Citation : 2009 Latest Caselaw 2790 Del
Judgement Date : 23 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: 8.7.2009
Date of Order: 23.7.2009
CS (OS) No. 66A/1992
% 23.07.2009
D.R.Sharma ... Plaintiff/Petitioner
Through: Shri B.M.Sehgal, Advocate
Versus
Delhi Development Authority ... Respondent/Defendant
Through: Ms. Renuka Arora, Advocate
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
The respondent/DDA filed objections against award dated
24.6.1991 whereby the learned Arbitrator allowed some of the claims of the
petitioner either fully or partly.
2. The petitioner was awarded a contract for laying down sewerage
line under Re-development Scheme of Kingsway Camp. The date of start of
work was 16.12.1984 and the stipulated date for completion of work was
15.4.1985. According to respondent/DDA the work was much behind the
schedule and was not completed by petitioner even by the end of 1986 with the
result that DDA was constrained to rescind the contract vide its notice of decision
dated 22.1.1987. The dispute was raised by the petitioner in respect of its claims
which was referred to the Arbitrator in terms of clause 25 of the Agreement
between the parties and the learned Arbitrator passed the impugned award.
3. Claim No.1 was made by the petitioner for a sum of Rs.80,000/-
due towards the final bill. The learned Arbitrator allowed an amount of
Rs.70,508.47. Claim No.2 for a sum of Rs.5,00,000/- towards extra/substituted
items was rejected by the learned Arbitrator. Claim no.3 for a sum of Rs.10,000/-
towards amount withheld by the respondent/DDA for not conducting Disc-test by
the petitioner was allowed in full. Claims No. 4, 5 & 6 of the petitioner were
rejected by the learned Arbitrator. Claim No.7 for a sum of Rs.2,00,000/- was
made by the petitioner for damages. The learned Arbitrator awarded a sum of
Rs.1,83,993.21. Claim No.8 made by the claimant for increase in rates of bricks
etc. was rejected. Claim No.9 made by the petitioner for a sum of Rs.15,000/-
claiming that the respondent had failed to release the payment in time was
allowed by the learned Arbitrator in full. Claims No. 10 & 11 made by the
petitioner were rejected. Claim no.12 was for pendent lite interest. The learned
Arbitrator allowed 12% p.a. interest from date of award to the date of actual
payment or upto the date of award being made a Rule of the Court.
4. Counter Claim No.1 of the respondent/DDA for a sum of Rs.
1,79,881/- on account of contract having been rescinded under Clause 3 of the
Agreement and the balance work got done at the risk and cost of petitioner by
incurring extra expenditure was rejected by the learned Arbitrator. Counter Claim
No.2 for a sum of Rs. 1,00,889/- on account of delay in work as well as Counter
Claim no. 3 for Rs.1,00,000/- against forfeiture of security deposit made by the
DDA were rejected. Counter Claim No.4 made by the respondent/DDA for
Rs.28,976/- on account of rectification of defects was allowed.
5. The respondent/DDA has assailed the award claim-wise. It is
stated by respondent/DDA that under Clause 25 of the Agreement, whereunder
the learned Arbitrator was appointed, it was obligatory on the part of the
Arbitrator to give reasons for awarding any amount, if the awarded amount was
more than Rs.50,000/-. The learned Arbitrator while allowing Claim No.1 for Rs.
70,508.47 gave no reasons and gave a totally non-speaking award thereby the
learned Arbitrator misconducted himself and the proceedings. The award of the
Arbitrator on this count was bad in law. It is also stated that the award against
claim no.1 was otherwise bad because it was contrary to clause 7 of the
agreement. On the other hand, the petitioner has submitted that objection raised
by the petitioner was baseless. Clause 7 of the agreement was not applicable
and there was no misconduct on the part of the Arbitrator.
6. A perusal of Award shows that while allowing a sum of
Rs.70,508.47 in favour of the petitioner under claim no.1, the only reason given
by the learned Arbitrator was - "After taking into consideration all the contentions
put forth by both the parties and all other relevant facts arising therefrom, I hold
that claim of the claimants is partly justified, to the extent of Rs.70,508.47".
7. There is no dispute about the fact that the learned Arbitrator was
required to given reasons in terms of clause 25 of the contract, the relevant part
of which reads as under:
"In all cases where the amount of claim in dispute is Rs.50,000/- (Rs.Fifty Thousand) and above, the Arbitrator will give reasons for the award".
