Citation : 2009 Latest Caselaw 2519 Del
Judgement Date : 8 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CS(OS)1887A/1996.
% Date of decision:08.07.2009
M/S ANANT RAJ AGENCIES ....... Petitioner
Through: Mr. Harish Malhotra, Sr. Advocate with
Mr. Uttam Datt & Ms. Meenakshi,
Advocates.
Versus
DELHI DEVELOPMENT AUTHORITY & ANR..... Respondents
Through: Mr. D.S. Mehandru with Ms. Alpana
Pandey, Advocates.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. The petitioner had filed a petition under Sections 14 & 17 of
the Arbitration Act, 1940 inter-alia for filing of the arbitral award
dated 26th July, 1996 in this court and for making the same a rule of
the court. Upon the arbitral award being filed in this court and
notice thereof being issued, I.A. No.12811/1996 under Sections 30 &
33 of the Act was filed by the respondent DDA. No objections have
been preferred by the petitioner to the award. Upon completion of
pleadings in the objections preferred by DDA, the usual issues were
framed on 11th August, 1997.
2. Disputes and differences had arisen out of the contract for
construction of 448 EWS Houses in Block-G, Pockets 12 to 15,
Rohini, Delhi. The objections preferred by DDA are hereafter taken
up in seriatim as in the objection petition.
3. Re: Deduction of Rs.40,540.39p by DDA from the final bill with respect to items 1.1 to 12.6.
a) The award in para 4 thereof records that no reason for this
deduction had been given by DDA and DDA before the
Arbitrator also said nothing about this short payment. The
Arbitrator thus for the reason of DDA having failed to give
any justification for deduction thereof allowed the said
payment to the petitioner.
b) The objection of DDA merely is that according to Clause 25
A this was an excepted matter, as the decision of the Supdt.
Engineer in this behalf is final and thus the award is outside
the scope of arbitration. The counsel for DDA has along
with a brief synopsis dated 15th January, 2007 placed on
record a tabulation with respect to the various claims,
award thereon and the objections of DDA thereto. However,
therein also I do not find any reference to the award in the
said sum. No arguments also have been addressed on the
same.
c) A perusal of the agreement shows that Clause 25 A inter-
alia provides that the decision of Supdt. Engineer regarding
the quantum of reduction as well as justification thereof in
respect of rates of substandard work which may be decided
to be accepted will be final and would not be open to
arbitration. DDA has in its objections neither pleaded nor
shown that it had before the Arbitrator pleaded or shown
that the said deduction was within the ambit of Clause 25 A
or on account of substandard work or had the approval of
the Supdt. Engineer. Without the same being pleaded or
shown, no error on the face of the award or misconduct can
be found. Even before this court nothing was shown as
aforesaid. Without the contention having been considered
before the Arbitrator of as to whether the said deduction
was within the ambit of Clause 25 A or not, the same is not
entertainable by this court.
The objection is dismissed.
4. Re: Deduction of Rs.1,03,577.72p from the final bill with respect to items 1.1 to 12.6.
a) The Arbitrator has held that the said deduction is on
account of various rebates to which DDA under the
agreement was entitled to for making regular monthly
payments and for making payment of the final bill within six
months of the date of completion of work and for making
payments of extra items within three months of the date of
occurrence and for releasing of security deposit within one
month after the expiry of six months maintenance period.
The Arbitrator found that the responsibility for preparing
the bills was on both the parties; if the petitioner prepared
the bill it had to be scrutinized by DDA by deputing the Jr.
Engineer to check the measurements; in terms of Clause 8 A
of the agreement measurements had to be recorded by an
officer of DDA; though under the agreement the
responsibility to submit the final bill is on the contractor but
on the basis of measurements by official of DDA; that there
was no evidence that DDA after completion of work ever
recorded the measurements or intimated the same to the
claimant; in the absence of recording of detailed
measurements no fault can be attributed to the claimant;
that there is practice prevailing in DDA for preparation of
running bills and the final bills by DDA; that no notice had
been given by DDA to the petitioner to file the running
account bills. In the circumstances the award holds that
DDA had failed to make the payments/release the security
deposit within the time and only whereupon it was entitled
to avail the rebate. The award thus directs payment of
amounts so deducted, to the petitioner.
b) The objection of DDA to this award is that the same is
contrary to R-7. If is further contended that the first 17
running bills were paid regularly and monthly and
subsequently on five different occasions two running bills
were paid within one month's time and thus deduction on
the said 27 bills could not have been disallowed. The rebate
on the said bills is stated to be amounting to Rs.14,995.89p.
c) The aforesaid would show that DDA accepts the award of
Rs.1,03,577.72p less Rs.14,995.89p.
d) The objections aforesaid of DDA are factual and this court in
exercise of jurisdiction under Sections 30 & 33 of the Act
cannot reappraise the evidence or to sit in appeal over the
award. An erroneous decision is neither an error apparent
on the face of the award nor misconduct.
e) This objection is also accordingly dismissed.
