Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Paragon Construction vs D.K.Sharma & Anr.
2009 Latest Caselaw 2391 Del

Citation : 2009 Latest Caselaw 2391 Del
Judgement Date : 1 July, 2009

Delhi High Court
M/S Paragon Construction vs D.K.Sharma & Anr. on 1 July, 2009
Author: Shiv Narayan Dhingra
*           IN THE HIGH COURT OF DELHI AT NEW DELHI


                                                Date of Reserve: April 24, 2009
                                                    Date of Order: July 01, 2009
+CS(OS) 946A/1997 & IA No.125/1998
%                                                                          01.07.2009
     M/s Paragon Construction                                       ...Petitioner
     Through: Mr. Ravi Sikri, Advocate

       Versus

       D.K. Sharma & Anr.                                           ...Respondents
       Through: Mr. K.L. Budhiraja Advocate


       JUSTICE SHIV NARAYAN DHINGRA

1.     Whether reporters of local papers may be allowed to see the judgment?

2.     To be referred to the reporter or not?

3.     Whether judgment should be reported in Digest?


       JUDGMENT

1. The subject matter of these objections is an award passed by the

learned Arbitrator on 6th January 1997 awarding a sum of Rs.10,13,185/- to

the claimant with 12% interest per annum on the amount awarded from the

date of award till actual realization/ payment. Though the award passed by

learned Arbitrator is a lumpsum award in which no reasons have been given

by the Arbitrator but a perusal of record would show that the Arbitrator had

first prepared a draft in which he had discussed all the claims and counter

claims giving reasons and then passed a lumpsum award. Thus, the reasons

can be deciphered from the record itself.

2. The award is objected to by the respondent National Projects

Construction Corporation Limited on the grounds that the appointment of the

Arbitrator itself was illegal since the claimant had accepted the final bill

CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 1 Of 7 without any demur and once the final bill was accepted, no further claim of

the petitioner could be raised before the Arbitrator. The other ground is that

the Arbitrator gave a non-speaking award and overlooked and ignored the

evidence placed before him which had vital bearing on the matter in

controversy and he did not deal with the claims made by the objector in

answering to the claims of the petitioner. The other objection is that the

award was contrary to the terms of contract. Most of the claims made by the

claimant were beyond the terms of the contract. The respondent had

provided to the learned Arbitrator a copy of measurement book (MB) duly

endorsed by the claimant. The claimant had accepted the correctness of the

measurements recorded therein and it was not open to the claimant to make

any claim against respondent in relation to the work order in question beyond

MB. It is further submitted that once the final bill had been accepted by the

petitioner, nothing remained due to the petitioner from respondent and thus

the arbitrator should have dismissed the claims. It is further submitted that

the claims of the claimant were barred by time as per the terms of contract

and the award was, therefore, without jurisdiction and had an error apparent

on the face of it.

3. The claimant had made following claims before the Arbitrator:

"Claim No.1 :Refund of Hire charges of Rs.21,685/- said to have been hired out to claimants.

Claim No.2: Refund of Rs.90,000/- recovered towards compensation payable to accident victim who died during an accident which was cowped by truch engaged at site by the claimant. Claim No.3: Refund of Rs.1,89,000/- withheld for alleged slow progress of work.

Claim No.4: Release of payment of Rs.3,02,500/- towards

CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 2 Of 7 extra lead charges for earth work.

Claim No.5: Payment of Rs.9,79,690/- towards idling charges of machinery, labour & overheads.

Claim No.6: Payment of pre-suit interest of Rs.15,60,086/. Claim No.7: Payment of Pendente-lite future interest @ 20% p.a. Claim No.8: Payment of Rs.50,000/- towards cost of arbitration.

4. Respondent also made following counter claims:

               "Counter claim No.1:         Payment         of       damages           of
                                            Rs.9,50,000/- for slow progress.
               Counter claim No.2:          Payment       of      Rs.15      lac      as
                                            overheads         charges      as       extra
                                            expenses           incurred         during
                                            extended period of 3 months,
                                            which was necessitated due to
                                            slow progress of claimants.
               Counter Claim No.3:          Payment      of      Rs.1,58,550/-        for
                                            providing technical staff for one
                                            year for giving lines & layout."




5. It is an undisputed fact that the claimant had accepted the final bill on

28th May, 1989 with following endorsement:

"Final bill accepted except that any amount paid to NPCL by NHPC against our work will be passed on to M/s Paragon Construction (India) Pvt. Ltd.

Sd/-

Subash (Director)"

6. The claimant had asked for additional payment on the ground of

CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 3 Of 7 additional lead in earth excavations. The respondent who had given this

contract on behalf of NHPC had also raised claims with NHPC for additional

amount on account of additional lead. The claimant's endorsement is in

respect of this claim which the objector had promised to pass on to claimant.

7. After acceptance of final bill, the claimant was to be paid the balance

security amount. The correspondence between the parties shows that at the

time of making the payment for balance security amount, the respondent

withheld an amount of Rs.90,000/- against accident case of M/s Complete

Experts and had also deducted hire charges of Rs.21,685/-. Claims No.1 and 2

pertained to these two amounts. The claim No.3 is in respect of deductions on

account of slow progress and claim No.4 is in respect of extra lead for which

endorsement was made by the director of the claimant company at the time

of accepting final bill.

