Citation : 2009 Latest Caselaw 2524 Del
Judgement Date : 8 July, 2009
* HIGH COURT OF DELHI : NEW DELHI
+ OMP No.10/2006
Reserved on: 19th February, 2009
% Decided on: 8th July, 2009
Bharat Sanchar Nigam Ltd. ...Petitioner
Through : Mr. Yashwant Das, Sr. Adv. with
Mr. Sukumar Pattjoshi and
Mr. S.K. Dubey, Advs.
Versus
Hughes Networks Systems ....Respondents
Through : Mr. Arvind Nigam, Sr. Adv. with
Mr. Dhamesh Misra and Mr. Ritesh
Sharma, Advs.
Coram:
HON'BLE MR. JUSTICE MANMOHAN SINGH
1. Whether the Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported Yes
in the Digest?
MANMOHAN SINGH, J.
1. The Petitioners herein filed an application under Section 34
of the Arbitration and Conciliation Act, 1996 challenging the impugned
award dated 16th September, 2005.
2. The brief facts of the case are that the objector/petitioner
floated a tender enquiry bearing no.15-44/92-MMD inviting offers for
supply of 64 kbps TDM-TDMA (VSAT) Data Network Equipment. The
offer of the respondent was accepted by the Petitioner and an advance
purchase order dated 27th September, 1994 was issued in favour of the
respondent.
3. The respondent furnished a performance security in the form
of a bank guarantee dated October 7, 1994 bearing No.4558 for a sum of
US $ 4,74,092 issued by Citi Bank, New Delhi.
4. The Petitioner issued a Purchase Order dated 28 th November,
1994 bearing no. 15-44/92-MMD/VOL-II for procurement of 64 kbps
TDM-TDMA (VSAT) Data Network Equipment in favour of the
respondent.
5. Under Clause 14 of the Purchase Order, the delivery of goods
had to commence within three months and was to be completed within
six months from the date of opening the operable Letter of Credit. The
same was issued by the Bank of India on 3 rd January, 1995. The goods
were delivered as per Clause 14 on 8th September, 1995 by putting them
on board and as per Clause 13 invoices and shipping document airway
bills were submitted to D.O.T. on 25 th September, 1995 i.e. within the
extended delivery period specified by the Petitioner.
6. The goods reached the site on 25 th November, 1995 and were
installed by 3rd December, 1995. The Petitioner started acceptance
testing and various defects were pointed out in D.O.T.‟s letter dated 12 th
February, 1996 as a result of these inspections.
7. The Petitioner claimed that certain equipment was either
defective as per specification. It also claimed that the Respondent
accepted the said deficiencies and agreed to remedy these deficiencies at
its own costs. The Respondent, on the other hand, claimed that the
Petitioner demanded substitution of goods beyond specification and also
sought supply of additional equipment beyond the scope of supply. The
Respondent further claimed that it agreed to do the above said for which
the Petitioner is liable to make payment.
8. The Petitioner submits that as per clause 14.9, if the supplier
fails to deliver any or all of the goods or perform the services within the
time period(s) specified in the Contact, the purchaser shall deduct from
the contract price a total of 2% of the delivered price of the delayed
goods or unperformed services for each month of delay until actual
delivery of performance. Since the billing software was delivered after
the contracted period of 3 months, the petitioner after adjusting an
outstanding bill of Rs. 30,00,540/- of the Respondent from Rs.
46,94,044/- which included the said liquidated damages amounting to
Rs. 32,94,909/-, demanded Rs.16,93,504/- from the respondent by a
letter dated 21st January, 2000. By letter dated January 9, 2003 the
petitioner revised and enhanced the earlier demand of liquidated
damages from Rs. 32, 94,909/- to Rs. 82,37,000/- (5% of the contract
value) and after adjusting certain payments, made a demand for an
amount of Rs. 66,35,595/-. Due to disputes with regard to the payment
of liquidated damages and despite various letters by the petitioner to the
respondent as regards the same, the same were not paid and the
respondent sent a legal notice dated February 4, 2003 to the petitioner.
9. Before the petitioner could take any action, vide letter dated
20th February, 2003 the respondent appointed J. S.S. Chadha as its
nominee Arbitrator and by letter dated 16 th June, 2003 the petitioner
appointed Sh. S.K. Sahrma as its nominee Arbitrator who appointed J.
B.N. Kirpal, former Chief Justice of India as Presiding Arbitrator in
consonance with Section 11(3) of the Arbitration & Conciliation Act,
1996 (hereinafter referred to as the „Act‟).
10. Claim Nos.6 to 13 & 15 of the claimants along with counter-
claim Nos. 1, 4, 5 6 & 8 of petitioners herein were dealt with in the
impugned award passed by the Arbitral Tribunal dated 16th September,
2005.
