Citation : 2009 Latest Caselaw 2535 Del
Judgement Date : 9 July, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Date of Reserve: April 06, 2009
Date of Order: July 09, 2009
+ CS(OS)Nos.2104/96 & 2021/96
% 09.07.2009
ENGG. PROJECTS INDIA LTD. .... Plaintiff
Through : Dr.A.M.Singhvi, Sr. Adv. with
Mr. Jagdeep Kishore, Adv.
Versus
M/S NOOR MOHD. & SONS .... Defendant
Through: Ms. Suruchi Aggarwal with Ms. Rohini Moosa, Advs.
&
ENGG. PROJECTS INDIA LTD. .... Plaintiff
Through : Dr.A.M.Singhvi, Sr. Adv. with
Mr. Jagdeep Kishore, Adv.
Versus
SH.C. RAMA RAO .... Defendant
Through: Ms. Suruchi Aggarwal with Ms. Rohini Moosa, Advs.
JUSTICE SHIV NARAYAN DHINGRA
1. Whether reporters of local papers may be allowed to see the
judgment?
2. To be referred to the reporter or not?
3. Whether judgment should be reported in Digest?
JUDGMENT
1. By this order, I shall dispose of objections filed by
Engineering Projects India Ltd. against the award dated 29th July, 1996
published by sole Arbitrator Sh. C. Ramarao.
2. The brief facts relevant for purpose of deciding this petition
are that the State of Kuwait awarded a contract for construction of SEIF
Palace area building project at Kuwait to M/s. Fujita Corporation of
Japan. M/s. Fujita Corporation in turn awarded civil and electrical
works of the building project to M/s. Engineering Projects India
Ltd(EPI)(plaintiff herein). EPI sub-contracted a part of civil work to M/s.
Noor Mohammad & Sons (NMS), the respondent herein. The sub-
contract was awarded to NMS on 28.4.1976. While the work under this
sub-contract was in progress, supplementary agreement/work orders
were issued by EPI from time to time. In terms of the contract, almost
entire material required for the work was to be supplied by EPI at pre-
agreed rates and the value of the material so supplied was to be
adjusted out of the running bills raised by NMS from time to time. EPI
had initially given and continued to give mobilization advances and
various other advances to NMS from the start of the contract. These
advances were also to be adjusted out of the running bills. NMS was
supposed to raise running bills in respect of the work done and every
bill was to be verified by EPI and after verification payment was to be
made. Out of the each running bill, 5% retention money was to be
retained by EPI. The contract provided for a defect liability period of
one year and all defects were to be cured by NMS free of cost upto 12
months of the completion of the work and the retention money was
payable after this defect liability period was over. EPI was also liable to
deduct income tax in terms of the Income Tax Act out of the
payments/running bills being made to the NMS.
3. It is a case of EPI that NMS had no source of its own to
raise money locally or by borrowing through banks. Under these
circumstances, whenever money was required by NMS the same used
to be paid by EPI as adhoc advances in the interest of the work and to
help NMS to fight its financial difficulties due to low productivity and
low billing. The value of original main contract was KD.21,36,992.412.
There were supplementary agreements namely for Pre-Cast Elements
for KD3.27 lakhs and for Storm Water Drainage work for KD1.54 lakhs,
beside other small work orders of the value of KD2,81,434.65. The
total value of all the works put together was KD.28,99,427.059.
However, these values of the works were estimated values. The
payment was to be made as per the rate agreed between the parties
under the contract in accordance with the actual bill of quantities.