5. Re: Deduction of Rs.1,11,642.56p from the final bill with respect to agreement items 1.1 to 12.6 on account of double of rate recovery under Clause 42 of the agreement.
a) Under Clause 42 of the agreement the surplus materials not
returned had to be recovered at penal rates. The Arbitrator
has held that DDA has not given any detail for the excess
amount on this account. Petitioner admitted deduction to
the extent of Rs.57,107/-. The Arbitrator also found that
neither there was any notice on record to show that there
was any wastage of any material by the petitioner nor were
there any averments in this regard; that while steel had
been issued to the petitioner on weighment basis, recovery
had been made on the basis of liener measurements
multiplied by standard co-efficient; that there was no
averment of any wastage and the entire material had been
used in the work; that since different methods had been
adopted at the time of issue and at the time of making
payment for steel, there was bound to be difference if the
steel is overweight. The Arbitrator accordingly not finding
any proof of wastage or loss, held the recovery at penal rate
of Rs.1,11,642.56p minus admitted Rs.57,107/-, to be bad
and awarded the said amount.
b) The objection of DDA is that the award in this respect is
contrary to the terms of the agreement.
c) The said objection is misconceived. The Arbitrator has not
made the award by holding that DDA was not entitled to
recover for the wastage on penal rates. The award returns a
finding of fact that there was no wastage. Such finding of
fact of the Arbitrator is not interferable. The objection is
rejected.
6. Re: Award of Rs.42,788.69p under items 3.5 (a) and 3.5
(c).
a) This amount has been allowed for the quantity of shuttering
of beams, holding the same to be an integral part of roof
slab and holding the same to be payable along with the
centering and shuttering of roof slab. The Arbitrator has in
this regard relied upon CPWD specifications. The
contention of DDA that the rates payable for beams were
different from that for slabs even under the CPWD
specifications was negatived by the Arbitrator.
b) The objection is that the Arbitrator misunderstood the
matter and has ignored para 5.2.9.1 (c) on page 104 of the
CPWD's specifications, 1977, Vol.I and thus the award for
the said amount is liable to be set aside.
c) No arguments have been addressed on this aspect also.
Moreover, from the objection it transpires that the objection
is as to the interpretation of CPWD specifications to which
the Arbitrator has also referred. It is not as if the Arbitrator
has not dealt with the Specification 5.2.9.1 (c). However,
the Arbitrator has interpreted the same to be entitling the
petitioner to the said amount of Rs.42,788.69p. For
arguments sake even if it is to be held that Arbitrator has
wrongly interpreted the said specifications, when even a
wrong application of law has been held to be not an error
apparent on the face of the award or misconduct, the
question of interference with the award on this ground does
not arise.
The objection is accordingly dismissed.
7. Re: Award of Rs.29,173.40p under item 3.6 for wrongful omission of certain RCC work done by the petitioner.
a) The award records that the deduction for the said amount
was made by DDA for not plastering with cement mortar 1:3
to the exposed RCC work under item 3.6. The petitioner had
denied that no such surface had remained unplasterred. The
contention of DDA was that the RCC surface where 12 mm
or 15 mm plaster had been done was considered as exposed
surface and for which deduction had been made. The
Arbitrator held that as per CPWD specifications, RCC
surface on which 12 mm and 15 mm cement plaster had
been done could not be considered as permanently exposed
surface and thus allowed the claim.
b) The objection before this court is that in terms of the item
3.6, wherever 6 mm cement plaster was not done, the DDA
was entitled to make a deduction; it is further contended
that the Arbitrator has failed to appreciate the controversy.
c) I am unable to sustain the said objection also. The Apex
Court in M/s Sudarsan Trading Co. Vs. Govt. of Kerala
AIR 1989 SC 890 and in Food Corpn. of India Vs.
Joginder Pal Mohinder Pal AIR 1989 SC 1263 relied upon
by the senior counsel for the petitioner held that the court
has no jurisdiction to find out whether the Arbitrator had
acted correctly or not and the court cannot substitute its
own evaluation of the conclusion of law or fact to come to
the conclusion that the Arbitrator had acted contrary to
bargain between the parties. It was further held that
whether a particular amount was liable to be paid or
damages liable to be sustained was a decision within the
competency of the Arbitrator and the court could not take
upon itself the burden of saying that any part of the award
was contrary to the contract and thus beyond the
jurisdiction of the Arbitrator. The objection is thus
meritless and is rejected.
8. Re: Award of Rs.75,541.69p under item No.3.7 on account of overweight steel supplied by DDA to the petitioner.
a) The contention of DDA before the Arbitrator was that there
was no provision in the agreement for adjustment of
overweight steel. The Arbitrator held that while the
petitioner had asked for Tor steel only, DDA had given
partly Tor steel and partly mild steel and the petitioner is
entitled for payment of differences of quantities of Tor steel
and mild steel and arrived at the figure of Rs.75,541.69p for
the same.
b) DDA save for pleading that the award is contrary to Clause
12 of additional conditions and thus contrary to the terms &
conditions of the agreement has not objected to the formula
applied by the Arbitrator for arriving at the figure of
Rs.75,541.69p.
c) In the award in this respect I neither find any plea of DDA
with respect to Clause 12 of the additional conditions nor
any adjudication on the same. DDA, before the Arbitrator
had opposed the said claim only on the ground that there
was no provision in the agreement for adjustment of
overweight steel and the payment had been made to the
petitioner as per CPWD specifications, 1977 applicable to
the agreement. In the absence of the plea on which
objection is taken having been shown to have been taken
before the Arbitrator and in the absence of the same having
been dealt with by the Arbitrator, the objection before this
court cannot be entertained for the first time and is
accordingly rejected.
9. Re. Award of Rs.56,372.45p under item No.6.1for providing T iron frames for doors and windows.
a) The claim was on account of DDA while making the payment
having not measured the weight of M.S. lugs, M.S. flats
welded at the back of the frame for fixing butt hinges and
the sill tie welded to door frame at the bottom. DDA before
the Arbitrator contended that weight of the said items was
not liable to be paid and also on the ground that no
reference thereto had been made by the petitioner during
the execution of the work.
The Arbitrator held that DDA had not denied fixing of the
lugs, welding to M.S. flats and sill tie or the quantities
claimed by the petitioner. The award further holds that the
interpretation of DDA of the CPWD specifications is not
correct; the specifications do not provide that lugs, M.S.
flats and sill tie will not be measured for the purpose of
calculating the total weight of chowkhat for payment.
Accordingly the claim was allowed.
b) The objection of DDA is that the Arbitrator's interpretation
of CPWD specifications is incorrect.
c) For the reason stated above, the same does not constitute a
ground for interference with the award.
10. Re: Award of Rs.8,587.40p under item No.9.9 (a) for applying priming coat on wood work.
a) While DDA contended that the wooden door and shutters
supplied to petitioner for fixing were finished with primer
coat and as such no primer coat was required to be applied,
the petitioner controverted and contended that it had
applied the primer coat on the entire quantity of wooden
doors and windows supplied to if and as per the
requirements of CPWD specifications. The Arbitrator found
that DDA had partly measured the quantity of primer coat
done on the shutters and thus concluded that DDA was
liable for payment for application of primer on the entire
quantity of shutters.
b) The objection to the award is that the part primer referred
to by the Arbitrator was with respect to item No.9.9 (b) i.e.
application of primer on mild steel work and not on wooden
shutters.
c) This dispute is purely factual. Moreover, the award does
not record or deal with any contention of DDA before the
Arbitrator that the part payment for primer and on the basis
whereof the claim for balance payment was allowed was
with respect to mild steel work. In the absence of the
objection having been recorded or dealt with in the award,
the same is not maintainable before this court and is
dismissed.
11. Re. Award of Rs.20,388.32p under item No.9.10 (a) for painting on steel work.
a) The claim was on account of incomplete measurement by
DDA. The Arbitrator found short measurements to a certain
extent and allowed the claim.
b) The objection before this court is that there was no proof
before the Arbitrator of application of extra quantity
claimed.
c) The sufficiency or insufficiency of evidence for the award is
not open for consideration under Sections 30&33 of the Act.
