Citation : 2009 Latest Caselaw 207 Del
Judgement Date : 21 January, 2009
* HIGH COURT OF DELHI : NEW DELHI
+ Writ Petition (Civil) No.17348 of 2006
Judgment reserved on: January 13, 2009
% Judgment delivered on: January 21, 2009
M/s Suncity Projects Pvt. Ltd.
(A company incorporated under
the Companies Act, 1956)
Having its Registered Officer at:
N-49, First Floor, Connaught Place
New Delhi-110001.
Through its Director Sh. Laxmi Narain Goel. ...Petitioner
Through Mr.Arun Jaitley, Sr. Advocate with
Mr.Dinesh Kumar Gupta, Adv.
Versus
1. Government of N.C.T. of Delhi
Through: General Manager
Transport Department
I.S.B.T., Kashmiri Gate
Delhi-110006.
2. RITES Ltd.
Through its General Manager
New Delhi House, 27
Barakhamba Road
New Delhi-110001. ...Respondents
Through Mr.Rakesh Tiku with Ms.Aruna
Tiku, Advs. for Resp. 1
Ms.Sadhana Sharma, Adv. for Resp.2
Coram:
HON'BLE MR. JUSTICE MADAN B. LOKUR
HON'BLE MR. JUSTICE SIDDHARTH MRIDUL
WP (C) No.17348/2006 Page 1 of 15
1. Whether the Reporters of local papers may
be allowed to see the judgment? Yes
2. To be referred to Reporter or not? Yes
3. Whether the judgment should be reported
in the Digest? Yes
MADAN B. LOKUR, J.
The question that arises for consideration is whether the
cancellation of the tender process initiated by Respondent No.1 was
mala fide and at the behest of Respondent No.2 (RITES Ltd.). In our
opinion, the circumstances justified the cancellation of the tender
process and no mala fides can be attributed to the cancellation.
2. Respondent No.1 decided to construct, operate and maintain
an Interstate Bus Terminal (ISBT) at Dwarka. It was decided that the
construction, operation and maintenance would be on a Build, Operate
and Transfer (BOT) basis. Respondent No.1 engaged RITES Ltd. as a
Project Development Consultant.
3. On or about 10th November, 2004 Respondent No.1 issued a
request for qualification as the first part of a bidding process. The
second part consisted of an invitation of request for proposal from pre-
qualified parties for submission of their technical and financial bids.
4. There is no dispute about the fact that the Petitioner was
technically qualified and was the highest bidder. The estimated cost of
the project was given by the Petitioner as Rs.25.87 crores and this
included Rs.6.6 crores as its profit component.
5. After the Petitioner gave confirmation of its bid (which was
some time in August, 2005), it was required by Respondent No.1 to
extend the validity of the bid security submitted in the form of a bank
guarantee and also the fixed deposit. It appears that the Petitioner was
required to continue the extension from time to time until it received a
letter dated 21st September, 2006 from RITES Ltd. simply stating that
the Transport Department of the Government of National Capital
Territory of Delhi had cancelled the tender for the development of ISBT,
Dwarka on BOT basis.
6. The Petitioner was obviously shocked and anguished at the
sudden turn of the events and, therefore, filed the present writ petition
under Article 226 of the Constitution for an appropriate direction for
quashing the communication dated 21 st September, 2006 and a direction
to Respondent No.1 to award the work to the Petitioner in terms of the
bid already submitted.
7. During the pendency of the writ petition, Respondent No.1
invited fresh tenders on 5th May, 2008. By an interim order passed by
this Court, it was made clear that the Petitioner would be entitled to
participate in the bidding process without prejudice to its rights and
contentions raised in the writ petition. It was also directed that the bids
now received shall not be finalized.
8. It appears that the Petitioner had some apprehension that
RITES Ltd. would also be participating in the second tender but it was
made clear by learned counsel appearing for RITES Ltd. on 22nd May,
2008 that his client would not be participating in the tender dated 5 th
May, 2008.
9. Respondent No.1 has filed a counter affidavit justifying the
decision taken by it. It is stated that there was a change of
circumstances in as much as the new Master Plan for Delhi and
Development Control Norms for ISBTs have been changed by the Delhi
Development Authority. Earlier, the ground coverage was 3% and it has
now been raised to 25%. Earlier, the floor area ratio (FAR) was 7 and it
has now been raised to 100. A provision has also been made for
hotel/passenger accommodation at ISBTs. According to Respondent
No.1, there is significant potential for better commercial utilization of
the ISBT plots which will be a source of maximum revenue generation.
Accordingly, it was decided in the public interest that the bid of the
Petitioner be cancelled and fresh tenders invited to generate maximum
revenue from the project.
10. Learned counsel for the Petitioner submitted that the Tender
Committee dealing with the original tender had come to the conclusion
that the revenue estimates in terms of the offer made by the Petitioner
appeared to be high and that the offer given by the Petitioner ought to be
accepted. It was also submitted that the original tender was cancelled at
the behest of RITES Ltd., as is evident from a letter dated 30 th August,
2006 issued by RITES Ltd. to the Transport Department of the
Government of National Capital Territory of Delhi. The letter dated 30th
August, 2008 reads as follows: -
"No. RITES/UT/445/2006 Dated: 30.08.2006
The Transport Commissioner GNCTD 5/9, Under Hill Road, Delhi-110054.