There is no dispute that the running bills were raised on the basis of
measurements of the work done and the rates as agreed between the
parties in respect of different items. The work got completed
sometime in March, 1983 and NMS did not stay back after that. EPI in
1984 wrote a letter to NMs that its books of account show that EPI had
to recover approximately KD.10 lakhs from NMS because of the excess
payments made it in advance. The figure was arrived at by EPI in the
following manner:-
"DETAILS OF ADHOC ADVANCES/PAYMENTS/MISC. RECOVERIES
AMOUNT(KD) AMOUNT(KD)
A. Value of work done(encl 1) 25,36,424.927
B. Deductions/recoveries due against
i) Materials supplied (encl 2) - 10,99,052.352
ii) Concrete supplied (encl 3) - 4,29,807.644
iii) Equipment hire charges (encl 4) - 1,23,439.030
iv) Miscellaneous recoveries including 2,00,648.438
PTAs etc. (encl 5) -
v) Income tax (encl 6) - 31,752.183
vi) Retention Money - 1,23,108.061
vii) Amount released (encl. 7) - 16,52,638.192 36,60,445.900
Amount recoverable (-) 11,24,020.973
C. Retention money available with the 1,23,108.061
claimant - item B(vi) above
Net amount (-) 10,00,912.912
recoverable from the
respondent"
4. Since NMS did not agree to this recovery, EPI referred the
matter for arbitration. Initially one Sh. J.S. Marya was appointed as an
Arbitrator who died after conducting proceedings for some time. Then
the matter came up before the Delhi High Court. NMS raised an issue
that supplementary work orders were not to be treated as part of the
same contract. However, during proceedings pending before this
Court, it was agreed by the parties that the reference of the dispute
raised by both the parties in respect of the main work order and
supplementary work orders be made to one common Arbitrator and
thereafter Mr. C. Ramarao was appointed as the Arbitrator who gave
the award in question. After Mr. C. Ramarao entered into the
reference, revised statement of claim was filed by EPI and counter
claim and rejoinder was filed by NMS. The claims were raised by EPI
on account of mobilization advance of KD.1,40,192/-, equipment
advance of KD.9,094.250, excess of ad hoc advances of
KD.10,00,912.912 and claim for overdrawn material for KD.34,875.570.
Claim no.5 was towards administrative cost for procuring material on
behalf of NMS of KD.61,513.168, claim no.6 for KD.29,258.072 on
account of maintenance expenses, claim no.7 for interest and claim
no. 8 for KD2,89,942.706 on account of delay penalty on the ground
that NMS had not completed the work within the stipulated time.
Claim no. 9 was for costs of arbitration.
5. The counter claims of NMS were as under:
Counter claim no.1 for KD.481,668.00 towards idling of resources upto
July, 1980.
Counter claim no.2 for KD.354,448.00 towards losses and damages
due to work prolonging beyond August, 1980.
Counter claim no.3 for KD.11,72,759.634 towards extra work done by
NMS (This claim had various sub-heads).
Counter claim no. 4 for KD.23,000.000 on account of non-payment
against tools, plant and machineries of NMS taken over by EPI.
Counter claim no. 5 for KD.1,42,400.000 towards loss due to offsite
overheads.
Counter claim no. 6 for KD.2,84,800.000 towards the loss of profit
earning capacity.
Counter claim no. 7, an unspecified claim towards non-release of
money withheld/unpaid as per final bill/retention money.
Counter claim no.8 for KD.378,170.000 against excess recovery of cost
of plant, machinery, material, etc.
Counter claim no. 9 for KD.559,108.034 towards extra cost involved in
re-mobilization of workers in extended period.
Counter claim no.10 for KD.126,500.000 towards excess costs involved
due to labour camp being 35 kilometers away from the work spot.
Counter claim no. 11 for KD.42,028.000 towards difference in cost of
labour supplied to EPI.
Counter claim no.12 for KD.60,834.000 towards non-payment of day
work schedule.
Counter claim no.13 for KD.640,744.00 towards extra cost involved in
engaging labour locally.
Counter claim no. 14 for interest.
6. Above counter claims were in respect of the main works.
NMS also preferred counter claims in respect of Storm Water Drainage
work as under:-
Counter claim no.1 for KD.1,07,642.303 as per letter dated 7.12.80 of
NMS.
Counter claim no. 2 for KD.7,700.000 towards loss of business due to
non-payment by EPI - 5% of the contract cost.
Counter claim no. 3 for KD.97,199.000 for interest.
Counter claim no.4 is an unspecified amount towards unpaid final bills
and release of retention money.
7. The third head of counter claims made by NMS was for Pre-
Cast Elements. Under this head counter claims are as under:-
Counter claim no. 1 for KD.51,670.000 towards idling resources.
Counter claim no.2 for KD.69,790.882 towards extra cost due to delay
beyond May, 1980.
Counter claim no. 3 for KD.284,135.891 towards non-payment of
various works carried out as per EPIs instructions (this claim contains
several sub-heads).
Counter claim no. 4 for KD.15,000.00 towards cost of tools and
machinery taken over by EPI.
Counter claim no. 5 for KD.33,700.00 towards loss due to offsite
overheads.
Counter claim no. 6 for KD.67,580.00 towards loss of profit earning
capacity.
Counter claim no. 7 for an unspecified amount towards non-release of
money withheld/unpaid against the final bill/retention money.
Counter claim no. 8 for interest and
Counter claim no. 9 towards costs of arbitration.