The objection is rejected.
12. Re: Award of Rs.5,730.26p under item No.11.2 (a) for providing and fixing brass bib cocks.
a) The opposition of DDA before the Arbitrator was of, though
the agreement providing for fixing of the same, the
petitioner having failed to do so. The Arbitrator held that
since as per the agreement the bib cocks were to be fixed,
DDA would not have recorded the completion of work if the
such bib cocks had not been fixed and hence allowed the
claim.
b) The objection before this court is that the completion
certificate was subject to provision of certain items
including the bib cocks and the Arbitrator has ignored the
completion certificate Exhibit R-1. The completion
certificate R-1 is contained in the record filed by the
Arbitrator. I am unable to find any notation therein of the
bib cocks having not been fixed or remaining to be fixed.
The completion however certificate generally refers to
fixing of brass fittings remaining. In the absence of anything
to show that the brass fittings referred to in the completion
certificate R-1 did not include bib cocks, the award to this
extent is contrary to the document. Moreover, the Arbitrator
has not given any reason as to why he has not included the
bib cocks in the brass fittings. Accordingly, the award in so
far as of Rs.5,730.26p under item No.11.2 (a) is set aside.
13. Re: Award of Rs.3,820.17p under item No.11.8 (a) towards price of brass stop cock.
a) The award and the objection under this head is the same as
under item No.11.2 (a) and for the same reasons the award
under this head is set aside.
14. Re: Award of Rs.16,621.16p towards painting and GI pipes and fittings.
a) While the petitioner contended that the painting of GI pipes
had been done, DDA contended otherwise. The Arbitrator
held that since the said work was required to be done in
terms of the agreement and since completion certificate had
been issued, the work is deemed to have been done and
allowed the claim. The objection is that the completion
certificate R-1 notes that the said work had not been done.
b) A perusal of R-1 shows that it has noted therein that final
coat of white wash paint and colour washing had not been
done. In my view, the aforesaid cannot include the painting
of GI pipes in which no final coat is required before delivery
of possession. Thus the finding of the Arbitrator cannot be
said to be contrary to the document and the objection is
dismissed.
15. Re: Award of Rs.425.87p under item No.11.5 for providing and fixing PVC connections.
a) The claim was opposed for the reason of petitioner having
abandoned the work and having left the site incomplete and
the PVC connections having not been provided. The
Arbitrator on the basis of the completion certificate and in
the absence of any proof of work having been abandoned
allowed the claim.
b) The objection before this court is of the finding of the
Arbitrator being contrary to fact and completion certificate.
c) A perusal of the completion certificate R-1 on arbitral
record does not show any noting therein of certain PVC
connections remaining to be provided. Accordingly, the
objection is rejected.
16. Re: Award of Rs.5990.23p towards excavating trenches for laying SW pipes.
a) The opposition was that the said work though part of the
agreement had not been executed and the SW pipes having
been laid on the existing ground level. The Arbitrator held
that the SW pipes could not be laid on ground level and
allowed the claim.
b) The objection before this court is that there was no proof
before the Arbitrator to substantiate the claim and the
award being based on presumption.
c) I find that if as per the agreement, the SW pipes had to be
laid in trenches and had not been so laid, the same would
have been mentioned in the completion certificate or there
would have been other correspondence in this regard. In
the circumstances nothing wrong can be found with the
approach of the Arbitrator in believing that SW pipes could
not be laid on the ground and must be in trenches.
The objection is rejected.
17. Re: Award of Rs.12,44.54p under item No.12.6 for making connection of sewer lines with the existing manhole.
a) The dispute was again with respect to execution/non
execution of the work. The Arbitrator held that since the
sewer lines could not be used unless connected with the
main sewerage line, the work must have been done and
accordingly the claim allowed.
b) The objection again is of the award being presumptuous.
c) As aforesaid no defect can be found with the approach
adopted by the Arbitrator.