(Kind Attention: Dr. V.S. Madan, IAS)
Subject: Development of ISBT at Dwarka on BOT basis.
Ref.: GNCTD/Transport Department letter No. F2(8)AE(p)04-05/TCD/ISBT/Pt.516/525 dated 11.8.2006
Dear Sir,
1.0 During the meeting held between RITES and representatives of Transport Department on 18.8.2006 it was brought out by you that recently DDA has in principle, agreed to new development control norms for ISBTs. The new norms allow for greater utilization of space for permitted commercial activities at ISBTs. Therefore, there was need to have a fresh look on the offer under consideration for award of Concession Agreement to the preferred bidder. Recommendations of RITES for further on date by you with MD/RITES and the undersigned and RITES recommendations for further action on the offer have been sought.
2.0 With the new development control norms there is significant potential for better commercial utilization of the plot. Accordingly it is proposed that fresh bids be invited for development of the ISBT. However we feel that this should be done only after the norms have been notified by the DDA.
3.0 Thanking you and assuring you of our best
attention always.
Yours faithfully,
Sd/-
(A.K. Arora)
Group General Manager (UT)
Copy to: Shri Krishna Kumar, GM, ISBT, Kashmere Gate, Delhi."
11. According to learned counsel for the Petitioner, the actual
reason why RITES Ltd. recommended cancellation was that it was
intending to make a bid in the re-tendering process. It was submitted
that this is clear from the fact that Respondent No.1 had once again
given an offer to RITES Ltd. for the project development consultancy
but this offer was turned down since RITES Ltd. had admitted that it
was contemplating to bid for the transport infrastructure project. For
this, learned counsel for the Petitioner has drawn our attention to a letter
dated 9th May, 2007 issued by RITES Ltd. to the Transport Department.
The letter dated 9th May, 2007 reads as follows: -
"No. RITES/UT/445/2005 Dt.: 09.05.2007
The General Manager Govt. of National Capital Territory of Delhi
Transport Department ISBT Kashmere Gate Delhi.
(Kind Attn. Shri Krishan Kumar)
Subject: Development of Dwarka & Narela ISBT on BOT basis.
Ref.: Your letter No. F2(8)AE(P)04-05/TCD/ISBT/ TPT/92 dated 03.05.2007 Dear Sir,
We thank you for your above referred letter asking us to submit a fresh Proposal for Project Development Consultancy for the subject work.
In this connection it is mentioned that we in RITES are contemplating to bid for transport infrastructure projects to be implemented through BOT/PPP route. Our association with the subject project as PDC will prohibit us from bidding for this project as BOT operator at a later date. You are, therefore, requested to make alternative arrangements for availing consultancy services.
Thanking you and assuring you of our best attention always.
Yours faithfully,
Sd/-
(A.K. Arora) Executive Director (UI)"
12. On these broad facts, the submissions made by learned
counsel for the Petitioner were three-fold. It was firstly submitted that
the Petitioner was admittedly the highest bidder as far back as in
August, 2005 and its bid was kept pending for more than a year for
some inexplicable reason. Though changes in the Master Plan were, in
fact, made in 2007 but surely that could not have been the real reason
for not awarding the contract to the Petitioner for such a long period of
time. In this context, it was submitted that even if Respondent No.1 was
aware of the proposal to amend the Master Plan, the increase in the
ground coverage and FAR could have been taken care of by making pro-
rata adjustments and asking the Petitioner to suitably increase the bid
amount.
Secondly, the entire exercise of re-tendering was mala fide in
as much as RITES Ltd. was itself interested in the contract and this is
clear from the fact that it refused the project consultancy at the stage of
re-tendering on the ground that it was contemplating making a bid for
the contract. Since the actions of RITES Ltd. were mala fide, they
naturally coloured the understanding of Respondent No.1 leading to an
avoidable cancellation of the tender.
Finally, it was submitted that there was no valid reason in
law for Respondent No.1 to have cancelled the tender. While it is true
that Respondent No.1 is entitled to generate the maximum revenue, it
must take other factors into consideration, such as the possibility of
awarding the contract to the highest bidder through negotiations.
13. We are not impressed with any of the submissions made by
learned counsel for the Petitioner. It is true (and unfortunate) that
Respondent No.1 kept the tender of the Petitioner pending for about a
year or so. It appears to us that Respondent No.1 was aware that
changes in the Master Plan were in the offing and that that would have a
major impact on the generation of revenue from the contract. This is
clear from the fact that in the letter dated 30 th August, 2006 issued by
RITES Ltd. to the Transport Department of the Government of National
Capital Territory of Delhi it was specifically mentioned that in a
meeting held on 18th August, 2006 it was brought out that the Delhi
Development Authority had, in principle, agreed to new Development
Control Norms for ISBTs. These new norms allowed for greater
utilization of space for commercial activities. It is clear, therefore, that
sometime in August, 2006, if not earlier, Respondent No.1 was aware
that there would be a change in the Development Control Norms which
would have a major financial impact. There is nothing on record to
suggest when actually Respondent No.1 came to know that the Master
Plan was likely to be changed or amended but assuming that it came to
know about this only in August, 2006 it took more or less immediate
steps by making the Petitioner know in September, 2006 that the tender
was cancelled. It is not clear what transpired between August, 2005 and
August, 2006 but learned counsel for the Petitioner has not made any
grievance in this regard. The time lag is unfortunate but it does seem
that Respondent No.1acted soon after it came to know of the changes.
