Citation : 2009 Latest Caselaw 2542 Del
Judgement Date : 9 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No.328/2009
% Date of decision: 09.07.2009
BHUMIKA ENTERPRISES PVT. LTD. ....... Petitioner
Through: Through: Mr. T.K. Ganju, Sr. Advocate
with Ms. Roopa Dayal and Ms. A Patra,
Advocates.
Versus
ATUL ENTERPRISES ....... Respondent
Through: Mr. S.K. Sharma with Mr. Mayank
Bansal, Advocates.
AND
OMP No.331/2009
MRS. SAROJ BALA,
PROPRIETOR ATUL ENTERPRISES ....... Petitioner
Through: Mr. S.K. Sharma with Mr. Mayank
Bansal, Advocates.
Versus
BHUMIKA ENTERPRISES PVT. LTD. ....... Respondent
Through: Mr. T.K. Ganju, Sr. Advocate with Ms.
Roopa Dayal and Ms. A Patna,
Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. The two petitions have been preferred by the two parties to the
agreement dated 5th March, 2009 containing an arbitration clause.
M/s. Bhumika Enterprises Pvt. Ltd. (BEPL) petitioner in OMP No.
328/2009 had put on sale certain machineries/buildings scrap etc. at
its works at Udaipur as detailed in Annexure 1 to the Agreement;
M/s. Atul Enterprises (AE) (through its proprietor Ms. Saroj Bala)
petitioner in OMP No. 331/2009 had agreed to buy the same for a
total sale consideration of Rs. 7 crores under the said Agreement
dated 5th March, 2009. The said consideration was agreed to be paid
in installments commencing from 20th March, 2009 till 5th
September, 2009 as mentioned therein and of which post dated
cheques were delivered by AE to BEPL. It was inter alia a term of the
said Agreement that, on receipt of each installment, BEPL in
consultation with AE would approve a lot from the list of machinery
in annexure 1 that AE can dismantle and remove from the premises
and the value of such machinery shall not exceed the installment
paid by AE; that if AE lifts more than the amount paid till then BEPL
shall forfeit all monies paid till then and put up the entire remaining
machinery for sale as per its discretion; that if AE did not pick up the
lot as approved on the due date, the payment of the next installment
shall still become due; that AE shall not be entitled to withdraw or
cancel and in case it does so, all monies paid till then shall be
forfeited by BEPL; time was the essence of the Agreement and it was
further provided that upon failure of AE to lift the entire machinery
within the agreed time and the grace time agreed, damages as
mentioned therein shall be levied for a further term of 30 days and
whereafter BEPL shall have the right to forfeit all the money paid till
then and to dispose of the entire machinery; the sale was to be on as
is where is basis.
2. Some of the cheques having been dishonoured, BEPL issued
notice of termination of the Agreement to AE and which has resulted
in the petitions being filed. In OMP No.; 328/2009 BEPL has claimed
the relief of restraining AE from interfering with BEPL selling,
transferring or creating third party rights in the machinery and
building scrap lying at the premises or from removal thereof. In OMP
No. 331/2009 AE has claimed the interim measures of staying the
operation of the letter dated 4th June, 2009 of BEPL of termination of
the Agreement and for directing BEPL to maintain status quo ante as
it existed on the date of execution of the Agreement. Vide ad interim
orders dated 15th June, 2009 the parties were directed to maintain
status quo in respect of machinery and building scrap lying at the
premises of BEPL. The said order was subsequently modified on 2nd
July, 2009 with the consent of the parties, to be with respect only to
the machinery subject matter of the Agreement and not with respect
to other machinery at the said premises of BEPL which did not form
part of the Agreement.
3. The dispute and controversy between the parties is as to the
amount paid by AE to BEPL till date; whether the machinery
admittedly removed till date was at the instance of AE and/or by its
nominees or by BEPL surreptitiously in breach of the Agreement.
4. It is not disputed that prior to the Agreement dated 5th March,
2009 (supra) Agreements dated 14th February, 2009 and 25th
February, 2009 with respect to same subject matter were also
executed by the parties. The said Agreements are identical to the
agreement dated 5th March, 2009 save that the consideration
mentioned in the Agreement dated 14th February, 2009 is Rs. 8.51
crores and in the Agreement dated 25th February, 2009 is Rs. 7.51
crores. The documents show that the consideration was so reduced
on the request of AE and for the reason of the fall in the prices of
scrap at that time. The counsel for AE has on the contrary contended
that in fact the sale consideration was Rs. 8.51 crores only and on
the insistence of BEPL, payments were made in cash by AE to BEPL
and on successive payments being made in cash agreements
reducing the sale consideration were executed and the cheques
which were given under the said two earlier agreements, were
returned by BEPL to AE agasint cash. It is further contended that the
documents containing the request of AE for reduction in sale
consideration were obtained by BEPL at the time of signing of the
Agreement of 5th March, 2009. The counsel for AE, in this regard
also relied upon the stamp papers used for the three agreements and
contended that the same were purchased by BEPL on the same date
and bear consecutive numbers. It is the submission of AE that
besides the sum of Rs. 1.51 crores paid in cash, a further sum of
Rs.2.07 crores has been paid till 20th April, 2009 making a total
payment of Rs. 3.58 crores to BEPL.
