Wednesday, 29, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Union Of India & Anr. vs Sudhir Engineering Company
2009 Latest Caselaw 2714 Del

Citation : 2009 Latest Caselaw 2714 Del
Judgement Date : 20 July, 2009

Delhi High Court
Union Of India & Anr. vs Sudhir Engineering Company on 20 July, 2009
Author: Mukul Mudgal
*       IN THE HIGH COURT OF DELHI AT NEW DELHI

                                              Date of Decision : July 20, 2009


+       FAO(OS) No. 185/2007 and CM Nos. 7903/2007 and 10759/2007


        UNION OF INDIA AND ANR.                         ..... Appellants
                      Through : Ms. Preeti Dalal, Mr. R.S. Bhatnagar
                                and Ms. Maneesha Dhir, Advocates

              versus


        SUDHIR ENGINEERING COMPANY             ..... Respondent
                     Through : Mr.Raman Kapur, Mr. Manish Kumar
                               and Mr. Amit Kumar, Advocates.
        CORAM:
        HON'BLE MR. JUSTICE MUKUL MUDGAL
        HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL

1. Whether reporters of local papers may be allowed to see the

     judgment?      NO

2. To be referred to the Reporter or not?   YES

3. Whether the judgment should be reported in the Digest?        YES


                           JUDGMENT (ORAL)

20.07.2009

MUKUL MUDGAL, J :

1. This appeal challenges the order of the learned Single Judge dated 13 th

September, 2006 dismissing the objections preferred by the appellants

(respondents before the learned Single Judge) by filing of IA No. 7169/1994

under Section 30 and 33 of the Arbitration Act, 1940 (hereinafter referred to

as „the 1940 Act‟). The learned Single Judge held that the award was signed

by two Arbitrators and the third Arbitrator declined to do so. The learned

Single Judge reasoned as under: -

"4. On the first objection, it may be noted that since time was expiring 2 Arbitrators who had concurred in the award, getting no response from the 3rd Arbitrator, published the award.

5. Surely, if 1 out of the 3 Arbitrators refuses to sign an award that does not mean that the majority would be left high and dry. It was open to the 3rd Arbitrator to give a dissenting award."

2. The reasoning given by the learned Single Judge is unexceptionable,

particularly, when the learned Arbitrators view in respect of claims no.1,3

and 5 was very factual in nature and did not warrant interference in the

limited jurisdiction of the Court in dealing with the challenges to the arbitral

awards.

3. In so far as the reasoning of the learned Single Judge in respect of

non-signing of the award by the third Arbitrator is concerned, the reasoning

is unexceptionable, in so far as it relates to the reluctance/obdurance/refusal

of the third Arbitrator to sign the award. In fact, the reasoning of the learned

Single Judge is in conformity with the legislative wisdom contained in

Section 31 of the Arbitration Act, 1996 (hereinafter referred to as the „1996

Act‟) the relevant part of which reads as follows: -

"31. Form and contents of arbitral award.

(1) An arbitral award shall be made in writing and shall be signed by the members of the arbitral tribunal.

(2) For the purposes of sub-section (1), in arbitral proceedings with more than one arbitrator, the signatures of the majority of all the members of the arbitral tribunal shall be sufficient so long as the reason for any omitted signature is stated."

4. In our view, Section 31 was drafted by the Legislature in view of such

situation having occurred where one of the three Arbitrators declined to sign

the award and therefore, Section 31(2) clearly provides that so long as the

arbitral award is signed by the two Arbitrators and records the reasons for

non-signing of the award by the third Arbitrator, in so far as the proceedings

under the 1996 Act are concerned, that is sufficient to render the said award

enforceable. The present proceedings are, however, under the 1940 Act.

While such a provision is not contained in the 1940 Act, which

is silent on this issue, we, nevertheless feel that the reasoning given by the

learned Single Judge is indeed what may be termed as prescient in nature, as

Section 31(2) of the 1996 Act now reflects to a large extent the reasoning of

the learned Single Judge.

5. The other grievance raised by the learned counsel for the appellant

was that the order of reference of this Court dated 13th November, 1992 read

as follows: -

"1. Whether the disputes and differences which have arisen between the parties are liable to be presented before the Arbitrator? If so, its effect?"

6. It has been submitted that the above order of reference clearly

visualizes the filing of the counter-claim. Quite apart from the fact that the

order of reference uses the phrase „have arisen‟ which may refer to the

claims/differences prior to the order of reference dated 13th November, 1992,

in any case, the arbitral tribunal in its interim award has reasoned as

follows:-

"....Consequently, these arbitrators feel that the counter claims being raised by the respondents before the Tribunal of Arbitrators are not covered by the reference order and as such these two arbitrators are also of the considered opinion that consideration and decision of the counter claims can, at the most, be kept open so that if the respondents have any legal remedy for getting such counter claims determined by law the same may not get barred by the present award of the Arbitrators by majority decision."

7. Thus, in our view, the grievance raised by the appellant, even if

accepted, is fully redressed by the observations of the learned Arbitrators.

We may also refer to the finding of the learned Single in paragraph 7 of the

impugned judgment, which reads as follows: -

"7. It is settled law that where disputes are referred to an Arbitrator by a court or by the nominating authority, mandate of the Arbitrator is to decide the disputes which are referred and no more."

8. No fault could be found by the court to the above reasoning of the

learned Single Judge nor was any pointed out by the learned counsel.

9. Accordingly, we are satisfied that there is no merit in this appeal and

the same is dismissed and stands disposed of. All the pending applications

also stand disposed of.

(MUKUL MUDGAL) JUDGE

(NEERAJ KISHAN KAUL) JUDGE July 20, 2009 sk

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter