Citation : 2009 Latest Caselaw 2490 Del
Judgement Date : 6 July, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP.Nos 174/2004 & 184/2004
% Date of decision:06.07.2009
BHARAT SANCHAR NIGAM LTD. ...... Petitioner
Through: Mr Chandan Kumar, Advocate
Versus
RENEWABLE ENERGY SYSTEM LTD & ORS ...... Respondents
Through: Mr Vikas Dutta and Mr. Manish Vaid,
Advocates for Respondent No.1 & Mr. Pradeep
Dewan, Advocate for Respondent No.2 Canara
Bank.
AND
CANARA BANK ..... Petitioner
Through: Mr Pradeep Dewan, Advocate
Versus
BHARAT SANCHAR NIGAM LTD & Ors ...... Respondents
Through: Mr Chandan Kumar, Advocate for
Respondent No.1 and Mr. Vikas Dutta & Mr.
Manish Vaid, Advocates for Respondent No.2
Renewable Energy System Ltd.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported
in the Digest? No
RAJIV SAHAI ENDLAW, J.
1. Both petitions under Section 34 of the Arbitration and
Conciliation Act, 1996 are with respect to the same arbitral award
and are being taken up together for consideration.
2. Bharat Sanchar Nigam Ltd. (BSNL), the petitioner in OMP
174/2004 is for the present purpose, the successor of the
Department of Telecommunications (DOT) of the Government of
India. M/s Renewable Energy System Limited (RESL) which is
respondent No.1 in OMP 174/2004 and the respondent No.2 in OMP
184/2004 was the successful bidder in a tender floated by DOT for
manufacture of Solar Power Generating Systems (equipment) and for
leasing the same to DOT. In order to carry out the contract, RESL
approached Canara Bank (Bank), the petitioner in OMP 184/2004 for
grant of finance/credit facilities and it was inter alia agreed between
the Bank and RESL that after manufacturing the equipment, RESL
shall sell the same to the Bank and the Bank would, in turn, give
them on lease to BSNL for a period of five years, on payment of lease
money on quarterly basis besides other charges. A tripartite
agreement dated 19th February, 1998 between DOT, RESL and Bank
was entered into in this regard. The said agreement also contained
an arbitration clause providing for arbitration on any question,
disputes or differences arising under that agreement or in
connection therewith of the Director General, DOT or his equivalent.
In the meanwhile, DOT was succeeded by BSNL as aforesaid.
Disputes and differences having arisen, RESL approached for
appointment of arbitrator and the Respondent No.3 in each petition
was appointed as the sole arbitrator. The Bank also approached for
appointment of arbitrator and also filed its statement of claim in the
arbitration already commenced between RESL and BSNL; the said
arbitration was clarified by BSNL to be of the claims of the Bank
also. An award dated 24th February, 2004 was published by the
arbitrator.
3. The arbitrator in the said award has inter alia held:
i. that arbitration of claims of Bank against BSNL was
maintainable in spite of dicta of the Apex Court in ONGC Vs
Collector of Central Excise 1995 Supp (4) SCC 541 laying down
for reference of disputes between two Government bodies as Bank &
BSNL are, to the committee under the control of the Cabinet
Secretary;
ii. that the arbitration agreement covered disputes not only qua
the 1000 units of equipment by then already delivered to BSNL but
also qua the entire 9070 units of equipment subject matter of the
agreement;
iii. that RESL could not have offered 8070 units of equipment for
testing/inspection without BSNL issuing a purchase order having
details of destination to RESL;
iv. that it was indeterminable on the information on hand, as to
how much time RESL would have needed to make the balance 8070
units of equipment after purchase order with destination therefor
had been placed by BSNL on RESL;
v. that BSNL had placed a clear lease order to supply to its
destinations, whose particulars were to be furnished by the BSNL
separately, an exact and unchangeable quantity of 9070 units of
equipment under the tripartite agreement dated 19th February, 1998
and the subsequent agreement dated 31st March/19th April, 2000
with respect to 1000 units of equipment was only a formality with
respect to the 1000 units of equipment supplied/delivered and was
not in supersession of the earlier tripartite agreement dated 19th
February, 1998 with respect to supply of entire 9070 units of
equipment;
vi. that it was the BSNL which was at fault for non delivery of the
remaining 8070 units of equipment and for this fault was liable
under Section 54 of the Contract Act to pay compensation for the
losses suffered by RESL/Bank;
vii. that RESL was ready and willing to perform its part of the
agreement for supply of remaining 8070 units of equipment and was
prevented from supplying the same owing to the order dated 22nd
May, 2001 of the Telecom Engineering Centre (TEC). The arbitrator
however while holding so also held that the precise extent of the
readiness of RESL could not be determined for want of evidence;
viii. that the balance 8070 units of equipment could not be supplied
by RESL owing to the BSNL having failed to supply details of
destination as provided in annexure II of the agreement;
ix. that the failure of the BSNL for making lease payments with
respect to 1000 units of equipment already supplied was owing to
the default of the Bank in complying with the necessary formalities
in terms of the agreement in that regard and only on compliance
whereof the said payment could be released by BSNL;
x. that the reasons alleged by BSNL for not furnishing the
particulars of destination for supply of balance 8070 units of
equipment were not valid;
xi. that RESL had not made any incorrect statement to BSNL,
owing to which the failure of BSNL to take delivery of balance 8070
units of equipment could be justified. Consequently, it was held that
BSNL was not justified in not taking delivery of balance 8070 units of
equipment and axiomatically the Bank and RESL had become
entitled to suitable compensation under the law from BSNL. The
said finding was, however, clarified with the observations that the
precise liability of BSNL could not be determined unless "the
parties" offer satisfactory proof of losses allegedly suffered by them
and attributable directly to the default of BSNL;
xii. that the balance 8070 units of equipment which RESL claimed
to have kept ready for delivery to BSNL, conformed to the technical
specifications of BSNL and were obviously end-use-specific and the
likelihood of their usefulness for a different purpose and by some
user other than the BSNL could not be entirely ruled out without a
technical field survey. It was further held that this issue was quite
irrelevant at that stage;
xiii. that RESL was not entitled to the relief of specific performance
of directing BSNL to take delivery of balance quantities for the
reason of RESL having not proved that the balance 8070 units of
equipment actually stood manufactured by dates stipulated in the
agreement for delivery thereof and also for the reason of the relief of
specific performance being not maintainable in law for reason of
monetary compensation being an alternative remedy;
xiv. that the claim of compensation of RESL could not be
determined with the available information and the award proposed
the matter to be investigated in detail by an expert committee
comprising of nominees of each of the three parties and an
independent body; if such expert committee concludes that any of
the balance 8070 units of equipment were actually ready and only
waiting for destination details for inspection and dispatch as on 31st
July, 1998, the liability of BSNL for compensation be determined
with respect thereto;
xv. Certain monetary claims of RESL were declined and with
respect to yet other claims it was held that unless further particulars
supported by documents were furnished by RESL, the same could
not be adjudicated. Though RESL was held entitled to costs,
however, for the reason of it having not furnished all particulars and
proof of costs incurred, no award for costs of arbitration was made;
privity of contract was found between BSNL and the Bank with
respect to the arrangement for leasing of equipment but not with
respect to sanction or disbursal of funds by the Bank to RESL;
though the Bank was held guilty of having failed to submit the
requisite documents for release of quarterly lease rentals with
respect to 1000 units of equipment supplied but otherwise it was
held that RESL / Bank could not have taken any other steps for
mitigation of losses suffered by them;
xvi. Collusion between Bank and RESL to the detriment of the
BSNL was ruled out;
xvii. An Award for Rs 266.06 lacs with respect to the quarterly
lease rentals due for 1000 units of equipment supplied was passed
against BSNL. However, BSNL was not held liable for any interest
or penalty for late payment for the reason of the Bank having not
complied with the necessary formalities for release of the said
payment though found to be overdue earlier. It was directed that
upon compliance of formalities, BSNL shall release the said payment
within 30 days to the Bank;
xviii. The claim of the Bank on account of loss of tax benefit was
held to be remote and rejected;
xix. Cost of Rs 26,650/ incurred by the Bank towards the stamp
paper for the award only was awarded. The claim of the Bank for the
remaining costs of arbitration was rejected for want of proof;
xx. The claims of the Bank against RESL were held to be not
arbitrable;
xxi. The summary of the award as given towards the end is as
under:
"To sum up, the respondent DOT/BSNL is held guilty of breach of contract, and hence liable to pay damages to the other two parties. Quantification of these damages being not possible at present in the absence of authentic data, certain modalities to ascertain the same have been suggested. The respondent is also liable, under the lease agreements of 19.2.1998 and 19.4.2000, to pay the Lease Management Fee and Quarterly Lease Rentals to the claimant Canara Bank. These have been quantified. No costs for arbitration have been awarded, except reimbursement of expenditure on stamp duty incurred by Canara Bank."