18. Re: Award of Rs.3,083.25p for extra and substituted items 1 to 5 & 20.
a) Though the execution of the extra items was not disputed,
the dispute was with respect to the rates paid therefor. The
formula for application of rates was also not in dispute. The
dispute was only as to certain rebates claimed by DDA on
the same. The Arbitrator held that DDA was not entitled to
claim rebates under the provision claimed.
b) The objection is that the Arbitrator has failed to consider
the letters dated 10th, 23rd & 31st August, 1985 to the
petitioner whereunder DDA was entitled to rebate and that
the award is contrary to the agreement between the parties
contained in the said letters.
c) I do not find any discussion in the award with respect to the
aforesaid letters; though DDA has pleaded that the bone of
contention between the parties has been noted by the
Arbitrator in para 2 at page 22 of the award but I do not
find any reference to the aforesaid letters therein also. It
has not been argued that the said letters were before the
Arbitrator. I have not found the said letters in the arbitral
record also. In the absence of the objection now taken
before this court having been shown to be taken before the
Arbitrator and having been dealt with by the Arbitrator, no
case of error on the face of the award or of misconduct is
made out.
The objection is rejected.
19. Re: Award of Rs.1,660.69p under extra item No.6 for providing balcony railings.
a) The case of the claimant was that payment therefor had
been made to it, treating the same as a RCC wall. The
contention of DDA was that the payment had been made as
per CPWD specifications. The Arbitrator held the railings to
be different from wall and thus allowed the claim.
b) The objection is that as per the drawings only a wall had to
be made and thus the payment had been correctly made.
c) The dispute aforesaid being of a factual nature and on
which the finding of the Arbitrator being the forum chosen
by the parties is final, the objection is misconceived and is
rejected. The senior counsel for petitioner has rightly relied
upon MCD Vs. Jagan Nath Ashok Kumar AIR 1987 SC
2316 laying down that reasonableness of reasons given by
an arbitrator in making his award cannot be challenged.
20. Re: Award of Rs.6,516.87p under extra item No.7 for rendering exposed surface of RCC railing with cement mortar.
a) This award and the objection thereto is the same as award
and objection under item No.6 above and the objection is
rejected for the reasons as in item No.6.
21. Re: Award of Rs.24,486.59p under extra item No.5 for centering and shuttering for RCC railings.
a) This award and objection thereto also is on the same
reasons as with respect to item No.6 above and the
objection is rejected for the same reason.
22. Re: Award of Rs.30,302.72p under extra item No.9 for fixing brass stop cock.
a) The award and the objection is the same as with respect to
the other brass items above. In view of the notings in the
completion certificate R-1 with respect to brass fittings, the
objection is allowed and the award to the extent of
Rs.30,302.72p is set aside.
23. Re: Award of Rs.3,327.80p under extra item No.19(a) for providing and laying cement concrete around floor traps.
a) While petitioner claimed to have done the work, DDA
contended that petitioner was not asked to provide the
same but had provided the same and for which payment had
been made. The Arbitrator found that as per the practice of
DDA the cement concrete around floor traps was required
to be provided and there being no dispute as to the rate,
allowed the claim for quantity found less paid.
b) In the objection before this court dispute as to
measurements is raised.
c) The same is outside the ambit of Sections 30&33 of the Act
and the objection is rejected.
24. Re: Award of Rs.19,665.65p under extra item No.19(b) for cement concrete around floor traps on other floors.
a) The award and the objection is the same as under item No.19(a) above and for the reasons stated above the objection is rejected.
25. Re: Award of Rs.21,314.20p under extra item No.23 for making grooves in the plastered surfaces.
a) Though the direction for carrying out the said work and
carrying out of the said work was not disputed, it was the
case of DDA that no separate payment was required to be
made with respect thereto. The Arbitrator after referring to
the CPWD specifications held that the same were to be
required to be paid separately.
b) The objection before this court is again on the
interpretation/view of the CPWD specifications and is not
maintainable and the objection is rejected.
26. Re: Award of Rs.6,199.20p under extra item No.24 for making cheques in treads of staircases.
a) While the petitioner contended that the work was carried out
as per the directions of DDA, DDA denied so. The Arbitrator
held that since the work was done as per the requirement at
site, payment therefor could not be denied.
b) The objection is of there being no proof before the
Arbitrator of the work having been done.
c) The award does not notice any contention of the respondent
of the said work having not been done. The only contention
of the respondent was that it had not directed carrying out
of the said work. The objection being beyond the face of the
award and even otherwise being factual in nature is
rejected.
27. Re: Award of Rs.42,195.98p under extra item No.25 for cutting holes in brick work for laying GI pipes and SCI pipes.
a) The contention of DDA was that this item of work was not
payable as per the condition of the contract on page 57
under para 3.1.6. The petitioner contended that since the
layout of SCI pipe and GI pipe had not been provided on
time by DDA the petitioner was required to carry out the
extra work. The Arbitrator found that DDA had not issued
the layout on due date and for the reason whereof the
petitioner had to do extra work; the petitioner could not
leave holes at the time of execution of work. There being no
disputes as per the quantity or the rate, the claim was
allowed.
b) The objection before this court is again on the basis of the
condition of contract relied upon before the Arbitrator also.