8. The learned Arbitrator allowed the claim of EPI against
mobilization advance, equipment advance and maintenance expenses.
However, it rejected the claim of EPI for recovery of excess adhoc
advances paid to NMS to the tune of KD.10,00,912.912 and on account
of material overdrawn by NMS and administrative charges for material
procured for NMS. It also rejected the claim of penalty for delay. The
Arbitrator allowed the claim of the respondent to the tune of
KD.4,74,29.255 against the non-payment of various items of work
carried out by NMS and also allowed a claim of KD.88,740.00 towards
extra cost involved due to labour camp being 35 kilometers away from
the spot. He also allowed a claim of KD.42,688.00 towards non-
payment of day work schedule bills against main contract.
9. The learned Arbitrator allowed a counter claim of
KD.40,143.034 towards the Storm Water Drainage Work and allowed a
claim of KD.1,56,488.212 towards Pre-Cast Elements Work. The net
result of the award was that the petitioner was to pay a sum of
KD.3,59,057.074 to NMS and interest thereon at the rate of 18% per
annum as allowed by the Arbitrator. EPI had invoked bank guarantee
of NMS after the contract was over since there was no response from
NMS for settling the accounts. The learned Arbitrator also directed the
refund of bank guarantee amount to NMS along with the interest
thereon at the rate of 18% per annum.
10. One of the objections of the petitioner against the award is
that there was an error apparent on the face of the award in
calculating the total value of the work done. It is submitted that the
learned Arbitrator calculated the total value of the work done on the
basis of the income tax deducted at source. The amount of income tax
deducted was KD.31,752.183. The learned Arbitrator concluded that
this amount represented 1% of the value of the work executed. Thus,
the total value of the work executed by the respondent would be
KD.31,75,218.300. It is submitted that the Arbitrator erroneously
assumed that the tax deducted at source under the Income Tax Act,
1961 was only out of the running bills raised by the respondent. It is
submitted that advance tax was liable to be deducted by the petitioner
under Section 194 C (2) of the Income Tax Act at the time of credit of
all sums or payments made to NMS either in cash or by cheque or by
any other mode. The deduction of Income Tax was therefore to be
made even out of the ad hoc advances as well as of the running bills,
which included the value of the material supplied by the petitioner.
The deduction of income tax by no means was relatable to the actual
value of work done by the sub-contractor. The determination of total
value of works is reflected only on preparation of final bills. The total
value of work done could not have been arrived at by reverse
calculations, i.e., multiplying tax deducted by 100 since the income tax
deductions were made from time to time whenever payment was
made to NMS either by way of adhoc advances or by way of material
supplied or towards R.A. bills. Only running bills showed the work
done.
11. It is submitted that out of the each running bill raised by
the respondent 5% retention money was retained and this was a
uniform practice. There was no dispute on the amount of retention
money so retained. The learned Arbitrator, if wanted to calculate the
total value of work on the basis of deductions, then the retention
money was the proper base for reverse calculations. The income tax
deduction could not have been, under any circumstances, a base for
reverse calculation. It is further submitted that the petitioner had
placed sufficient material before learned Arbitrator to show that the
value of the work done by the respondent was of KD25.36 lakhs and
this found support from the fact that the cost of material used in the
work admittedly was of KD15.28 lakhs. It is argued that as per CPWD
Manual, in case of building works, the component of material and
labour are to be taken as 75% and 25% respectively. However, even if
this material and labour ratio is taken as 60%, since 40% labour
component was admitted by NMS, the value of total work would be
KD25.47 lakhs. Petitioner submitted that it was matter of record that
the respondent/NMS had protested during the course of contract
against reduced scope of block work in every building. While the
estimated value of the work was KD28.72 lakhs, the actual value of the
work done was less than the estimated value in view of the reduced
scope and thus the value of total work could not have been more than
KD25.47 lakhs under any circumstances and the learned Arbitrator by
committing an error of reverse calculation on the basis of income tax
deduction, doubled the value of the work done and this was an error
apparent on the face of the award.