8. It is obvious that the learned Arbitrator had given no reason for
awarding the amount. In Gora Lal v. UOI (2003) 12 SCC 459 the arbitration
clause between the parties provided that the Arbitrator on all matters referred to
him shall indicate his findings along with sums awarded separately on each
individual item of the dispute. The Arbitrator in that case had not given his
finding and the award was set aside by the High Court. The matter went to
Supreme Court and Supreme Court observed as under:
7. The point for determination in this case is: whether the arbitrator ought to have given reasons in support of his findings, along with the sums awarded, on each item of dispute. To decide this point, we have to go by the text and the context of clause 70 of the arbitration agreement quoted above. Under the said clause, the arbitrator was required to identify each individual item of dispute and give his findings
thereon along with the sum awarded. In this context, one has to read the word "findings" with the expression "on each item of dispute" and if so read it is clear that the word "finding" denotes "reasons" in support of the said conclusion on each item of dispute. The word "finding" has been defined in "Words and Phrases, Permanent Edn., 17, West Publishing Co." to mean "an ascertainment of facts and the result of investigations". Applying the above test to clause 70, we are of the view that the arbitrator was required to give reasons in support of his findings on the items of dispute along with the sums awarded. We make it clear that this order is confined to the facts of this case and our interpretation is confined to clause 70 of the arbitration agreement in this case.
9. I consider that the award of the learned Arbitrator under claim no.1
is liable to be set aside in view of clause 25 of the contract as it gives no reason
why the amount has been awarded. Even otherwise, I find that the learned
Arbitrator in his discussion had observed that the claimant had largely depended
upon the theoretical calculations for the measurement claimed by them. The
claim was not based on actual measurements and could not have been allowed
by the Arbitrator by a non-speaking award. The award against Claim no.1 is set
aside on this count.
10. Claim No.3 was made by the petitioner for sum of Rs.10,000/-.
This amount was deducted from the bill of the petitioner as the petitioner failed to
perform the necessary Disc-test in order to ascertain the functionality of sewer
lines laid by the petitioner. There is no dispute about the fact that this disc test
was not performed by the petitioner and this amount was deducted because of
non-performance of this test. The learned Arbitrator allowed this amount to the
petitioner on the ground that the respondent had also not carried the Disc-test
and put the sewer line to use without the Disc-test. It is stated by
respondent/DDA in objections that this amount could not have been awarded to
the petitioner as the deduction was admittedly made for not conducting the test.
The fact that DDA put the sewer line to use without conducting the same test is
no ground for awarding the amount to the petitioner. The learned Counsel for
petitioner has argued that the amount was justly awarded and no recovery could
be made if the amount deducted was not spent for the purpose it was withheld.
11. Under the contract, the petitioner was to perform the Disc-test on
the sewer line. This was one of the conditions of the contract and since this
condition was not fulfilled, the amount which was to be spent on the test was
deducted. It was not obligatory on the respondent/DDA to conduct this Disc-test
before putting the sewer line to use. DDA could have ensured the clearance of
sewer line by manual inspection or other modes. The Disc-test was the
obligation of the contractor. The amount deducted cannot be directed to be
refunded back to the contractor on the ground that the same test was not
conducted by DDA. I, therefore find that this amount was awarded to the
Contractor, contrary to contract. The Arbitrator is bound by the contract and
cannot allow a claim which is contrary to contract. The award of this claim is
therefore, set aside.
12. Claim No.7 was raised by the claimant for damages of
Rs.2,00,000/-. The learned Arbitrator observed that the entire site was not made
available to the claimant by respondent, during currency of the stipulated contract
period ie. 04 months. He observed that it was respondent/DDA, which was liable
for prolongation of the contract beyond the stipulated date of completion. The
claimant at relevant time had requested respondent to measure up the work and
pay for work executed by then, or pay 40% above the Delhi Schedule of Rates,
1981, for the work yet to be executed thereafter. The work was not measured up
and paid, but the work continued. No new date for completion of remaining work
was fixed by mutual consent or otherwise. The time for completion of work was
thus set at large by the conduct of the parties. The arbitrator held that under
these circumstances the delay beyond the stipulated date of completion was
attributable to DDA and claimant was entitled to be compensated for work done
beyond the stipulated date of completion, due to breaches committed by DDA.
He therefore awarded a sum of Rs.1,83,993.21.
13. It is argued by the learned Counsel for the respondent that the
award was contrary to the terms of the contract. It was specifically provided in
the contract that no compensation would be awardable in case of partial
availability of site or delay in providing of material at site and the work was to be
rescheduled accordingly and in case of rescheduling of the, work the Contractor
would not be entitled to any compensation or damages for the period of delay.
