Citation : 2009 Latest Caselaw 74 Del
Judgement Date : 14 January, 2009
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Arb. Appl. No. 261/2008
*
% Date of decision : 14.01.2009
STERLITE OPTCAL TECHNOLOGIES LTD. ....Petitioner
Through: Mr. Tarun Gulati and Mr. Neil
Heldrieth, Advocates
Versus
BHARAT SANCHAR NIGAM LTD. .... Respondent
Through: Mr. U.C. Mittal and Mr. Ankur
Mittal, Advocates
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
RAJIV SAHAI ENDLAW, J.
1. The factum of the parties to this petition being parties to an
agreement containing in arbitration agreement and the factum of
this being the right High Court to be approached is not in dispute.
The arbitration clause in the agreement between the parties is as
under:-
"Clause 20. In the event of any question, dispute or difference arising under this agreement or in connection there-with (except as to the matters, the decision to which is specifically provided under this agreement), the same shall be referred to the sole arbitration of the CMD, BSNL or in case his designation is changed or his office is abolished, then in such cases to the sole arbitration of the office for the time being entrusted (whether in addition to his own duties or otherwise) with the functions of the
CMD, BSNL or by whatever designation such an officer may be called (hereinafter referred to as the said officer) is unable or unwilling to act as such, then to the sole arbitration of some other person appointed by the CMD, BSNL or the said officer. The agreement to appoint an arbitrator will be in accordance with the Arbitration and Conciliation Act, 1996....."
2. The petitioner applied under Section 11 ( 6) of the Arbitration
Act on the ground that the respondent in spite of request has refused
to join in the appointment of the arbitrator and / or the appointing
authority has failed to appoint the Arbitrator and thus the agreed
arbitration procedure has failed.
3. The respondent has contested the application on three
grounds. Firstly, it is contended that the agreement is of arbitration
by CMD of the respondent or by any person appointed by the CMD;
the petitioner never approached the CMD and only approached the
DDG (MM) of the respondent for arbitration. Secondly, it is
contended that the dispute raised fall in the excepted matter under
the arbitration clause aforesaid. Thirdly, it is contended that in fact
there is no dispute inasmuch as the claim as set out in the petition
and disputed by the respondent is not under the agreement but
tantamounts to the petitioner wanting the agreement to be re-
written.
4. As far as the first contention of the respondent is concerned,
admittedly there is no communication from the petitioner, after the
disputes have arisen to the CMD of the respondent. The agreement
between the parties is of reference of disputes to a named arbitrator
i.e. CMD of the respondent who under the agreement is also entitled
to nominate/appoint some other officer of the respondent as the
arbitrator. The petitioner has relied upon its letter dated 23rd April,
2007 to the DDG (MM) of the respondent stating that in view of
disputes have arisen, the petitioner in terms of Clause 20 of the bid
document was calling upon the addressee to forthwith nominate and
appoint the arbitrator to adjudicate the issues in dispute and further
stating that if the appointment of the arbitrator is not made in terms
of clause 20, the petitioner shall proceed on the basis that there is no
agreement on the procedure for appointing arbitrator and proceed
with appointment of arbitrator in accordance with the Act. The
Assistant Director General (ST) of the respondent replied to the
aforesaid communication on 7th May, 2007 stating that the request
for appointment of an arbitrator in terms of clause 20 of the bid
document was not tenable in view of terms and conditions of the
document. The advocate for the petitioner sent another letter dated
7th June 2007 again to the DDG (MM) of the respondent and which
was replied to 21st June, 2007 by the Assistant Director General (ST)
reiterating the stand taken earlier.
5. The question which arises is that where the CMD of the
respondent is named arbitrator but the petitioner instead of
approaching the CMD writes to some other official of the respondent
to appoint the arbitrator, whether it can be said that the conditions
of Section 11 (6) are satisfied entitling the petitioner to approach
this Court to take the necessary measure. This is all the more
relevant when the official of the respondent approached has denied
reference to arbitration on ground other than that the petitioner
having not approached the CMD.
6. Under Section 11 (2) of the Act, the parties are free to agree
on a procedure for appointing the arbitrator. Sub-section 6 provides
that where under an appointment procedure agreed upon by the
parties, a party fails to act as required under that procedure or the
parties or the two appointed arbitrators fail to reach an agreement
expected of them under that procedure or when a person fails to
perform any function entrusted to him under that procedure, a party
may request the Chief Justice or his designate to take the necessary
measure for securing the appointment. Sub-section 5 deals with a
situation of the parties having not agreed on any procedure for
appointment of arbitrator.