14. That substantial changes were made to the Master Plan in
2007 is not in dispute. According to learned counsel for the Petitioner,
these changes could have been taken into consideration and the
Petitioner asked to make pro-rata adjustments in its bid. Of course, this
was a possibility that was available to Respondent No.1. But another
option available was to go in for a fresh tender which might have
attracted wider and greater participation due to the sweeping changes
brought about in the Master Plan which increased the ground coverage
from 3% to 25% and FAR from 7 to 100. Which was the better option
to adopt is not really for the courts to decide and Respondent No.1 must
be given adequate leeway in taking a decision in this regard. The
Supreme Court has time and again observed that if the Court prefers one
option to another, it does not mean that the less preferred option taken
by the administrative authority is incorrect. Some latitude must be given
to the administrative authority in the decision making process and the
courts should restrain themselves from exercising the power of judicial
review unless necessary. (See for example Tata Cellular v. Union of
India, (1994) 6 SCC 651)
15. It is true that the decision taken by Respondent No.1 should
not be arbitrary or should not be colourable. But what we find in the
present case is that the decision not to go in pro-rata adjustments was
not an irrational decision but it was a decision taken after considering
the revenue implications as a result of the changes in the Master Plan.
The tender was essentially a commercial venture on the part of
Respondent No.1 and it took a commercial decision which cannot be
said to be either unreasonable or irrational so as to warrant interference
under Article 226 of the Constitution. We, therefore, reject the first
submission made by learned counsel for the Petitioner.
16. In so far as the involvement of RITES Ltd. as a consultant to
Respondent No.1 is concerned, it is true that it was involved in a project
development consultancy at an earlier stage. It does appear that RITES
Ltd. did intend to bid when fresh tenders were sought to be called but
better sense prevailed and it was decided that it would not participate in
the fresh tender. This is what one could have expected from RITES Ltd.
which had access to "insider" information in so far as the ISBT project
was concerned. But this does not lead to the conclusion that the original
tender was cancelled at the behest of RITES Ltd.. As we have noticed
above, relevant and germane factors were taken into consideration by
Respondent No.1 for cancelling the tender and it is on that basis that it
had acted. Even otherwise, RITES Ltd. was only a consultant to the
project and its opinion was not binding upon Respondent No.1, which
could have always rejected the recommendation to cancel the tender, if
circumstances so warranted. It cannot be said with any degree of
certainty on the material before us that the cancellation of the original
tender was entirely at the behest of RITES Ltd. or was motivated by the
desire of RITES Ltd. to participate in the re-tender. We do not find any
substance in the second contention urged by learned counsel for the
Petitioner.
17. There is no doubt that in law Respondent No.1 has the power
to cancel the tender and indeed this was not even questioned by learned
counsel for the Petitioner. However, that power cannot be exercised
arbitrarily or contrary to the provisions of Article 14 of the Constitution.
If the discretionary power is so exercised, the courts can always step in
by way of judicial review and remedy the situation. This has been so
held by the Supreme Court in Master Marine Services (P) Ltd. v.
Metcalfe & Hodgkinson (P) Ltd. and another, (2005) 6 SCC 138.
18. In so far as the present case is concerned, we have come to
the conclusion that there were good reasons for Respondent No.1 to
cancel the tender and one of the major (and relevant) factors that
influenced Respondent No.1 was the fact that a significant change had
been made in the Master Plan specifically with regard to ISBTs. That
change would have had a considerable impact on the amount of revenue
that could have been generated by Respondent No.1 as well as greater
participation in the project from some other builders and contractors.
Apart from the change in ground coverage and FAR, the Master Plan
now permitted the construction of hotels and passenger accommodation
which was not permissible in the earlier Master Plan. In fact, we have
been informed that earlier hotel and passenger accommodation were not
even permissible at the ISBTs. We have also been informed by learned
counsel for Respondent No.1 that there has been an encouraging
response to the re-tendering process and participation has gone up
manifold. In our opinion, Respondent No.1 could have, in law,
cancelled the tender on the basis of the material before it, which it did,
and no fault can be found with the decision taken.
19. We find no merit in the writ petition. It is accordingly
dismissed with costs of Rs.20,000/-. The Petitioner will deposit this
amount in the Registry of this Court by way of a demand draft drawn in
favour of the Registrar General within four weeks from today.
20. List for compliance on 26th February, 2009.
MADAN B. LOKUR, J
January 21, 2009 SIDDHARTH MRIDUL, J
kapil
Certified that the corrected copy of the judgment has been transmitted in the main Server.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!