12. The other objection raised by the petitioner is that the
learned Arbitrator made an award contrary to the terms of the
contract. The Arbitrator mechanically picked up some large claims and
some small claims out of the given counter claims of NMS and allowed
a sum of KD7.74 lakhs (approximately Rs.9 crores) to the respondent
without any justification, contrary to the terms of the contract. While
the Ministry of Public Works, Kuwait allowed 50% extra payment on
rates of quantities with respect to some of items, the learned Arbitrator
allowed 50% of higher rates to NMS on all the items on the ground of
higher wages to the workers while the workers were employed by NMS
under a contract in India. The Arbitrator also failed to note the correct
labour wages. It is stated while allowing 50% higher wages, the
learned Arbitrator quoted example of EPIs rates in Storm Water
Drainage Works. The Arbitrator did not consider the fact that the
Storm Water Drainage Work was completely underground and hence
higher labour rate was allowed for working in filthy conditions. Even
the BOQ rates in respect of Drainage Work items were higher than the
main contract on this ground. These rates could not have been taken
as a criteria by the Arbitrator and the Arbitrator mis-conducted himself
by allowing 50% extra amount on the ground of higher wages.
13. The petitioner has also submitted that the award of the
learned Arbitrator in respect of various items of counter claims of NMS
was non-speaking award although the learned Arbitrator had agreed to
give reasons during the arbitration proceedings. No justification or
reasons had been given as to why the counter claim had been allowed,
how the figures of amount had been arrived at by the Arbitrator. In
some cases the Arbitrator has given rates much above 150% of the
agreed rates.
14. It is further submitted that the learned Arbitrator
committed grave error by relying upon RA bills submitted by NMS
believing that NMS was submitting RA bills for the work done. It was
pleaded on affidavit before learned Arbitrator that EPI was preparing
RA bills and the same were cross-checked by NMS and then forwarded
for payment to the employer. While the learned Arbitrator disbelieved
the figures/value of the work done as projected by EPI on account of
non-submission of the final bill, the learned Arbitrator wrongly
presumed that the NMS was preparing RA bills and the figure as
projected by NMS was corrected.
15. In response to the objections taken by the petitioner, it is
submitted by the respondent that the award does not suffer from any
infirmity or illegality and the learned Arbitrator has passed its award on
the basis of evidence and material placed before him. The objections
raised by the petitioner were vexatious and frivolous.
16. Regarding total value of the work done, the respondent has
supported the method of calculation adopted by the learned
Arbitrator and has stated that the Arbitrator rightly came to conclusion
that the total value of the work done was KD39,77,257.955. There
was no misconduct on the part of the Arbitrator. The learned Arbitrator
dealt with each claim and counter claim carefully. He was an
experienced person, having knowledge of the technical aspects and
the award of a technical person should not be interfered with by the
Court so lightly. It is stated that the learned Arbitrator has specifically
recorded that the claimant and the respondent both feel that income
tax deduction from RA bills was KD31,752.183. If the income tax
deduction from the RA bills was KD31,752.183, there was no reason to
disagree that the total work would be 100 times of the income tax
deducted since income tax was only 1% and the Arbitrator rightly
came to conclusion that the total work under main contract was for
KD31,75,218.300. It is also denied that the Arbitrator had not kept the
terms and conditions of the contract in mind while adjudicating the
dispute. The Arbitrator was very well aware of the terms and the
conditions of the contract.
17. Learned counsel for the respondent submitted that this
Court does not act as a Court of appeal while considering the
objections against the award. Since this award was under Arbitration
Act, 1940, the scope of interference in the award was limited and the
error apparent on the face of the award must be such which goes to
the root of the award. However, every error on the face of the award
would not render the award null and void.
18. The main issue before the Arbitrator was as to what was
the total value of the work done by NMS. The Arbitrator observed that
the final bills were not finalized by March, 1983 and the number of
advances were given to NMS spreading over 4 years and odd. In
March, 1983 EPI had written to NMS that there persons in Kuwait were
now of little use in finalizing their claims and their bills would be
finalized on the basis of built-up drawings, as per record available in
New Delhi without any difficulty. The respondent's stand before the
learned Arbitrator was that it was not possible to settle the final
account on the basis of built-up drawings, running bills, advances,
materials, etc. During the pendency of the arbitration proceedings
(before the earlier Arbitrator) respondent (NMS) had made an
application for production of documents by EPI and EPI sent its
representative to Kuwait to collect the documents as ordered. The
learned Arbitrator observed that on EPI producing various documents
as demanded he had offered to give a speaking award provided all
documents were made available to him. But EPI could not make all
documents as demanded by him available to him. He therefore had to
adopt some method to find out the total value of the work done by the
respondent.