It is contended that the petitioner ought to have left the
holes as may be required for the said purpose and nothing
extra was payable therefor.
c) From Clause 3.1.6 of the contract relied upon by the
Arbitrator the view taken by the Arbitrator of DDA being
required to provide a plan and the finding of fact of the
Arbitrator of DDA having not so provided the plan and the
petitioner being thus not in a position to leave holes cannot
be said to be such which is improbable. On the settled
principles, the objection is not maintainable under Sections
30&33 of the Act and is rejected.
28. Re: Award of Rs.72,737.28 under extra item No.26(a) & 26(b) for providing SCI collars to SCI pipes.
a) The contention of the petitioner before the Arbitrator was
that the item was executed as per requirement at site; that
DDA issued pipes of one length only leading to the necessity
of providing collars; had DDA not intended to pay for the
collars, it should have provided the pipes of the required
length. DDA contended that the petitioner had used the
collars for their own benefit.
b) The Arbitrator held that DDA had not denied the provision
of the collars and the quantity claimed and had also not
denied the issue of pipes of the same length, while pipes of
different length were required and use of which pipes
necessitated use of collars. Hence the collars were found
payable and the award with respect thereto made in
accordance with the DSR rates applicable to the contract.
c) The objection before this court is that under Clause 3.15 of
the specifications and conditions of contract, the petitioner
was to provide the collars free of cost and nothing extra was
payable therefore and thus it is contended that the award is
contrary to the terms & conditions agreed.
d) The objection is tenable. The petitioner has in its reply to
the objections not stated that the respondent had not taken
the said plea before the Arbitrator and has also not disputed
Clause 3.15 relied by DDA. As per the said clause, the
petitioner was required to provide SCI collars required for
fixing SCI pipes of the required size free of cost and nothing
extra is payable therefore. The award does not deal with
this aspect. The arbitrator cannot award what is prohibited
under the agreement. The award under this item being
contrary to the agreement between the parties is set aside.
29. Re: Award of Rs.8,751.04p under extra item No.27 for providing flush pipe to flushing cistern. The dispute was on account of the length of the pipe used.
a) The contention of the petitioner was that in view of the
location of the WC pan, extra length had to be used. The
Arbitrator found in favour of the petitioner as per the site
condition.
b) The objection before this court is that no specific length of
the pipe had been provided for in the specifications and it
was a lump sum item and the claim for extra length was not
entertainable.
c) The Arbitrator has in the award held that as per CPWD
specifications, 1977, Vol.II, Page 83 Para 18.1.4 the length
of flush pipe to be provided is 1.25 mtr. while the petitioner
had to provide 1.80 mtr. No objection has been taken to the
said reasoning of the Arbitrator and in view whereof the
award under this item is non-interfereable in these
proceedings.
30. Re: Award of Rs.5,664.96p under extra item No.28 for providing and fixing SCI terminal guards.
a) The dispute was that the said guards had not been provided
at site and thus had not been paid. The Arbitrator held that
the provision of such terminal guards was necessary for
completion of works and with respect whereto a certificate
had been issued and thus allowed the claim.
b) The objection is on the basis of the completion certificate
Exhibit R-1. However a perusal of R-1 does not show any
noting therein of the said terminal guards having not been
provided. The objection is thus rejected.
31. Re: Award of Rs.1,84,903/- under extra item No.30 for straightening, cutting and hoisting of the steel bars issued in coils and bent up bundles.
a) The dispute was that the said works were covered as per
the CPWD specifications and the rates were included in the
rate of item already paid. The Arbitrator on the
interpretation of the agreement and the CPWD
specifications allowed the claim.
b) The objection besides on the basis of interpretation of
CPWD specifications is also on the basis of additional
conditions Clause 12 as per which no claim on account of
issuance of twisted bars, flats, tees, angles in available
length were to be entertained. It is thus contended that the
award is contrary to the agreement.
c) The petitioner in reply to the objections has not
controverted Clause 12 of additional conditions referred to
in the objections. In view thereof the award on this account
is contrary to the agreement between the parties and is set
aside. Senior counsel for the petitioner also fairly agreed to
the setting aside of the award to this extent for the reason
of the petitioner having not given notice for carrying out
said extra work, as required to be given, as held in Wee Aar
Constructive Builders Vs. DDA 2001 (3) Arb. LR 468
(Delhi).