4. BSNL as well as the Bank having preferred these petitions, the
stage for constitution of an expert committee as suggested in the
award did not arise.
5. BSNL has, in its petition, inter alia stated that due to change in
government policy, procurement of equipment with respect whereto
the aforesaid tripartite agreement was entered into was stopped and
accordingly it could place destination details for supply of only 1000
units of equipment. The challenged to the award by BSNL is limited
to:
i. the arbitrator having entertained the disputes between BSNL
and Bank and having not referred the same to the committee
under the control of the Cabinet Secretary;
ii. the failure of the arbitrator to give final arbitration award.
iii. the suggestion in the award of constitution of expert
committee being beyond the tripartite agreement and the
terms of the reference and specially when the arbitrator had
concluded that RESL and the Bank had not proved their
claims;
iv. the award being incomplete.
BSNL thus sought setting aside of the award to the aforesaid
extent.
6. The challenge by the Bank to the award is limited to:
i. the finding of the arbitrator of the claims of the Bank against
RESL being not arbitrable before him;
ii. the finding of the arbitrator of the precise liability of BSNL
for compensating the Bank/ RESL being in detriminable on
the basis of material on record;
iii. restricting the claim of the Bank for loss of profit only to the
extent of actual number of equipments manufactured and
kept ready for delivery as on 31st July, 1998 by RESL. It is
contended that the Bank having provided finance for the
entire 9070 units to RESL was entitled to loss of profits from
BSNL for the entire balance quantity of 8070 units;
iv. inconsistency in the award in, at page 45 holding that the
entire 8070 units could not at the relevant times be kept
ready fabricated and that the batteries had to be
manufactured only 15 days prior to the submission thereof
for testing and in other part of the award holding that it was
for the expert committee to decide as to how many units were
kept ready by 31st July, 1998 by the RESL;
v. the finding of the Bank having defaulted in complying with
the formality and in submission of documents for release of
quarterly lease rentals with respect to 1000 units of
equipment supplied. It is contended that BSNL had in its
reply to the statement of claim not taken the said plea and
had only taken the plea of having not released payments
owing to an order of the Calcutta High Court in a proceeding
filed by one Magma Leasing Company Ltd against RESL and
had taken the said plea subsequently as an afterthought. It is
further contended that the Bank had at the contemporaneous
time also never contended that it was unable to release the
payment for the reason of any failure of the Bank to comply
with the formalities. It is further contended that the order of
the Calcutta High Court had also come to an end in the year
2001. It is also claimed that the lease rentals were due from
27th June, 1998 while the arbitrator had awarded the same
w.e.f. 1st July, 1998.
7. RESL has not preferred any objections to the award. However,
in the reply to both the petitions RESL has also challenged the award
to the extent, of being in determinative and negating its other claims.
However, the said replies of RESL cannot be treated to be a petition
under Section 34 of the Arbitration Act and are even not within the
time prescribed in Section 34 (3) of the Act. The counsel for the
RESL during his oral submissions also has challenged the award. The
counsel for RESL also contended that the arbitrator after having held
the BSNL liable for loss caused to RESL and Bank ought to have
determined the quantum of the said losses himself and urged that
the matter should be remitted for determination of the quantum of
compensation. It was further contended that without BSNL
intimating the destination for delivery there could be no question of
RESL keeping the balance units ready for delivery. It was further
contended that in any case the remission ought to be only for
determination of the quantum of liability of BSNL and the other
findings ought not to be disturbed. The counsel also cited judgments
listed in index dated 18th September, 2008 but it is not found
relevant to deal with the same.