11. The Petitioners contend that the Arbitral Tribunal has erred
in deciding that the matter was an arbitrable dispute as the disputes
submitted were not arbitral as the same had either been waived or had
not been raised at an earlier appropriate stage by the respondent.
Further, even if it was accepted for the sake of argument that they were
arbitral, they were still at the outset barred by limitation.
12. The Petitioners submit that as per Clause 14.9 Part I of the
Purchase Order they are entitled to liquidated damages from the
respondents as there was delay in supply of Data Software which
affected commercial use of the equipment. They further submit that the
said Clause 14.9 is outside the purview of the arbitration clause.
13. The Petitioners also submit that the Arbitral Tribunal,
without any documentary basis on the record, has come to the
conclusion that the respondent had four instead of three months for
delivery of billing software from the date of supply of tariff structure
and hence there is no delay on part of the respondent.
14. The Petitioners state that the Arbitral Tribunal has
erroneously come to the conclusion that there has been no delay in the
performance of the contract and that there has been no pleading with
respect to the liquidated damages on behalf of the Petitioners. The
Petitioners submit that the Arbitral Tribunal has erred in awarding
Rs.25,69,255/- under Claim No.5 to the respondent as this claim has
been awarded only on the basis of an alleged acknowledgment by the
Petitioners.
15. The respondent submits that an arbitral award made by an
Arbitrator is not open to challenge on the ground that the arbitrator on
interpreting certain documents, evidence and the contract etc. has
reached a certain conclusion.
16. The respondent also submits that this court is not a court of
appeal and hence it ought not to interfere with the findings of fact and
construction of clauses of the contract. The respondent claims that it is
well settled that on appreciation of the facts of the case, if more than one
view is probable and the arbitrator has taken a particular view, then this
Court may not adopt another view by way of which it can interfere with
the award.
17. The respondent avers that the objections made by the
Petitioners in the application under Section 34 of the Act do not fall
under any of the grounds of Section 34 of the Act and are thus liable to
be rejected.
18. The respondent states that the arbitration clause of the
Purchase Order, i.e. Clause 21, is very wide providing for adjudication
of all disputes touching the agreement including the operation and
construction thereof as also the rights, duties and liabilities of the
parties. Before the Learned Arbitrators, the Petitioner did not once raise
the objection that Clause 14.9 Part I was outside the purview of the
Arbitration Clause.
19. The respondent submits that ground No.2 of the objections is
in the nature of memorandum of appeal and as such the conclusion of
the Learned Arbitrators is not to be interfered with as the matters are
within the exclusive domain of the arbitrators.
20. During arguments, various objections were raised by the
petitioner against the arbitral award. The first of these is that the Arbitral
Tribunal was wrong in construing the terms of the contract as providing
four months time from the date of receipt of the tariff structure for the
development and supply of billing software. The submission that the
time period for development and supply of billing software was three
months only is disputed as incorrect and misconceived by the
respondent. The basis for the demand of liquidated damages is the
alleged delay of 18 days by the respondent in providing the billing
software. As it is, prior to 21st January, 2000 there was no demand for
liquidated damages and a clean certificate was determined wherein
respondent was not held liable for such damages. It appears that the
Learned Tribunal has rightly constructed the relevant terms, i.e.
Clause(s) 11.4, 11.5 and 14.4 of the contract, which are as follows :
a) Clause 11.4 as per which the respondent had to develop and give billing software to the Petitioner within three months of initial delivery of the goods;
b) Clause 11.5 as per which the Petitioner was to provide the tariff structure to the respondent within two months of opening of the Letter of Credit;
c) Clause 14.4 as per which the initial delivery of the goods was to commence within three months of opening of the Letter of Credit and to be completed till three months thereafter.
21. In view of the above-stated clauses, contractually there was
one month prior to and three months after initial delivery of the goods
which were available to the respondent. Further, due to the 15 month
delay on the Petitioner‟s part, time was set at large and had ceased to be
of essence. Keeping all the above-mentioned circumstances in
consideration, I find that the Learned Tribunal has correctly carried out
finding of this fact. Further, this finding of fact by the Arbitral Tribunal
that time was set at large due to the Petitioner‟s 15 month delay has not
been challenged either in the objection petition or during arguments. I
am of the considered opinion that time had indeed ceased to be of
essence and hence, liquidated damages cannot be demanded.
22. The second objection taken up by the Petitioner is that the
respondent has admitted its liability in letter dated 2 nd March, 2000. It is
to be noted that the respondent was being asked to keep the bank
guarantee of USD 474,092 alive though the performance, for which it
was actually given, was long over. In the said letter dated 2 nd March,
2000 the respondent made no admission of liability as the statement was
made without prejudice and was subject to adjudication as to the same.