19. The value of the work done by the respondent as per EPIs
figure was as under:-
S.No. Particulars Final Figures as As per Audited shown b y EPI P-30 figures at P-21 of of Folder-10 Folder No.12 as on 31-3-1982 (1) (2) (3)
(KD) (KD)
1 MDFA Building 9,94,927.948 10,53,269.079
2 ESP Building 2,57,499.459 2,68,665.000
3 CDM Building 3,44,021.566 3,69,610.430
4 AC Centre 63,252.419 83,175.547 Building
20. The learned Arbitrator found that there was difference in
the initial figures and audited figures of EPI (as seen in the above
table) and observed that EPI did not give any specific argument for
higher figures of work done shown in the audited accounts. The
Arbitrator also observed that the Ministry of Public Works, Kuwait vide
its order dated 22.12.81 had sanctioned 50% extra over BOQ rates and
these were not allowed by EPI originally but later it agreed to pay extra
to NMS. The Arbitrator also observed that regarding Pre-Cast Element
contract, EPI had not supplied him the schedule of quantities of the
agreement. However, NMS had supplied him a copy of 28th running bill
and according to NMS the work done was KD3,99,583.00 while the
work done as per final bill presented before him was of
KD3,44,835.640. Looking at the contradictions in the amount of total
work done between the figures of petitioner and the respondent, the
Arbitrator found that since 1% income tax had been deducted of the
value of the work done and income tax deduction made by EPI was
KD31,752.183, the total value of work done must have been
KD31,75,218.30, which he considered, tallied with the work orders of
all the agreements and 42 work orders. He further added to this the
work done of the value of KD8,02,039 and arrived at a value of work
done by NMS as KD39,77,257.955. It is this figure which is the bone of
contention, apart from other objections on different items.
21. Income tax deduction was done by the petitioner under
Section 194 C(2) which reads as under:-
"(2) Any person (being a contractor and not being an individual or a Hindu undivided family), responsible for paying any sum to any resident (hereafter in this section
referred to as the sub-contractor) in pursuance of a contract with the sub-contractor for carrying out, or for the supply of labour for carrying out, the whole or any part of the work undertaken by the contractor or for supplying whether wholly or partly any labour which the contractor has undertaken to supply shall, at the time of credit of such sum to the account of the sub-contractor or at the time of payment thereof in cash or by issue of a cheque or draft or by any other mode, whichever is earlier, deduct an amount equal to one per cent of such sum as income-tax on income comprised therein.
Explanation I : For the purposes of sub-section (2), the expression "contractor" shall also include a contractor who is carrying out any work (including supply of labour for carrying out any work) in pursuance of a contract between the contractor and the Government of a foreign State or a foreign enterprise or any association or body established outside India.
Explanation II : For the purposes of this section, where any sum referred to in sub-section (1) or sub-section (2) is credited to any account, whether called "Suspense account" or by any other name, in the books of account of the person liable to pay such income, such crediting shall be deemed to be credit of such income to the account of the payee and the provisions of this section shall apply accordingly."
22. It is apparent from reading of this provision that tax is to be
deducted whenever any payment is credited to the account of the sub-
contractor or any payment is made in cash or by cheque. Explanation
2 makes it further clear that even if the amount is credited to the
suspense account or account by any other name in the books of
accounts of the sub-contractor, income tax at 1% is liable to be
deducted. Thus deduction of 1% of tax was mandatorily to be made by
the petitioner out of all payments made to the respondent whether of
adhoc advances or by way of supply of material etc. It was for the
respondent to file return for the concerned years with the assessing
officer, if the deductions were more than the tax due, to claim refund.
It is not the case of the respondent that no income tax deduction was
made from the respondent when advances were given to him or when
ad hoc payments were made. The petitioner in this case had made ad
hoc payments to the respondent of KD16,52,638.192 and supplied
material to the tune of KD10,99,052.352 and supplied concrete to the
tune of KD4,24,807.664. These 3 figures together make more than KD
31 lakhs and would have necessitated deduction of an income tax
amount of KD31,752.183.
23. The question arises whether amount of income tax
deducted reflected one per cent of the work done. If the respondent
had been made payments of the running bills and tax had been
deducted only from the running bills, the income tax deducted would
have reflected 1% of the work done. But here the sub-contractor was
dependent upon the petitioner for all its finances and had neither
raised funds nor had capacity to raise funds locally from Kuwait. The
evidence shows that NMS was depending upon the petitioner for all its
requirements of finance and the petitioner had been making advances
irrespective of the work done, after deducting 1% tax, thus the tax
deduction could not correlate to the total amount of work done. It
would, in fact, reflect the total payment made to the respondent,
irrespective of the work done. If any figure had direct relationship with
the work done it was retention money or the value of material used for
the work. The retention money was retained by the petitioner out of
each running bill at the rate of 5% of the bill. Since the respondent
was not to purchase its own material and most of the material was
supplied by the petitioner, the other direct element which had
relationship with the work done was the material supplied. The
learned Arbitrator ignored both the elements which were having direct
relationship with the work done and choose to calculate the total
amount of work done on the basis of income tax deduction made by
the petitioner. I consider that this method of calculating the total work
done by the learned Arbitrator was fallacious, totally whimsical and
reflects an error apparent on the face of the award which goes to the
root of the entire award. Consider, for example a contractor who
received advance before the start of work and thereafter on one or the
other pretext, instead of doing the assigned work, spend money on
shopping and other things and comes back to India, leaving the work.