8. The counsel for BSNL during oral submissions pointed out it is
also borne out from the record that BSNL during the pendency of
these proceedings had deposited the sum of Rs 266.06 lacs in this
court and which sum has since been ordered to be released to the
Bank. The counsel for BSNL further submitted, that the arbitrator
found that RESL had not manufactured the balance 8070 units; that
RESL has not challenged the award and thus the said finding in the
award of RESL having not manufactured the balance machineries
has attained finality - the Bank is not competent and has no locus to
challenge the said findings. It is contended that in the aforesaid
state of affairs the challenge by BSNL is only to para 31 under issues
15-21 constituting a committee of experts. It was further contended
that the recourse, if any, of the Bank was against RESL and not
against BSNL and RESL has since been declared sick within the
meaning of SICA, 1985 and it was only owing to the sickness of RESL
that the Bank was pursuing its claims against BSNL.
9. The counsel for the Bank has contended that the Bank has
rendered financial assistance of over Rs 12 crores to RESL; that the
said finance was for the entire quantity of 9070 units of equipment;
that however the Bank had not received any payment in return; that
the Bank does not know who is at fault whether BSNL or RESL and
had hence asked for an award against whichever of the two was
found to be at fault; that both the Bank and RESL had moved an
application in the sitting held by the arbitrator at Hyderabad for an
inspection of balance quantity of equipments which were lying at
Hyderabad only but the arbitrator did not opt for the said inspection;
that the arbitrator erred in not awarding interest and penalty in
terms of the agreement to the Bank against BSNL with respect to
1000 units of equipment already supplied; that there was
inconsistencies in the award - while under issue 24 it has been held
that the Bank's claim for loss of profit in respect to balance 8070
units of equipment was beyond ambit of arbitration, in para 31 under
issues 15-21 direction for constitution of expert committee had been
given; that under Section 26 of the Act the arbitrator was entitled to
appoint an expert and if so desirous, ought to have first appointed an
expert and thereafter published the award; that in spite of liability of
the BSNL being determined, the award did not determine the
quantum of liability. Lastly it was urged that the arbitrator erred in
not adjudicating the claims of Bank against RESL which fell within
the ambit of arbitration clause in the tripartite agreement.
10. The counsel for BSNL, in rejoinder, contended that the
arbitrator is not a person steeped in law and owing to that while
holding that there was no evidence of balance 8070 units having
been manufactured and ready for delivery and which would have led
to dismissal of the claims for compensation, directed the constitution
of an expert committee. It was contended that the said direction was
severable from the remaining award and on such severance the
award otherwise was valid. It was further contended that on the
basis of available material neither RESL nor the Bank was entitled to
any other amount and fresh/further evidence could not be permitted
to be led before the expert committee suggested in the award.
11. A perusal of the objections of BSNL shows that BSNL has not
objected to the finding in the award insofar as holding BSNL to be in
breach of the contract and holding BSNL liable for losses suffered by
RESL/Bank. The main contention of BSNL/its counsel is that the
arbitrator having held RESL/Bank not to have placed sufficient
material before the arbitrator to prove the losses suffered or the
compensation to which they had become entitled, the arbitrator
ought not to have given directions for appointment of a committee
and award to which extent only is sought to be set aside by BSNL.
12. I am however unable to accept the aforesaid contention of
BSNL. It is not as if the arbitrator has gone through the evidence
and held that RESL/Bank has not proved to have suffered any loss.
On the contrary, the arbitrator has left the said question
undetermined. The loss to he Bank which has released finance even
for the remaining 8070 units of equipment to RESL is res upsa
loquitor. The arbitrator has also found the equipment to be specific
for use of BSNL and not found RESL/Bank guilty of not mitigating
losses. The arbitrator himself has in the award noted that during the
sitting of the arbitrator at Hyderabad both RESL and the Bank had
offered inspection of the remaining 8070 units which RESL was
averring it had already manufactured and kept ready for delivery to
BSNL. BSNL opposed the said request. The arbitrator has not given
any reason whatsoever as to why said inspection was not
undertaken. The arbitrator has not given enough weightage to the
said offer. The said offer lends one to believe that RESL was in a
position to give inspection of balance units. Moreover, I find that law
does not require the goods required to be supplied to be kept in
readiness. All that that the law requires is that the party claiming
compensation on account of breach ought to prove that in the
absence of the breach it was ready to perform its part of the
agreement so as to be entitled to a claim for loss of profit. All the
said aspects have not been gone into by the arbitrator and for the
reason that the arbitrator did not contemplate the award to be the
culmination of the proceedings but intended a further inquiry in this
respect. The award to the said extent is found to be against law and
public policy.