The bank guarantee was to be released pending adjudication. The said
letter ought to be read in this context. I am of the opinion that the
Arbitral Tribunal has assessed this material correctly.
23. The third objection of the Petitioner is that the respondent
admitted its liability with regard to liquidated damages in the letter
dated 26th June, 1999. However, it appears that the said letter itself
states that Goods Item A to D were supplied within time. In fact, it was
the Petitioner who pleaded that the demand for liquidated damages was
due to late supply of the billing software by 18 days. In view of the
statements above, the delay of 18 days as a basis for demanding
liquidated damages is not available to the Petitioner as the respondent
has four months to complete his side of the contract and in any event,
time had ceased to be of essence. In light of these considerations, I find
that neither was there any delay nor any admission of liability as regards
the liquidated damages.
24. The fourth objection of the Petitioner is that the respondent‟s
claim for recovery of payment of bill against its services is time barred.
It appears that on 20th August, 1998 the Petitioner admitted that a
payment of Rs.30,00,500/- was due to the respondent against service
already carried out. The same was again admitted on 21 st January, 2000
and on 9th January, 2003, but both times, the Petitioner stated that it
wished to adjust the amount. It was on 4 th February, 2003 that
arbitration proceedings were initiated by the respondents. Therefore,
under Section 18 of the Limitation Act, 1963 time began to run from the
date of admission of liability and hence the Arbitral Tribunal‟s finding
that the claim was well within the limitation period is clear and correct.
25. The last objection taken up by the Petitioner that the arbitral
award is against public policy is erroneous and misconceived as there is
no question or issue of public policy that has arisen as regards the facts
of the present case. The award is based on considered appreciation of
material, assessment of evidence and construction and interpretation of
the terms of the contract between the parties.
26. In my view, the scope of interference by this Court with an
arbitrator's award under Section 34 of the Arbitration and Conciliation
Act, 1996 has been extensively dealt with by the Hon'ble Supreme
Court in Oil and Natural Gas Corporation Ltd. v. Saw Pipes Ltd.
(2003) 5 SCC 705. The relevant observations of the Supreme Court in
the said judgment are reproduced hereinbelow:
"31. Hence, in our view in addition to narrower meaning given to the term 'public policy' in Renusagar's case it is required to be held that the award could be set aside if it is patently illegal. The result would be - award could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
XXX XXX XXX
74. In the result, it is held that:
A. (1) The court can set aside the arbitral award under Section 34(2) of the Act if the party making the application furnishes proof that:
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration.
(2) The court may set aside the award:
(i) (a) if the composition of the Arbitral Tribunal was not in accordance with the agreement of the parties,
(b) failing such agreement, the composition of the Arbitral Tribunal was not in accordance with Part I of the Act.
(ii) if the arbitral procedure was not in accordance with :
(a) the agreement of the parties, or
(b) failing such agreement, the arbitral procedure was not in accordance with Part I of the Act.
However, exception for setting aside the award on the ground of composition of arbitral tribunal or illegality of arbitral procedure is that the agreement should not be in conflict with the provisions of Part I of the Act from which parties cannot derogate.
(c) If the award passed by the Arbitral Tribunal is in contravention of the provisions of the Act or any other substantive law governing the parties or is against the terms of the contract.
(3) The award could be set aside if it is against the public policy of India, that is to say, if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality; or
(d) if it is patently illegal.
(4) It could be challenged:
(a) as provided under Section 13(5); and
(b) Section 16(6) of the Act."
27. The approach in Oil and Natural Gas Corporation Ltd. v. Saw
Pipes Ltd. (supra) has been upheld and followed by the Apex Court in
State of Rajasthan and Ors. v. Basant Nahata, (2005) 12 SCC 77
and Hindustan Zinc Ltd. v. Friends Coal Carbonisation, 2007 (1)
SCALE 1.
28. It is a settled position in law that the Court while exercising
jurisdiction under Section 34 of the Act does not sit as a court of appeal
to re-assess the material, evidence and the terms of the contract assessed
and interpreted by the arbitrators. It is further a settled position in law
that the court while exercising jurisdiction under Section 34 of the Act
would not substitute its opinion for that of the arbitrators.
29. In view of the settled principles, I do not find any patent
illegality in the award as the award is not against any of the principles of
the law as enunciated by the Hon‟ble Apex Court. The grounds for
objections under Section 34 of the Arbitration and Conciliation Act,
1996 are limited. The objections ought to fall strictly within the four
corners of Section 34 of the said Act. I find that the petitioner has not
urged any valid ground within the meaning of Section 34 of the Act on
which an award is liable to be set aside. Therefore, the petition for
setting aside the award is liable to be rejected and dismissed.
No costs.
MANMOHAN SINGH, J JULY 08, 2009 nn
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!