Would the income tax deducted reflect the work done by him. I
consider that since EPI, as per law, was liable to deduct 1% of the
amount paid by it, as tax, irrespective of the fact whether respondent
had done the work or not, it could not be presumed by the learned
Arbitrator that the respondent had done work of the amount tax
deducted multiplied by hundred. Under no stretch of imagination, the
Arbitrator could have come to conclusion that merely because the
petitioner had deducted 1% tax of all the amounts it paid to the
respondent, the work done by respondent was also of equivalent
amount. The work done and the amount paid were not co-related in
this case. The amount was being paid as advance because of the
circumstances that respondent had landed in Kuwait to undertake the
work. Even for landing in Kuwait the mobilization advance was given
by the petitioner to the respondent. I therefore come to conclusion
that the award passed by the learned Arbitrator regarding the value of
the work done stood vitiated because of the error apparent on the face
of the award, i.e., the value of work done was calculated on the basis
of income tax deducted by the petitioner. The income tax deductions
only reflected the money paid either by way of cash or by kind
(material etc.) to the respondent. This income tax deduction could not
have been reflected the work done. The work done could have been
calculated by the Arbitrator either on the basis of material used by
using ratio 60:40; 60% for cost of material, 40% for cost of labour or
the work done could have been calculated on the basis of retention
money which was 5% of the total amount of all running bills. If this
had been multiplied by 20, the figure of work done would have been
correctly arrived at.
24. The learned Arbitrator while discussing the value of the
work done did not rely upon the final figures of petitioner on the
ground that there was difference in the final figures as shown by the
petitioner and the audited figures of the petitioner as given in the chart
below:
S.No. Particulars Final Figures as As per Audited shown b y EPI P-30 figures at P-21 of of Folder-10 Folder No.12 as on 31-3-1982 (1) (2) (3)
(KD) (KD)
1 MDFA Building 9,94,927.948 10,53,269.079
2 ESP Building 2,57,499.459 2,68,665.000
3 CDM Building 3,44,021.566 3,69,610.430
4 AC Centre 63,252.419 83,175.547 Building
25. Auditing is done in all public limited companies to
crosscheck the accounting of the accounts department and to see that
the bills have been prepared in accordance with the contract. If the
auditors of the petitioner had found some discrepancy in the
accounting of the petitioner and the final figure arrived at by the
auditors of the petitioner was more than the figures as prepared by the
accounts department of the petitioner, that rather shows that the
auditors of the petitioner acted in a fair manner and the Arbitrator
should have relied upon the figures as arrived at by the auditors of the
petitioner instead of rejecting the figures on this ground. Award also
shows that the petitioner, during proceedings, had conceded about
payment of 50 per cent extra amount on certain quantities as
sanctioned by Under Secretary's order dated 22.12.1981 in respect of
guard headquarter building, MOFA variation and MOFA New Gate. The
learned Arbitrator had a grievance that he was not furnished all the
documents as required to determine the exact value of the work done.
Therefore, he had no option but to calculate the work done on the
basis of income tax deduction. This was a grave error apparent on the
face of the award. The learned Arbitrator had sufficient material
before him like retention money retained by the petitioner, building
material supplied by the petitioner, to come at a proper value of the
work done by the respondent instead of adopting the method of
reverse calculation on the basis of income tax deduction despite
knowing that the income tax was deducted on all advances paid
whether against the running bills or ad hoc advances given to the
respondent to facilitate the doing of work irrespective of the quantum
of the work.
26. The total value of the main work was of KD21,36,942.412
and in respect of Pre-Cast Elements it was KD3,27,000.000 and in
respect of Storm Water Drainage work it was KD1,54,000.000 and in
respect of other work orders it was thus KD2,53,886.128. The total
value of the orders thus was KD28,71,828.540. As per petitioner the
total contract value even after including the supplementary orders was
of KD28,99,427.056. The learned Arbitrator on the basis of income tax
deduction first concluded that the work done was of KD31,75,218.000
and then added to it further work of KD8,02,039 and thus concluded
that the total work done was of KD39,77,257.955.