13. I find the aforesaid aspect to be no longer res integra. In
National Highways Authority of India Vs ITD Cementation
India Ltd MANU/DE/9104/2007 (DB) the arbitral tribunal noted that
although the claimant had produced some documents, but on the
basis thereof losses suffered could not be worked out; certain other
statements produced by the claimant in support of its claim were
also found to be lacking in details; the arbitrators held themselves at
a loss to work out the claim and in the circumstances declined to
quantify the amount due to the claimant and granted a declaratory
award holding that the claimant was entitled to additional costs
incurred by it and left the question of quantification to be
determined by National Highways Authority of India. It was
contended by the National Highways Authority of India in its
objections to the said award that the award was imperfect inasmuch
as it left the question of quantification of the amount undecided. It
was further contended that the arbitrators having clearly observed
that the material on record was insufficient to enable them to
determine the amount payable, the logical result which ought to
have followed was a rejection of the claim made before them and the
arbitrator could not have followed the unusual course of giving to the
claimant a chance to produce material and to satisfy NHAI regarding
additional costs. The procedure adopted by the arbitrator was
contended to be legally impermissible as the arbitrators were duty
bound to determine all questions in controversy and the exact
amount, if any.
14. The Division Bench of this court held that though ordinarily,
failure on the part of the claimant to substantiate its claims should
result in rejection of the claim but it is not an invariable rule. It was
held that it was possible in certain situations to leave the actual
quantification to be made by a party or an agency to be appointed by
the arbitrators on principles laid down by the arbitrators. The
Division Bench however in that case held that the facts thereof were
not such where determination of principle could result in
quantification of the amount by a simple process of calculation. It
was held that determination of disputed questions of facts had to be
at the hands of the arbitrators only and could not be delegated to
any other person or authority. It was further held that inasmuch as
the arbitrators had left the issues regarding quantification of the
amount open but required the same to be decided by NHAI which
was the party to the dispute, they committed a mistake.
Quantification of the amount was held to be a major area of
controversy between the parties. It was further held that the claim
could not be rejected in toto simply because the material was not
sufficient and it was necessary that the amount was quantified in
spite of being left open for determination. Resultantly the award
was set aside and the matter remitted back to the arbitrators, limited
to the issue of quantification. The division Bench also gave
additional opportunity to the parties to adduce evidence on
quantification before making a fresh award.
15. I am respectively bound by the aforesaid dicta of the Division
Bench. Similarly, the Division Bench of the Kerala High Court in
Sulaikha Clay Mines Vs Alpha Clays AIR 2005 Kerala 3 held while
setting aside an award for procedural violation the court is
empowered under Section 34(4) of the Act to also change the
arbitrator. I may add that I have also in Union of India Vs Modern
Laminators Ltd MANU/DE/1237/2008 held that the court is
empowered in dealing with an application under Section 34 of the
Act to not only remit the matter back but also to modify the award.
16. In the present case also I find that several disputed questions
of fact will be entailed in quantification of damages losses and
determination thereof is in sole domain of arbitrators and cannot be
left to the committee proposed. From the findings of the arbitrator as
summarized herein above and to which there is no challenge, it
cannot be said that the present is a case of no losses having been
suffered by RESL/Bank. In the aforesaid circumstances the
objections of BSNL are not found sustainable and accordingly OMP
No. 174/2004 is dismissed. Consequently, OMP.No.184/2004 insofar
as seeking remission of the matter to the arbitrator is concerned has
to be allowed.
17. I may at this stage notice that though BSNL had also preferred
objection qua the disputes between the BSNL and the Bank being
not arbitrable for the reason of being required to be referred to the
Committee under the control of the Cabinet Secretary, but the same
was not pressed during the arguments. Even otherwise, the award
records that the said Committee was approached and declined the
request on the ground of the disputes being required to be resolved
by arbitration. The award cannot be faulted with on the said ground.
