/- from the date of the
institution of the suit till realization. Since parties
had an agreement that defendant shall pay interest
to the plaintiff @18% per annum if the installments
were not made in time, plaintiff is entitled to the
interest at the agreed rate on the principal amount
of Rs.22,00,000/- (principal amount of Rs.12 lacs
plus Rs.10 lacs, value of the space) from the date of
filing of the suit i.e. 4.12.1989 till realization.
95. In view of my observations on the issues as above, I
hereby pass a decree for Rs.28,30,000/- with cost in
favour of the plaintiff and against defendant No.1.
Suit as against defendant No.2 is hereby dismissed.
Plaintiff is also awarded interest pendentelite and
future interest @18% per annum on the principal
amount of Rs.22,00,000/-. Decree be prepared
accordingly.
ARUNA SURESH (JUDGE) July 24, 2009 jk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!