32. Re: Award of Rs.41,26,467/- under item No.2 of other payments due on account of loss due to increase in price of building materials and other expenses.
a) The claims under other payments due were made owing to
alleged delay in execution of the work. The date of award of
work was 31st August, 1985 and the date of start was 10th
September, 1985. Stipulated date of completion was 9th July,
1986. The work could be completed only on 30th August,
1991. The delays according to the petitioner were
attributable to DDA. It was also not disputed that DDA had
granted extension of time up to 30th August, 1991without
levy of compensation. It was contended by the petitioner on
the basis thereof that DDA thus admitted delay attributable
to it. It was the contention of DDA before the Arbitrator that
the claims under said head were not arbitrable; that the
petitioner is not entitled to any amount for delay in as much
as the petitioner had been compensated under Clause 10 CC
of the agreement; that in terms of Clause 1 of the additional
specifications and conditions of the contract also no
damages were liable to be paid.
b) The Arbitrator held the claims to be arbitrable in as much as
the agreement was for reference of all claims under the
agreement and the said claim was also under the agreement.
The Arbitrator also held that the work had been delayed
because of lapses of DDA in handing over of site, layout plan,
drawings, finalization of colour scheme etc. sanction of extra
and substituted items and payment of running account bills
and in supply of stipulated material. It was further held that
whenever there is delay in building contract, the contractor
is bound to suffer. It was further held that Clause 1 of the
Additional Specifications and Conditions of contract did not
bar the said claims and excluded only those losses which
were suffered because of change in programme of
construction during the stipulated period of contract and
not beyond the stipulated period of the contract. It was held
that Clause 1 did not cover the delay on account of drawings,
decisions, non-release of payments. The Arbitrator also held
that Clause 10 CC does not take into its ambit complete
escalation coming into work though the amounts given under
Clause 10 CC were deductable from the actual escalation to
which the petitioner may be entitled. Holding so, the
Arbitrator applying the method of cost indices worked out
the total escalation to be of Rs.48,58,012.90p and after
deducting therefrom Rs.7,31,546/- given under Clause 10
CC, made an award for Rs.41,26,467/-.
c) The objection of DDA inter-alia is that DDA had granted
extension of time without levy of compensation on the basis
of undertaking of the petitioner that it had not suffered any
damages and was not to claim any such damages. It was thus
contended that the petitioner was barred from putting forth
such claim. Reliance was also placed on M/s Ishwar Singh
& Sons Vs. DDA MANU/DE/0310/1994 laying down that
arbitrator has no jurisdiction to award any sum on account of
damages contrary to specific provision of the contract. DDA
also relied upon C-67 in this regard.
d) The petitioner has in reply to the objections not denied
having given an undertaking. With respect to Annexure C-67
it is stated that the same was given under coercion as huge
payments of the petitioners were withheld and otherwise it
was not the requirement of the contract that any such
undertaking will be given.
e) The counsel for DDA has in this regard also relied upon
Anant Raj Agencies Vs. DDA 2005 (1) Arbitration Law
Reporter 590 (Delhi). In the said judgment, following the
judgments of the Division Benches of this court in DDA Vs.
U. Kashyap 1998 VII AD (Delhi) 300 & in DDA Vs. K.C.
Goyal & Co. 2001 II AD (Delhi) 116 it was held that an
award for compensation for escalation on the basis of cost
indices, beyond Clause 10 CC of the contract is erroneous on
the face of it and amounts to misconduct. It was further held
that where a contract provides for a formula as per which
escalation has to be worked out, Arbitrator being bound by
the contract between the parties cannot adopt a different
methodology. The award for amounts in excess of those
worked out under Clause 10 CC was thus set aside holding
the same to be in patent duplication.
f) I also find that the same view has been taken thereafter also.