7. A bare reading of the arbitration clause in the present case
would show that the parties had in the agreement itself agreed on
the arbitrator. The CMD of the respondent was the agreed
arbitrator. When the parties have agreed on the arbitrator to whom
the disputes are agreed to be referred, upon disputes arising, the
parties or any of them are required to approach the said named
arbitrator. In such case, sub-sub-clause (c) of sub section 6 is
attracted and a party becomes entitled to request the Chief Justice
for securing the appointment only when the named arbitrator fails to
perform any function entrusted to him under that procedure. When
an arbitrator is named in the agreement, the parties raising the
dispute or making the claims is not required to approach the other
party to join in the appointment of the arbitrator or to appoint the
arbitrator as the petitioner has done in the present case. There was
no need for the petitioner to approach the DDG (MM) of the
respondent for nominating and appointing the arbitrator inasmuch
as the arbitrator was already named in the agreement. What the
petitioner was required to do was to approach this CMD of the
respondent with its claims and only if the said CMD had failed to
either himself act as an arbitrator or to nominate/appoint anyone
else as the arbitrator, could the petitioner have any cause of action
for approaching this Court. The petitioner having admittedly not
done so, the petition is liable to be rejected as without cause of
action.
8. The next aspect to be examined is as to would the refusal of
the Assistant Director General (ST) of the respondent to appoint an
arbitrator make any difference. The petitioner had agreed to the
arbitration of CMD or his nominee, notwithstanding the proximity of
the said CMD to the other party, for the reason of special faith
having been reposed in the person occupying the office of the CMD.
It was open to the parties to agree and provide that in the event of
disputes, the respondent shall nominate/appoint the arbitrator. The
parties instead of agreeing so, agreed to the arbitration of CMD or
his nominee. Thus, CMD of the respondent, at least for the purpose
of arbitration agreement was treated differently from the respondent
and cannot be equated with the respondent. Thus, the denial by the
Assistant Director General (ST) of the respondent to the request of
the petitioner for appointment of arbitrator is of no avail. Moreover,
the request itself was not in accordance with the agreed procedure.
Thus, in my view, the application is without any cause of action and
is liable to be rejected on this gourd alone.
9. The second contention of the respondent that the dispute
raised is an excepted matter can be discussed together with the third
contention of there being no dispute between the parties.
10. The case as set out in the petition/application is that under the
agreement between the parties, under Clause 3 titled "Price
Variation' the composite price of each size of cable was to be worked
out on monthly basis, based upon the monthly Copper Price Circular
issued by the respondent; that the petitioner had agreed to the price
being determined as per the Copper Price Circular issued by the
respondent because the respondent in the past had always adopted
the market price issued in the monthly circular of Hindustan Copper
Limited (HCL) which being the sole indigenous producer of primary
copper in India and being also a public sector undertaking issued
monthly price circular of copper and which was always reflective of
the market price; that historically, the price circulars issued by the
respondent have been identical to the HCL price circulars and in the
past the cable industry had no reason to raise a grievance to the
respondent reserving a right to determine the copper prices because
of being satisfied by the same being copper price as published by the
HCL; that however this time around during the currency of the
agreement subject matter of the application, the respondent in
complete disregard of past practice determined the copper prices at
variance and lower than that of the copper price as published by
HCL. The said action of the respondent was impugned in the
petition/application as arbitrary and is the basis of the claims raised
by the petitioner and disputed by the respondent and for
adjudication of which appointment of arbitrator is sought.
11. The second contention aforesaid of the respondent is that the
prices of copper under the agreement were to be determined by the
respondent and thus the disputes raised fell within the excepted
matters in the arbitration clause i.e., the decision of which was
specifically provided under the agreement. Thirdly, it was
contended that since it was not disputed that the petitioner had been
paid as per the price of copper published in circulars of the
respondent and the claim was based on the prices of copper
published in the circulars of HCL, there was in reality no dispute
requiring the parties to be referred to arbitrator.
12. The second contention raised by the respondent is no longer
res integra. The Apex Court recently in BSNL vs. Motorola India
Pvt. Ltd. 2008 (12) Scale 720 : MANU/SC/4021/2008 has held that
for the matter to fall in the excepted matter, an adjudicatory
mechanism/process has to be provided therein. In the absence of
any adjudicatory process it cannot fall within excepted matter, the
decision of which is provided under the agreement.
13. In this regard, it may be noted that the counsel for the
respondent had argued that the only matter the decision whereof
under the agreement was to be of the respondent was with respect
to the publication of the aforesaid prices of copper and thus the
exception in the arbitration clause applied to the determination of
price of copper only and could not apply to any other matter.