The learned Counsel for the petitioner on the other hand argued that as per the
contract the site was to be made available on the date of contract and the
petitioner suffered loss due to site not being available and the work dragged on
due to this. The rates given in the tender were based on Delhi Schedule of
Rates, 1977 whereas when the work was completed Delhi Schedule of Rates
1988 was applicable. There was no escalation clause in the agreement because
clause 10(c) which was applicable only in case of statutory increase. The
Arbitrator therefore rightly awarded damages on the basis of difference in rates of
Delhi Schedule of Rates of 1988 and 1977, since the breach was committed on
the part of the respondent.
14. Clause 7 of General Conditions of the contract reads as under:
"The contractor is advised to see the site of work before tendering to apprise himself of the conditions existing at site of work."
15. . It is apparent that the contractor/claimant was to see the site
before even filing tender/quotations for the work and to apprise himself what was
the condition of site, the site was clear and available for work or not. Despite the
fact that in notice inviting tender clause 2-A read "The site of the work is
available", the specifications and conditions attached with the contract
specifically provided as under:
The Contractor must get acquainted with the proposed site for the works and study specifications and conditions carefully before tendering. The works shall be executed as per program approved by the Engineer-in-Charge. If part of the site is not available for any reason or there is some un- avoidable delay in supply of materials stipulated by the department, the program of construction shall be modified accordingly and the contractor shall have no claim for any extras or compensation on this account.
16. The above condition makes it abundantly clear that the non-
availability of site in time could not be a ground for payment of damages. This
clause also makes it clear that time was not essence of the contract and in case
the site was not partly available for any reason, the period for executing the
contract could be extended and rescheduled and in case of modification of the
schedule of completion of contract, the claimant was not to lay any claim for extra
compensation/damages on this ground. The learned Arbitrator ignored this
condition of contract altogether. The contention of the respondent had been that
the delay was on the part of the contractor and the site order book and various
letters written by the respondent/DDA calling upon the petitioner to expedite the
work have been ignored by the learned Arbitrator. Not going into this contention
- whether the Arbitrator appreciated the evidence regarding delay on the part of
the contractor, still I consider that in view of the specific clause in the contract
that the contractor would not be entitled for compensation because of
rescheduling of the contract, the learned Arbitrator could not have awarded
compensation. The Arbitrator himself has observed that it was due to conduct of
both the parties that the time was set at large, the learned Arbitrator could not
have therefore, held that DDA alone was responsible for setting the time at large
and thereafter awarded compensation. When both the parties' conduct set the
time at large, the contractor would not be entitled for any compensation, more so
in view of the specific clause given in the contract that rescheduling of work shall
not entitle the contractor for any compensation. It is also not understood in view
of the fact that there was no escalation clause provided in the contract, how the
learned Arbitrator could have provided escalation to the contractor? The
Arbitrator is prisoner of the contract and he cannot write a new contract for the
parties. If there is no clause for escalation, the Arbitrator cannot introduce
escalation clause and give enhancement/compensation to the contractor. I,
therefore set aside this award being contrary to contract.
17. Claim No.9 was for refund of Rs.15,000/- claimed by the DDA as
rebate. The learned Arbitrator observed that this rebate was offered by the
contractor conditionally and the condition was not fulfilled by DDA while
deducting the rebate. I find no reason to disturb the award of the Arbitrator on
this count.
18. It is submitted by learned Counsel for respondent/DDA that counter
claim no.1 was in respect of rest of the work got done at risk and cost of the
petitioner in terms of clause 3 of the agreement and therefore could not have
been rejected. Conclusion arrived at by the learned Arbitrator was that the
contractor had already done the quantum of work as per contract inclusive of
deviation provided therein. This finding of the Arbitrator cannot be assailed by
the DDA I, therefore, consider that any further work beyond the original contract
and deviation could not have been done at cost and risk of the contractor. The
Counter Claim has been rightly rejected by the Arbitrator. Similarly, the award of
Arbitrator on Counter Claims no.2 & 3 is upheld. The learned Arbitrator allowed
Counter Claim no.4 of the respondent and awarded a sum of Rs.28,976/- to the
respondent. This awarding of amount has not been assailed by the
claimant/contractor by filing any objections.
19. As a result of my above discussion, the award of the learned
Arbitrator in respect of claims no.1, 3 & 7 are set aside and rest of the award is
upheld and made a Rule of Court. Decree Holder would be entitled to interest @
8% p.a. from the date of award till realization.
Decree Sheet be prepared accordingly.
July 23, 2009 SHIV NARAYAN DHINGRA, J. vn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!