Two other single judges of this court in Anant Raj Agencies
Vs. DDA CS(OS) No.2650A/1996 decided on 21st February,
2008 as well as in Jagat Ram Trehan & Sons Vs. DDA
2002 63 DRJ 92 have taken the same view.
g) I however find that another Division Bench of this court in
DDA Vs. M/s S.S. Jetley MANU/DE/0861/2000, inspite of
earlier judgment in V. Kashyap (Supra) held that claim for
prolongation of contract due to fault of DDA and for idle
labour, staff, machinery, centering, shuttering and
electricity, water etc. was dehors Clause 10 CC and
allowable. It was however reiterated that with respect to
items provided in 10 CC, no formula other than that applied
in 10 CC can be applied.
h) The matter does not rest there. Even in subsequent
judgment, dichotomy persists. Another single judge in Satya
Prakash & Bros. Vs. DDA decided on 28th September, 2001
held that arbitrator cannot act contrary to contract and the
award, since it was not possible to bifurcate the amount
awarded on account of delay by DDA in taking decisions (for
which it was held no claim could be allowed owing to clause
1) and for delay on account of non supply of cement, and
further since award did not deal with aforesaid clause 1, the
matter was remanded back. However, another single judge
in Narayan Das R. Israni Vs. DDA 126 (2006) DLT 10 held
that clause 10 CC applies only in respect of increase in
labour rates and material rates for period beyond stipulated
time and refused to interfere with the award for damages
under other heads on account of prolongation of contract for
reasons attributable to DDA.
i) I however find that in the present case, the challenge is not
to the computation done under clause 10CC. The claim and
award though on account of prolongation for reasons
attributable to DDA the damages awarded with respect
thereto are under the same heads as under clause 10CC. It is
for this reason only that the arbitrator after assessing the
damages payable by DDA to petitioner for such prolongation
has allowed deduction therefrom the amount already paid
under clause 10CC. Had the said assessment been with
respect to items not covered clause 10CC, the question of
deducting therefrom the amount assessed and paid under
clause 10CC would not have arisen. The arbitrator has thus
assessed damages under the same head as in clause 10CC
but applying the formula other than that provided in clause
in 10CC. This is an error apparent on face of record and not
permissible as per the judgments (supra) and thus this part
of the award is not sustainable and liable to be set aside.
j) I also find that the Arbitrator though noticing that
undertakings had been given by the petitioner at the time of
seeking extension of time, not to claim damages from DDA,
has not dealt with the same. The said undertaking by the
petitioner takes the form of a contract between the parties
and the said contract having provided that no damages
would be payable the petitioner could not turn around and
claim damages for delay. Though the petitioner has
contended that the said undertakings were under coercion
but no finding in that regard has been returned by the
Arbitrator. No further material has been cited to show that
immediately after furnishing the undertaking or at any time
did the petitioner take a stand that the said undertaking had
been obtained under coercion. The award is liable to set
aside for this reason as well.
33. Re: Award of Rs.1,28,000/- under item No.3 of other payments due on account of deployment of watch and ward staff at the site.
(a) The only objection is that there was no evidence before the
Arbitrator for the said claim of the petitioner. The sufficiency
or insufficiency of evidence is outside the domain of a
proceeding under Sections 30&33 of the Act. The petitioner
had claimed a sum of Rs.6,10,950/- on this account. The
Arbitrator after finding that the petitioner remained at site and
recording that DDA had not disputed the said position and
after further recording that the petitioner was not required to
remain at site after the defect liability period and on his
assessment of the salaries of the staff deployed by the
petitioner made the award. The said award is not interfereable
by this court and this court cannot impose its own opinion in
place of the award of the Arbitrator. The objection is
accordingly dismissed.
34. Re: Award of interest.
(a) The Arbitrator has awarded interest on the claims other
than the "other dues" at 18% per annum from 1st March, 1992
till the date of the award and upon failure to pay the awarded
amount within 60 days from the date of award, at 18% per
annum with quarterly rests from the date of the award till the
actual payment or till the decree whichever is earlier. Interest
at 18% per annum has been awarded on the amounts allowed
under "other dues" from the date of the award.
(b) In view of the recent dicta of the courts, taking note of the
rates of interest prevailing from time to time, I deem it
appropriate to modify the rate of interest from the date of the
award to 12% simple interest till the date of the decree. No
interference is however called for to the award of interest at
18% per annum for the pre reference period pendent lite
before arbitrator.
35. IA No.12811/96 is allowed to the aforesaid extent. Judgment is
pronounced in terms of the award as modified above. Decree sheet
be drawn up. Petitioner shall also be entitled to interest on the
principal amount under Section 28 of the Act from the date of decree
till the date of payment at the rate of 9% per annum.
RAJIV SAHAI ENDLAW (JUDGE) July 8, 2009 PP
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!