However, a perusal of the clause relating to publication of price of
copper by the respondent shows that no adjudicatory process was
entailed therein. Merely, because the so called excepted matter in
the arbitration clause could not apply to any dispute for the reason
that the decision of no matter by adjudicatory process was left to the
respondent, is no ground to apply the said exception clause to the
case in hand. Moreover, the Apex Court in the judgment aforesaid
has also held that such a clause would also be contrary to Section 28
of the Contract Act being in restraint of legal proceedings and has to
be held to be bad. Following the said dicta, the second contention of
the respondent is not found tenable.
14. As far as the third contention of the respondent is concerned, it
tentamounts to saying that the dispute raised is illusionary or no
dispute and hence the parties ought not to be put through the
expensive exercise of arbitration. The counsel for the respondent
has in this record relied upon SBP & Co. vs. Patel Engineering
Ltd. & Anr. (2005) 8 SCC 618. The Constitution Bench of Apex
Court in the said judgment, overruling the earlier position held that
at least in the matter of deciding his own jurisdiction and in the
matter of deciding on the existence of an arbitration agreement, the
Chief Justice when confronted with two points of view presented by
the rival parties has to decide between them. The Apex Court in
para 37 of the judgment citing the examples of claims being made 10
or 20 years after the period of contract come to an end and of where
appointment of arbitrator is sought after the parties had settled the
accounts and the party concerned had certified that he has no
further claim against the other and when dead claims are sought to
be resurrected or where assertions are made of the existence of
arbitration agreement when in fact such existence is strongly
disputed or a controverted or as to whether the claim that is sought
to be put forward comes within the purview of arbitration clause
concerned at all, held that the Chief Justice has necessarily to apply
his mind to these aspects before coming to a conclusion one way or
the other and before proceeding to appoint an arbitrator or declining
to appoint an arbitrator. The Constitution Bench in para 32 of the
judgment further held that if the parties are compelled to take
objection to the jurisdiction or the existence of an arbitration
agreement before the arbitral tribunal, the parties have to
participate in the arbitration proceedings extending over a period of
time by incurring substantial expenditure and then come to the
Court with an application under Section 34 of the Act seeking the
setting aside of the award on the ground that there was no
arbitration agreement or that there was nothing to be arbitrated
upon when the tribunal was constituted. It was held that the same
meant considerable expenditure and time spent by the party before
the arbitral tribunal. It was held that on the contrary if the decision
on the aforesaid aspect is taken when the court is approached for
appointment of an arbitrator, this will put to an end a host of
disputes between the parties and leave the arbitral tribunal to decide
the disputes on merits unhampered by preliminary and technical
objections. This option was considered by the Constitution Bench to
be more conducive in matter coming under the Act.
15. The third contention of the respondent in the present case is in
fact on the merits of the dispute. It is the case of the respondent
that the claim raised is not tenable under the agreement inasmuch
as the claim is based on HCL published list of copper prices whereas
under the agreement the price was to be determined as per the
respondent published copper price. Whether the court when
approached under Section 11(6) is entitled to consider this aspect
also? The same would necessarily entail interpretation of the
contract. But so would determination of whether the disputes are
arbitrable or not or fall in excepted matter or not and which, the
Constitution Bench of the Apex Court as aforesaid held was to be
determined at this stage only.
16. Though the scope of inquiry in both the situations may not be
different but it cannot be lost sight of that while one is a plea of the
very arbitrablilty of the disputes, the other is the plea of tenability of
the claim. In the light of the prohibition contained in Section 5 of the
Act, even though present may be of a very clear case where
admittedly the claim is contrary to the written words of the
agreement, this court hesitates from expanding the scope of
intervention of the court to also consider where the claim is tenable
on merits or not. If same were to be permitted, it would open the
flood gates to pleas in this regard and litigants, may be with a view
to delay the disposal of the application would make all sorts of
pleadings to urge that the claim was not in terms of the agreement
or is a sham and fictitious.
17. Having held so, I may, however, observe that since I have on
the first contention of the petitioner found the petition to be without
cause of action, the finding on the second and third contention
aforesaid of the respondent, would not constitute res judicata in a
subsequent petition/application if any under Section 11(6) of the Act,
in the event of the CMD of the respondent failing to act in spite of
being approached by the petitioner. However, since the contention
had been raised and it is a requirement of law that notwithstanding
the matter being found to be not maintainable on one ground alone,
finding on all the grounds urged has to be returned so that the
parties are not compelled to successive rounds of litigations, these
findings would be relevant if either of the parties dissatisfied with
this order takes the matter further.
18. For the reasons aforesaid, the application is rejected accepting
the contention No. 1 of the respondent. However, in the facts of the
case, the parties are left to bear their own costs.
RAJIV SAHAI ENDLAW (JUDGE) January 14, 2009 rb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!