27. Thus due to this error apparent on the award, the learned
Arbitrator calculated the value of work done more by about
KD10,78,830.896 from the total awarded work. Whereas there had
been no material on record to show that the respondent had done work
more than the work awarded to him.
28. Due to this error which crept into the award, the entire
award stands vitiated. On the basis of this calculation alone the
petitioner was burdened with an additional amount payable to the
respondent to the tune of KD5,38,060.000 after deducting
KD35,62,305.620 of which the advances, services and material had
already been supplied by the petitioner to the respondent. The learned
Arbitrator wrongly disallowed the claim of the petitioner regarding
refund of the excess advances paid to the respondent on the basis of
reverse calculation making income tax as the base.
29. It is settled law that an Arbitrator is a creature of contract
and is bound by the contract between the parties. He cannot write a
new contract between the parties. The contract between the parties is
contained in the document signed between the parties or the
correspondence which is entered into between the parties during the
continuation of the contract. The learned Arbitrator awarded a sum of
KD88,741.00 to the respondent under counter claim no.10 on the
ground that the respondent had to transport labour from labour camps
to site. A perusal of Clause 13 of the contract between the parties
would show that the respondent only was to make necessary
arrangements for labour and staff required for the execution of work
and it was the respondent who was to pay his labour and staff not only
for doing work but other expenses such as transportation, etc. The
petitioner's responsibility was only to provide a site for construction of
temporary labour residence. It was not provided in the contract that
the petitioner shall give this site for construction of temporary
residence near the site of the work. Rather the contract between the
petitioner and the employer specifically provided that no labour
residence, temporary or permanent, shall be near the site or within the
site of work. In view of the specific provisions in the contract that no
labour residence was to be near the site of the work or within the site
of the work, the petitioner could have provided to the respondent only
that site which was provided to it by the employer. The
correspondence between the parties shows that the respondent had
raised this issue of labour site being about 35 kilometers away from
the worksite and wanted the petitioner to bear the charges of drivers.
The petitioner had only agreed for sympathetic consideration of this
demand. The correspondence does not show that the petitioner had
agreed for payment of extra charges for drivers. However, the learned
Arbitrator went further and passed an award holding that the normally
the site for labour camp is provided either at the worksite itself or if the
building was government building, considering the security involved,
near the office building itself. The learned Arbitrator totally ignored
the contract between the petitioner and respondent that the labour
camp was not to be situated within the building or near the building.
The award of this amount is contrary to the terms and conditions of the
contract.
30. The learned Arbitrator awarded a sum of KD37,533.249
against counter claim no. 3 (sub-claim no.5) in respect of
manufacturing and affixing of Teak Grill works. A letter dated 15th
December, 1980 from the respondent to the petitioner which is on
record of the Arbitrator would show that the respondent submitted to
the petitioner that the rates of this item quoted by it were wrongly
quoted rates and the items were not workable within the quoted rates.
He wanted petitioner to revise the quoted rates. The petitioner had
not agreed to revise the quoted rates. Thus, the work was required to
be done in terms of the contract only on the quoted rates. The quoted
rates were provided in bills of quantities as signed between the parties
in respect of Teak Grills. However, the learned Arbitrator ignoring the
contractual rates awarded additional amount of KD37,533.000.
Obviously, the learned Arbitrator wrote a new contract between the
parties awarding a new rate to the respondent for manufacturing and
affixing of Teak Grills. It is settled law that the Arbitrator cannot write
a new contract between the parties and is bound by the contract
already executed between the parties.