5. The senior counsel for BEPL controverts the aforesaid position
and has relied upon the documents of reduction of sale consideration
and denied having received Rs. 1.51 crores in cash. It is contended
that a total sum of Rs. 1.48 crores has been received from AE till
date as shown in the statement filed by BEPL along with its
documents and leaving a balance of Rs. 5.52 crores out of total
agreed sale consideration of Rs. 7 crores.
6. The counsel for the AE contends that in spite of AE having
made the aforesaid payment of Rs.3.58 crores till date AE has not
removed any machinery or scrap from premises of BEPL, till date. At
the time of hearing on 2nd July, 2009, it was contended by the counsel
for AE that BEPL has surreptitiously removed machinery worth Rs. 3
crores from the premises. Invoices raised by BEPL on other parties
with respect to sale of the machinery forming subject matter of the
Agreement have been filed by AE along with its petition.
7. Per contrary the senior counsel for BEPL has contended that
the machinery which is alleged to have been surreptitiously removed
by BEPL in fact was removed and invoices aforesaid were drawn at
the instance of AE; that AE did not have sales tax number of its own
in Rajasthan from where machinery was to be removed and AE being
a scrap dealer himself had after entering into the Agreement with
BEPL identified the actual buyers of the material and asked BEPL to
effect sale directly in favour of the said purchasers leading to the
invoices aforesaid. BEPL has also filed letters received from the said
purchasers to the effect that they had lifted the said goods from
premises of BEPL after striking a deal with AE and that their
negotiations were with AE. The senior counsel for BEPL has also
drawn attention to the statement of payments received, filed by
BEPL in which all the said payments have been accounted for
besides certain other payments also received in cash from other
parties brought by AE and to whom the goods were delivered at the
instance of AE.
8. It is further the contention of BEPL supported by documents,
that BEPL was desirous of dismantling the machinery and factory
premises aforesaid for purposes of another project on the said
premises and if the said machinery is ordered to remain at site as
contended by AE, the same will lead to the project of the BEPL being
delayed, leading to incalculable damages to BEPL. The senior
counsel has further contended that the time was made the essence of
the Agreement for this reason only. It is further contended by the
senior counsel for BEPL that considering the nature of the
Agreement, the same is not specifically enforceable under the
provisions of the Specific Relief Act. Several judgments have been
cited in this regard. It is conte nded that even if AE succeeds in
establishing the averments aforesaid, the claim of AE against BEPL
shall at best be a monetary claim and for which the proposed project
aforesaid of BEPL cannot be jeopardized. It is informed that BEPL
has in terms of the agreement already appointed the arbitrator. On
enquiry as to whether the order of status quo could not be granted
for securing the amount, if any, ultimately found due to AE, the
senior counsel has drawn attention to the petition of AE and
contended that that is not the case with which AE has came before
the Court; the petition of AE is on the premise of AE being entitled to
status quo ipso facto during the pendency of the arbitration
proceedings.
9. On 2nd July, 2009 during hearing, it was put to the counsel for
AE whether AE was willing to lift the plant, machinery and goods in
terms of the Agreement lying at site, since according to it, as on that
date goods worth Rs. 3 crores had been removed and the goods
worth balance value of Rs. 5.51 crores were still lying in the factory
premises of BEPL. The counsel for AE at conclusion of hearing had
stated that since the statement that goods worth Rs. 3 crores had
been removed was made on the basis of the status existing as on the
date of filing of OMP No. 331/2009 i.e. 12th June, 209, AE before
accepting or rejecting the other would like to inspect the premises
again. As such the matter was adjourned to today only for the
purposes AE responding to the said offer of the Court. On suggestion
of the counsel for the parties on that date and to avoid any further
delays, a Court Commissioner was also appointed to draw up an
inventory of the machinery, building's scrap subject matter of
Agreement lying at site. The commission has been executed and the
Court Commissioner has filed the report.
10. The counsel for AE has today further contended that on
inspection it has been found that today goods/building's scrap of
value of Rs. 2.5 crores only are lying at site and valuable items are
missing. It is also contended that a list of plant and machinery
forming part of the agreement was prepared by parties while
negotiating the contract. The same does not form part of any of the
agreements. A copy thereof has been handed over in court. Several
items as mentioned in the said list are averred to have been removed
by BEPL. The counsel has on query also stated that AE is not
interested in specific performance of the Agreement and in any case
the agreement is now incapable of specific performance.
11. The counsel for AE has however contended that BEPL has
acted fraudulently not only in matter of receiving the huge sum of
RS. 1.51 crores in cash and also in removing the machinery
surreptitiously not only prior to the filing of the petition but also
thereafter and in preparing successive agreements and also taking
all the documents including letter dated 5th May, 2009 filed by BEPL,
from AE in advance and thus equities are not in favour of BEPL and
thus AE is entitled to the order of status quo. It is now orally
contended that the said order be also made to secure the monetary
award, if any, in favour of AE. He contends that BEPL has obtained
the letters aforesaid from its purchasers and that though AE does not
have a sales tax number in Rajasthan but the temporary sales tax
could have been obtained within hours in case of such transactions.
12. It being the admitted position that the agreement is not
specifically enforceable, no case of restraining BEPL from removing
the machinery or of maintaining status quo of the property is made
out. If AE is not interested in purchasing goods at site and/or if BEPL
cannot be compelled to sell the same to AE, no purpose will be
served by retaining the same. An inventory has already been
prepared. The photographs filed by court commissioner also show
that if the goods are ordered to remain as they are, there may be
pilferages and deterioration. While the claim of AE is monetary only,
and yet to be established if the said machinery/building's scrap are
not permitted to be removed immediately, the property of BEPL shall
be wasted and cannot possibly be put to use for the new project as
claimed. In fact during the hearing on 2nd July, 2009 an offer was
given to the counsel for AE to furnish security for such losses which
will be suffered by BEPL if the order of status quo is to be continued
but the same was declined.
13. As far as the prima facie of the case is concerned at this stage,
though the stamp papers suggest that same were bought at the same
time but in view of the documents bearing the admitted signatures of
AE, it cannot be said that actual sale consideration is 8.51 crores or
was reduced against payments in cash. Moreover in my view, AE
being itself a party to the illegality alleged, cannot take the said
stand before the Court.
14. As far as the averments of BEPL having surreptitiously
removed the goods to detriment of AE and of AE in-spite of paying
the huge amount of Rs.3.58 crores having not removed single
machinery from the premises is concerned, the same is also prima
facie unbelievable. It was a term of the Agreement that the
machinery shall be permitted to be removed in proportion to the
payments made. AE is not a novice in the business. During the
course of hearing, the counsel for AE on instructions had stated that
AE has annual turnover of over 25 crores. I find it hard to believe
that AE, in spite of having paid the said monies would not have
removed the proportionate machinery. Similarly the reliance by AE
on the invoices by BEPL in favour of third parties is at this stage
prima facie met by the letters of such third parties of having dealt
with AE. It is not disputed that cheques given by AE have bounced.
BEPL in terms of the agreement is entitled to forfeit monies paid till
now and to sell to machinery to others.
15. In the circumstances aforesaid AE on the basis of the
averments in its petition is not found entitled to the interim
measures claimed.
16. As aforesaid, AE neither has prima facie case in its favour nor
will suffer irreparable injury if the machineries are removed and sold
by BEPL. The balance of convenience is also not in favour of AE.
While claims of AE are for monies allegedly paid and damages, if the
machinery is not allowed to be removed, the new project of BEPL
will be held up causing incalculable loss to BEPL.
17. Though AE has not made out a case of securing monies if any
ultimately found due, the senior counsel for BEPL has contended
that the factory premises itself are worth 50 crores and are
unencumbered.
18. OMP No.331/2009 in the circumstances is dismissed and OMP
No. 328/2009 is allowed. AE shall not interfere in the dismantling
and removal of the machinery by BEPL from the premises aforesaid.
19. Needless to add that any observation made herein shall not
affect the determination of the matter on merits during the
arbitration proceedings. Parties are however left to bear their own
costs.
20. The counsel for BEPL states that the expenses incurred in the
commission besides the fee of the commissioner were born by BEPL
and in accordance with the order of the Court AE shall reimburse its
share within 15 days.
IA No. 7884/2009 in 328/2009 and IA NO. 7903/2009 in 331/2009
The petitions having been disposed of, these applications have
become infructuous and are dismissed.
RAJIV SAHAI ENDLAW,J July 09, 2009 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!