Citation : 2009 Latest Caselaw 2636 Del
Judgement Date : 15 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: July 10, 2009
Date of Order: July 15, 2009
+OMP 363/2009
% 15.07.2009
M/s Delhi Paper & Product Company Ltd. ...Petitioner
Through: Mr. Shiv Khorana, Advocate
Versus
Union of India ...Respondent
Through:
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this petition under Section 34 of the Arbitration & Conciliation Act,
1996 (for short, "the Act"), the petitioner has assailed the award dated 17th
February 2009 on the ground that the learned Arbitrator wrongly rejected the
claim of the petitioner on the ground that the store was offered by the
petitioner after the validity of the rate contract. It is submitted that a
concluded contract had come into operation between the petitioner and
respondent when respondent received the supply order on 11th October 2002
and offered to supply the material. The arbitrator should have held that a
concluded contract was there and hence should have awarded the claims of
the petitioner.
2. Brief facts relevant for the purpose of deciding this petition are that the
respondent had entered into a rate contract with the petitioner for delivery of
OMP 363/2009 M/s Delhi Paper & Product Company Ltd. v.UOI Page 1 Of 4 paper. This rate contract was valid from 14th August 2001 to 1st August 2002.
An official of the respondent dispatched a supply order for supply of material
under the rate contract on 5th October 2002 which was received by the
petitioner on11th October 2002. The letter /supply order though was
dispatched by respondent's official on 6th October 2002 but it was ante-dated
as 27th July 2002. After the petitioner received this supply order on 11 th
October 2002, the petitioner wrote to the respondent's department that the
material, as mentioned in the supply order, was ready for inspection.
However, respondent never inspected the material and instead extended the
delivery period up to 30th April 2003. Respondent vide another letter dated 2nd
July 2003 cancelled the RC on the ground that its validity had already expired
on 1st August 2002 and no delivery of material could be taken.
3. After this cancellation of RC, claimant protested and stated that it had
manufactured the store and suffered losses and invoked the arbitration
clause claiming loss of Rs.37 lac.
4. Learned Arbitrator observed that the rate contract was valid from 14th
August 2001 to 1st August 2002 and there was no contract for supply of stores
between the parties existing on 11th October 2002 i.e. after the expiry of the
rate contract and the arbitration clause also ceased to exist. There was no
valid and binding contract between the parties. The supply order did not
constitute any valid contract between the parties and therefore no claim
could be laid by claimant.
5. It is not disputed by petitioner that the rate contract entered into
between petitioner and respondent come to an end on 1st August 2002.
OMP 363/2009 M/s Delhi Paper & Product Company Ltd. v.UOI Page 2 Of 4 Through the petitioner has not placed on record the rate contract but the
general conditions of the rate contract of DG&SD provides a specific period up
to which requisition under the contract can be placed on the contractor and
this period was between 14th August 2001 and 1st August 2002. Another
clause (clause 5) of the rate contract specifically provided that a requisition
under the rate contract has to be so placed so as to reach the contractor on
or before the last date on currency of the rate contract. Thus, requisition on
the petitioner for supply of material had to reach the petitioner before 1st
August 2002. If any requisition reached the petitioner after 1 st August 2002,
that could not be said to be under the rate contract. In the present case, the
supply order/ requisition was dispatched on 5th October 2002, much after the
expiry of the rate contract and had reached the petitioner on 11 th October
2002. It is obvious that the rate contract was not in force at that time and had
already come to an end by afflux of time. The arbitration clause of the rate
contract had also come to an end. The supply order thus did not constitute a
contract under the rate contract. The respondent was therefore not obliged to
take any supply under the rate contract from petitioner and the cancellation
letter issued by respondent was merely an intimation of something which had
already happened i.e. rate contract having come to an end on 1 st August
2002.
6. The contention of the counsel of petitioner is that the supply order in
itself constituted a new contract and it was an offer made by respondent
which was duly accepted by the petitioner by writing a letter that the
petitioner was ready to supply the stores and the same should be inspected.
If the supply order is considered as a separate offer and letter of the
petitioner is considered as an acceptance even then petitioner has no case.
OMP 363/2009 M/s Delhi Paper & Product Company Ltd. v.UOI Page 3 Of 4 The supply order had no arbitration clause independent of rate contract. The
supply order only was a requisition of the goods and if the letter written by
petitioner was taken an acceptance, this would constitute a contract separate
from the rate contract having no arbitration clause. The petitioner in that
eventuality could not have invoked the arbitration clause and could not have
laid any claim before the arbitrator. The very fact that the petitioner invoked
the arbitration clause shows that the petitioner relied on the rate contract,
that expired on 1st August 2002. Since the rate contract had already come to
an end, no requisition could have been entertained by petitioner without
asking the respondent to renew the rate contract so that he could supply the
material. Since the rate contract was not renewed, no contract came into
force between petitioner and respondent and the award made by the learned
arbitrator is a valid award.
7. The petition is hereby dismissed. No orders as to costs.
July 15, 2009 SHIV NARAYAN DHINGRA J. rd
OMP 363/2009 M/s Delhi Paper & Product Company Ltd. v.UOI Page 4 Of 4
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!