31. The learned Arbitrator awarded 50% extra amount towards
the work done prior to 1981 to the respondent under counter claim
no.3 sub-claim nos. 1, 3, 6, 13, 19, 118 and 122. The petitioner had
got 50% additional rate for some of the quantities vide an order of
Under-Secretary dated 22nd December, 1981. Vide letter dated 30th
May, 1982, the petitioner intimated the respondent that since it would
be getting revised rates at the rate of 1.5 times of old rates with MPD
for new work in terms of Under-Secretary's order dated 22nd December,
1981, it shall be increasing the rates of bill of quantities in the same
proportion for all similar items for respondent also. It is obvious that
these additional rates were to be given by the petitioner to respondent
in respect of the new gate building, since petitioner was receiving
additional rates for this work only. However, the learned Arbitrator
allowed additional rates in respect of above stated items to which it
was not applicable. The Arbitrator therefore acted contrary to the
contract between the parties. The Arbitrator had no authority to
increase the rate of bill of quantities of his own. He could have
awarded increased rates only in respect of those items about which the
petitioner had got additional rates from the employer and not in
respect of those items about which the petitioner had not got the
increased rates. The petitioner has placed on record its
correspondence with the respondent regarding increased rates in
respect of various items. This shows that the petitioner passed on the
additional rates to the respondent in respect of those items for which it
got the additional rates. Apart from those items for which petitioner
had got the additional rates from employer, the Arbitrator could not
have increased the rates of bill of quantities. The Arbitrator allowed
counter claim of additional 50% for above items only on the ground
that 50% additional rate was being allowed over bill of quantities to
petitioner in view of sanction under MPW, Under-Secretary's order,
without considering that this sanction was not in respect of all items
and was not for the period prior to December, 1981.
32. However, the learned Arbitrator while dealing with the
counter claim no. 3 sub-claim nos.72 and 116 allowed more than 50%
of the additional cost amount to the claimant, while only 50% could
have been allowed in terms of the letter of Under-Secretary. In case of
sub-claim no.72 (claim no. 3), the Arbitrator awarded an additional
amount of KD15,230,00. The amount already paid was KD12,738.00.
50% of this would amount to KD6,369.00 while the Arbitrator awarded
KD15,238,861.00 amount. In sub claim no.116 (claim No.3), the
Arbitrator awarded KD46,295.00. The amount already paid was
KD57,777.00. 50% of this would have been KD28,888.00. The
Arbitrator thus awarded KD17,407.00 extra. These are all errors
apparent on record.
33. A perusal of award would show that instead of calculating
50% extra, the learned Arbitrator has relied upon the abstract cost of
estimate furnished by the respondent. The Arbitrator was not writing a
new contract between the parties on the basis of fresh costing to be
done by the respondent. The respondent was free to do costing before
tendering for the contract. The respondent had no liberty to do re-
casting while arguing counter claims before the Arbitrator. Since 50%
additional amount was allowed by the Under-Secretary to the
petitioner which was to be passed on to the respondent, the Arbitrator
could have only allowed 50% on the amount already paid. Thus, award
on these items is contrary to the contract.
34. It was pleaded before the Arbitrator that since the
Arbitrator was an Engineer he need not go into the various clauses of
the contract since the conditions of the contract and sub-conditions of
the contract in such type of contracts were known to him. The
Arbitrator recorded that he therefore would not like to go to the
respective clauses. I consider that the learned Arbitrator, despite
being told by the respondent that he was not required to go into the
various clauses of contract, should have considered it as his duty to
pass an award in accordance with the contract and not ignoring the
clauses of the contract.
35. In view of my above discussion, the counter claim no.
3(sub-claim no. 5), counter claim no. 3(sub-claim nos. 1, 3, 6, 13, 19,
118 & 122) and part of the counter claim no. 3 (sub-claim nos. 72 &
116) were awarded contrary to the contract and not tenable.
36. The learned Arbitrator had allowed the claim of
KD1,42,651.000 (mobilization advance), KD9,094.250(equipment
advance) and KD29,258.072(maintenance expenses) in favour of the
petitioner. However, the learned Arbitrator wrongly rejected the claim
of the petitioner for refund of excess ad hoc advances on the basis of
an error in calculating the total work done as discussed above. The
learned Arbitrator allowed the counter claims of KD4,74,029.255 of the
respondent on the basis of the same calculation of the work done
which could not have been allowed by the learned Arbitrator. As
discussed above amounts of KD88,741.000 and KD37,533.000 were
wrongly allowed in respect of counter claim nos. 3 and 10, contrary to
the contract, apart from allowing 50 per cent excess payment in
respect of various items as discussed in Para 23. If counter claims
allowed despite being contrary to contract and the amounts allowed on
the basis of wrongful calculation made in respect of total work done
are considered, the net result would be that EPI will have not to pay to
the respondent any amount and rather EPI would have to recover some
amount from the respondent. However, since this Court had not
ventured into the area as to what should the award had been, I
consider it would not be proper to direct the respondent to pay any
amount to the petitioner.
37. In view of my above discussion, I consider that the award
suffers from errors apparent on the face of it as discussed above. Part
of the award is also contrary to the contract between the parties. The
award is liable to be set aside on these grounds and is hereby set
aside.
July 09, 2009 SHIV NARAYAN DHINGRA J. ak
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!