18. I also do not find any merit in the objection of BSNL of the
arbitrator having found that RESL had not manufactured the balance
8070 units and/or of the said finding having become final for the
reason of RESL having not challenged the award. Not only is the
said finding of the arbitrator inconsistent to other findings in the
award, but as observed by me above, the question of determination
of compensation is to be determined irrespective of whether 8070
units were lying ready for delivery or not. Moreover, the Bank being
party to the agreement and being the real affected party is even
otherwise entitled to challenge the said finding and the failure of
RESL to file objections would not affect the rights of the Bank. The
Apex Court in K.P. Poulose Vs. State of Kerala 1975 (2) SCC 236
has held that an inconsistent award is liable to be set aside by the
court.
18.A The counsel for BSNL has relied upon:
i. Hind Builders Vs. U.O.I. AIR 1990 SC 1340 laying
down that court cannot interfere with possible
interpretation of contract by arbitrator.
I do not find the same applicable. The arbitrator in
holding in one part of award of liability of BSNL being
limited to the units of equipment kept ready or in
appointing expert committee has not interpreted any
contract.
ii. MCD Vs. Jagan Nath Ashok Kumar AIR 1987 SC 2316
and UOI Vs. Santiram Ghosh AIR 1989 SC 402, neither
of which is also found relevant for the issues involved.
19. As far as the other objections of the Bank to the award are
concerned, firstly I do not find any error apparent on the face of the
award in the finding that the claims of the Bank against RESL were
not arbitrable. The interest of the Bank and RESL in the agreement
containing the arbitration clause was in unison. The purport of the
arbitration agreement is of resolution of disputes by arbitration to
which BSNL is a party. It does not stand to reason as to why the
officer of BSNL should be an arbitrator in disputes between the
RESL and the Bank. Moreover, it is the admitted position that
besides the agreement containing the arbitration clause, there are
other documents between the RESL and the Bank. The arbitrator
himself has in the award referred to Bank having obtained an
indemnity from RESL. It is not the case of the counsel for the Bank
that the said documents also provided for arbitration by the officer of
BSNL. The officer of BSNL has not given his consent to be the
arbitrator in the inter se disputes between the RESL and the Bank.
In the circumstances the arbitrator was justified in taking a view of
the said inter se disputes between the Bank and RESL being not
arbitrable before him. The award also records that the counsel for
the Bank had agreed with the aforesaid stand of the arbitrator. I
have perused the objections preferred by the Bank. I do not find any
statement therein that the said part has been erroneously recorded
by the arbitrator or that no such statement was given or stand taken
by the counsel for the Bank before the arbitrator. The counsel for the
Bank having agreed before the arbitrator that the said inter se
disputes were not arbitrable is not entitled to now object to the
same.
20. However, the objection of the Bank to the observations/finding
of the arbitrator of the claim against BSNL being limited to the
extent of actual number of equipments manufactured and kept ready
is contrary to law. There is no such requirement in law. If
Bank/RESL by evidence or otherwise are able to establish before the
arbitrator that but for the breach by BSNL they were in a position to
perform their part of the agreement, Bank/RESL would be entitled to
compensation for breach as also held by the arbitrator. The award
to that effect is set aside.
21. However, I do not find the objection of the Bank to the award
to the extent holding the Bank to be in fault in complying with the
formalities for release of the payments with respect to 1000 units of
equipment to be within the ambit of Section 34 of the Act. The said
finding is factual in nature and this court is not to sit in appeal over
the award and no question of public policy is involved. The said
objection is thus dismissed. similarly no interference is called for in
the finding as to the amount due towards the said 1000 units of
equipment.
22. Thus the award to the extent aforesaid is set aside and
remitted back to the arbitrator. Since the arbitrator was an officer
of BSNL and may not now be in a portion to arbitrate, it is clarified
that in the event of the same arbitrator being unavailable for
arbitration the arbitration be held by the present incumbent in office.
BSNL to intimate the particulars of arbitrator to other parties within
30 days of today. The arbitrator to render an award of the
compensation payable by BSNL for breach of contract. In
consonance with the law laid down by the Division Bench of this
court (supra) the parties shall be entitled to adduce further evidence
on the quantum to be determined by the arbitrator.
With the aforesaid directions, the petitions are disposed of
leaving the parties to bear their own costs.
RAJIV SAHAI ENDLAW (JUDGE) July 06, 2009 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!