8. Learned Arbitrator came to conclusion that the deductions of hiring

charges of Rs.21,685/- was without any basis and without any evidence and

this amount should be refunded. Similarly, in respect of claim No.2, he

observed that this amount was rightly withheld initially but since respondent

had not paid any amount to the victim and the claim of victim was settled by

insurance company, this amount cannot be kept by respondent and,

therefore, should be refunded back to the claimant. He observed that even

otherwise the claim of victim must have become barred by time in view of

clause 166(3) of Motor Vehicles Act. Thus, above two claims in fact arise after

final bill was finalized because of deductions made from the security amount.

The letter of respondent dated 13th June 1991 gave the details of deductions.

Thus, these two claims in fact arose after payment of final bill. However,

CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 4 Of 7 other claims are of the period when the contract was in progress and before

finalization of the final bill. Clause 48 of the contract which is in respect of

payment of final bill reads as under:

"CLAUSE 48: PAYMENT OF FINAL BILL.

The final bill shall be submitted by the sub contactor within one month of the date fixed for completion of the work or of the date the certificate of completion furnished by the Engineer-in-charge. No further claim in this regard unless as specified herein under shall be entertained. Payment shall be made within three months if the amount of the contract plus that of the additional items is Upto Rs.2 lac and in 6 months, if the same exceeds Rs.2 lac of the submission of such bill. If there shall be any dispute about any item or items of the work, then the undisputed item or items only shall be paid within the said period of three months of six months, as the case may be. The contractor shall submit a list of the disputed item within thirty days from the disallowance thereof and if he fails to do so, his claim shall be deemed to have been fully waived and absolutely extinguished"

9. A perusal of this clause would show that after finalization of work and

submission of final bill, in case there was any disputed item disallowed in the

final bill, the contractor had to submit a list of disputed items within 30 days

from the disallowance thereof and if he failed to do so, his claim shall deemed

to have been waived and shall stand extinguished. In view of this clause in

the contract, the claimant could not have raised disputes after 28 th June 1989

i.e. after 30 days of the finalization of the bill and acceptance of it by

respondent. Therefore, the claims made by claimant under Claim No.3 and 5

could not have been raised by the claimant in view of this clause of the

CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 5 Of 7 contract after 28th June 1989. However, claim No.4 was in respect of extra

lead and the director of claimant had made endorsement that in case an

amount was received by respondent, it shall be passed over to the claimant.

It is apparent that the claimant was not paid for extra lead with the assurance

that the respondent has also made a claim for extra lead with NHPC and

whenever received, it will be passed over to the claimant. It seems that the

respondent did not receive payment against extra lead from NHPC.

Consequently, it did not pass over any payment to claimant and the claimant

was forced to re-agitate this point before the Arbitrator.

10. There is no clause in the contract in respect of payment on account of

idling charges which is claim No.5 neither this claim was received within 30

days of the acceptance of final bill. Similarly, claim No.3 was not made within

30 days. The learned Arbitrator failed to consider the clause 48 of the

contract while passing award in respect of different claims of claimant.

11. It is settled law that the arbitrator is the prisoner of contract. He cannot

adjudicate the claims between the parties of his own whims and fancies and

he has to adjudicate the claims on the basis of the contract. He cannot

adjudicate those claims which are in the nature of tortuous liabilities. He can

adjudicate only those claims which arise directly out of the contract. While

adjudicating claims, he cannot travel beyond the contract, nor can write a

new contract for the parties.

12. Although the award is a lumpsum award but the draft of the award

gives a split up of the claims allowed by the arbitrator as under:

       Claim No.1 :        Rs.21,685/-

CS(OS) 946A/1997    M/s Paragon Construction v D.K. Sharma & Anr.   Page 6 Of 7
        Claim No.2 :       Rs.90,000/-
       ClaimNo.3   :      Rs.1,89,000/-
       Claim No.4 :       Rs.3,02,500/-
       Claim No.5 :       Rs.4,10,000/-
                          ----------------
       Total       :      Rs.10,13,185/-
                          ------------------



13. Claims No. 3 and 5 could not have been entertained by the learned

Arbitrator in view of clause 48 of the contract, however, claims No.1, 2 and 4

were within the purview of the arbitrator since these claims arose after

signing of final bill and because of the fact that respondent did not receive

any amount from NHPC against extra lead. I, therefore, consider that the

award passed by learned Arbitrator only to the extent of claims No.1, 2 and 4

can be allowed amounting to Rs.4,14,185/- and award against claims No.3

and 5 are beyond the terms of the contract and could not have been raised

by the claimant in view of clause 48 of the contract. The objections of the

objector in respect of claim No.3 & 5 are allowed.

14. I, therefore, partly allow this award to the tune of Rs.4,14,185/-. The

amount awarded is modified accordingly. Claimant shall be entitled to 12%

interest per annum over this amount from the date of award till actual

realization as allowed by the learned arbitrator. The objections are allowed

partly in above terms. The modified award be made rule of court in above

terms. The petition stands disposed of.

July 01,    2009                                  SHIV NARAYAN DHINGRA J.
rd




CS(OS) 946A/1997 M/s Paragon Construction v D.K. Sharma & Anr. Page 7 Of 7

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter